Scheduled Construction Lane Closures

Impact Key
Minimal
Traffic moving
Minor
Delays up to 5 min.
Moderate
Delays 5-20 min.
Severe
Delays >= 20 min.

Erie Region


For The Week Starting Monday 10/13/2025
Erie Region

Mainline I-90
Between Exits Work Description Lane Closure Information Likely Impacts Comments
55 & 57A  Highway Construction  West: Alternating right lane with the left lane,
Sunday 10/12/25 7:00pm-6:00am Monday 10/13/25. Monday 10/13/25 7:00pm-6:00am Tuesday 10/14/25.

 
Minimal  None 
57 & 57A  Bridge Work  West: Left lane,
Saturday 10/4/25 7:00am-2:00pm.

 
Minimal  None 
57A & 59  Road Work  West: Left lane,
Monday 10/6/25 7:00am-2:00pm.

 
Minimal  None 
59 & 58  Bridge Inspection  West: Right lane,
Tuesday 10/14/25 7:00am-10:00am. Wednesday 10/15/25 7:00am-10:00am.

East: Left lane,
Tuesday 10/14/25 10:00am-2:00pm. Wednesday 10/15/25 10:00am-2:00pm.

 
Minimal  None 
60 & 59  Bridge Inspection  East: Right lane,
Thursday 9/18/25 7:00am-2:00pm.

 
Minimal  None 
61 & 60  Bridge Inspection  West: Alternating right lane with the left lane,
Thursday 9/18/25 10:00am-2:00pm.

East: Alternating right lane with the left lane,
Thursday 9/18/25 7:00am-10:00am.

 
Minimal  None 


For The Week Starting Monday 10/20/2025
Erie Region

Mainline I-90
Between Exits Work Description Lane Closure Information Likely Impacts Comments
57A & 57  Bridge Inspection  West: Right lane,
Monday 10/20/25 11:00am-12:00pm.

West: Left lane,
Monday 10/20/25 12:00pm-1:00pm.

East: Left lane,
Monday 10/20/25 10:00am-11:00am.

East: Right lane,
Monday 10/20/25 7:00am-10:00am.

 
Minimal  None 
57A & 59  Road Work  West: Left lane,
Monday 10/6/25 7:00am-2:00pm.

 
Minimal  None 
59 & 58  Bridge Inspection  West: Left lane,
Wednesday 10/22/25 10:00am-11:00am.

West: Right lane,
Wednesday 10/22/25 7:00am-10:00am.

East: Left lane,
Wednesday 10/22/25 12:00pm-1:00pm.

East: Right lane,
Wednesday 10/22/25 11:00am-12:00pm.

West: Right lane,
Thursday 10/23/25 7:00am-10:00am.

West: Left lane,
Thursday 10/23/25 10:00am-11:00am.

East: Left lane,
Thursday 10/23/25 12:00pm-1:00pm.

East: Right lane,
Thursday 10/23/25 11:00am-12:00pm.

West: Left lane,
Tuesday 10/21/25 10:00am-11:00am.

West: Right lane,
Monday 10/20/25 7:00am-10:00am.

East: Right lane,
Tuesday 10/21/25 11:00am-12:00pm.

West: Left lane,
Friday 10/24/25 10:00am-11:00am.

West: Right lane,
Friday 10/24/25 7:00am-10:00am.

East: Left lane,
Tuesday 10/21/25 12:00pm-1:00pm.

East: Right lane,
Friday 10/24/25 11:00am-12:00pm.

East: Left lane,
Friday 10/24/25 12:00pm-1:00am.

 
Minimal  None 
60 & 59  Bridge Inspection  East: Right lane,
Thursday 9/18/25 7:00am-2:00pm.

 
Minimal  None 
61 & 60  Bridge Inspection  West: Alternating right lane with the left lane,
Thursday 9/18/25 10:00am-2:00pm.

East: Alternating right lane with the left lane,
Thursday 9/18/25 7:00am-10:00am.

 
Minimal  None 

Back to Top

Buffalo/Niagara Region


For The Week Starting Monday 10/13/2025
Buffalo/Niagara Region

Niagara I-190
Between Exits Work Description Lane Closure Information Likely Impacts Comments
21 & 20  Bridge Construction  South: Right lane,
Monday 10/13/25 10:00pm-6:00am Tuesday 10/14/25. Tuesday 10/14/25 10:00pm-6:00am Wednesday 10/15/25. Wednesday 10/15/25 10:00pm-6:00am Thursday 10/16/25. Thursday 10/16/25 10:00pm-6:00am Friday 10/17/25.

 
Minimal  None 


For The Week Starting Monday 10/20/2025
Buffalo/Niagara Region

Niagara I-190
Between Exits Work Description Lane Closure Information Likely Impacts Comments
20 & 21  Bridge Construction  North: Right lane,
Monday 10/20/25 10:00pm-6:00am Tuesday 10/21/25. Tuesday 10/21/25 10:00pm-6:00am Wednesday 10/22/25. Wednesday 10/22/25 10:00pm-6:00am Thursday 10/23/25. Thursday 10/23/25 10:00pm-6:00am Friday 10/24/25.

 
Minimal  None 

Back to Top

Rochester Region


For The Week Starting Monday 10/13/2025
Rochester Region

Mainline I-90
Between Exits Work Description Lane Closure Information Likely Impacts Comments
43 & 46  Paving  West: Left lane,
SUN-SAT CONTINUOUS

 
Moderate  None 
45 & 43  Paving  East: Right lane,
CONTINUOUS SUN-SAT

 
Moderate  None 
45 & 44  Paving  East: Right lane,
MON-SAT Continuous

East: Alternating right lane with the left lane,
MON-WED 8PM-7AM, THU 8PM-6AM

 
Moderate  None 
46 & 44  Paving  East: Left lane,
MON-WED 8PM-6AM, THU-FRI 9PM-6AM

 
Moderate  None 
46 & 45  Other  West: Right lane,
Wednesday 10/8/25 7:00am-4:00pm. Thursday 10/9/25 7:00am-4:00pm.

East: Right lane,
Monday 10/6/25 7:00am-4:00pm. Tuesday 10/7/25 7:00am-4:00pm.

 
Minimal  None 
45 & 46  Shoulder Work  East: Left lane,
Friday 10/17/25 2:00am-11:00am.

West: Left lane,
Tuesday 10/14/25 4:00am-2:00pm.

 
Minimal  None 
45 & 47  Shoulder Work  West: Left lane,
Wednesday 10/15/25 4:00am-2:00pm.

 
Minimal  None 
46 & 45  Shoulder Work  West: Right lane,
Friday 10/17/25 2:00am-11:00am.

East: Left lane,
Friday 10/17/25 2:00am-11:00am.

 
Minimal  None 
46 & 47  Shoulder Work  West: Right lane,
Friday 10/17/25 2:00am-11:00am.

 
Minimal  None 
47 & 45  Shoulder Work  East: Right lane,
Tuesday 10/14/25 6:00pm-2:00pm.

 
Minimal  None 
46 & 47  Shoulder Work  West: Right lane,
Wednesday 10/15/25 6:00pm-2:00pm.

 
Minimal  None 
46 & 47  Road Work  West: Shoulder,
Monday 9/29/25 6:00am-6:00pm. Tuesday 9/30/25 6:00am-6:00pm.

 
Minimal  None 
47 & 46  Shoulder Work  East: Left lane,
Friday 10/17/25 2:00am-11:00am.

West: Left lane,
Thursday 10/15/25 4:00am-2:00pm.

West: Right lane,
Friday 10/17/25 2:00am-11:00am.

East: Left lane,
Friday 10/17/25 2:00am-11:00am.

East: Right lane,
Thursday 10/16/25 6:00pm-2:00pm.

 
Minimal  None 
47 & 48  Road Work  West: Shoulder,
Tuesday 10/7/25 7:00am-4:00pm. Wednesday 10/8/25 7:00am-4:00pm. Thursday 10/9/25 7:00am-4:00pm.

 
Minimal  None 
48A & 48  Road Work  East: Shoulder,
Tuesday 10/7/25 7:00am-4:00pm. Wednesday 10/8/25 7:00am-4:00pm. Thursday 10/9/25 7:00am-4:00pm.

 
Minimal  None 
49 & 48A  Road Work  East: Shoulder,
Tuesday 10/7/25 7:00am-4:00pm. Wednesday 10/8/25 7:00am-4:00pm. Thursday 10/9/25 7:00am-4:00pm.

 
Minimal  None 


For The Week Starting Monday 10/20/2025
Rochester Region

Mainline I-90
Between Exits Work Description Lane Closure Information Likely Impacts Comments
44 & 43  Road Work  West: Left lane,
FRI 3AM-7AM

West: Right lane,
WED-THU 3AM-7AM

East: Left lane,
FRI 3AM-7AM

East: Right lane,
WED 3AM-7AM

 
Minimal  Weather permitting 
44 & 41  Road Work  East: Alternating right lane with the left lane,
THU 6PM-8AM, FRI 8PM-9AM

 
Minimal  Mobile Closure 
43 & 46  Paving  West: Left lane,
SUN-SAT CONTINUOUS

 
Moderate  None 
45 & 43  Paving  East: Right lane,
CONTINUOUS SUN-SAT

 
Moderate  None 
45 & 44  Paving  West: Center lane,
MON-WED 8PM-6AM, THU-FRI 9PM-6AM

East: Right lane,
MON-SAT Continuous

East: Alternating right lane with the left lane,
MON-WED 8PM-7AM, THU-SAT 9PM-6AM

 
Moderate  None 
46 & 44  Paving  East: Left lane,
SUN-SAT Continuous

 
Moderate  None 
46 & 15  Shoulder Work  East: Right lane,
Wednesday 10/22/25 4:00am-2:00pm.

 
Minimal  None 
47 & 45  Other  West: Alternating right lane with the left lane,
Thursday 10/23/25 7:30am-1:00pm.

East: Alternating right lane with the left lane,
Thursday 10/23/25 7:30am-1:00pm.

 
Minimal  None 
47 & 45  Shoulder Work  East: Right lane,
Tuesday 10/21/25 4:00am-2:00pm.

 
Minimal  None 
46 & 47  Shoulder Work  West: Left shoulder,
Friday 10/24/25 2:00am-11:00am.

East: Right lane,
Monday 10/20/25 2:00am-11:00am.

West: Left shoulder,
Thursday 10/23/25 4:00am-2:00pm.

 
Minimal  None 

Back to Top

Syracuse Region


For The Week Starting Monday 10/13/2025
Syracuse Region

Mainline I-90
Between Exits Work Description Lane Closure Information Likely Impacts Comments
33 & 34  Shoulder Work  West: Shoulder,
THU 7AM-5PM

 
Minimal  None 
34 & 33  Road Work  West: Right lane,
TUE-WED 6AM-1PM

East: Left lane,
THU-FRI 7:30AM-2PM

 
Minimal  Weather permitting 
34 & 35  Bridge Construction
Long Range: Bridge Construction I-481 
West: Alternating right lane with the left lane,
MON 4AM-2PM, TUE-THU 4AM-3PM, FRI 4AM-1PM, SAT 4AM-11AM

 
Minimal  Set up as needed 
35 & 34  Bridge Work  East: Alternating right lane with the left lane,
WED 5AM-2PM, THU 5AM-3PM, FRI 5AM-10AM

 
Minimal  Weather permitting 
35 & 34A  Bridge Construction
Long Range: Bridge Construction I-481 
East: Alternating right lane with the left lane,
MON-TUE 4AM-3PM, WED 4AM-2PM, THU 4AM-3PM, FRI 4AM-10AM, SAT 4AM-4PM

 
Minimal  Set up as needed 
34A & 36  Bridge Construction  West: Left lane,
WED 7AM-2PM, THU 7AM-3PM, FRI-SAT 7AM-2PM

West: Right lane,
TUE Noon-3PM

 
Minimal  None 
36 & 35  Road Work  West: Other,
TUE-THU 7AM-1PM

East: Other,
TUE-THU 7AM-1PM

 
Minimal  Weather permitting 
36 & 35  Bridge Construction  East: Left lane,
TUE noon-3PM, WED 8AM-2PM

East: Right lane,
THU 8AM-3PM, SAT 7AM-3PM

 
Minimal  None 
41 & 40  Road Work  East: Right lane,
WED-THU 7:30AM-1PM

 
Minimal  Weather permitting 
40 & 42  Road Work  West: Alternating right lane with the left lane,
FRI 8PM-9AM

 
Minimal  None 
42 & 40  Road Work  West: Alternating right lane with the left lane,
WED-THU 7:30AM-1PM

East: Alternating right lane with the left lane,
WED-THU 7:30AM-1PM

 
Minimal  Weather permitting 
41 & 42  Road Work  West: Alternating right lane with the left lane,
FRI 3AM-10AM

 
Minimal  Weather permitting 
42 & 40  Road Work  East: Alternating right lane with the left lane,
THU 6PM-8AM

East: Left lane,
TUE 7PM-8AM, WED 7PM-9AM

 
Minimal  None 


For The Week Starting Monday 10/20/2025
Syracuse Region

Mainline I-90
Between Exits Work Description Lane Closure Information Likely Impacts Comments
33 & 34  Road Work  West: Alternating right lane with the left lane,
MON-TUE 7:30AM-noon

 
Minimal  Weather permitting 
33 & 34  Shoulder Work  West: Shoulder,
THU 7AM-5PM

 
Minimal  None 
34 & 33  Road Work  West: Alternating right lane with the left lane,
TUE-WED 7:30AM-10AM

East: Left lane,
TUE-WED 7:30AM-10AM

 
Minimal  Weather permitting 
34 & 35  Bridge Work  West: Alternating right lane with the left lane,
MON-FRI 4AM-7AM

 
Minimal  None 
34 & 35  Bridge Construction
Long Range: Bridge Construction I-481 
West: Alternating right lane with the left lane,
MON 4AM-2PM, TUE-THU 4AM-3PM, FRI 4AM-1PM, SAT 4AM-11AM

 
Minimal  Set up as needed 
35 & 34  Bridge Work  East: Alternating right lane with the left lane,
MON-THU 5AM-3PM, FRI 5AM-10AM

 
Minimal  None 
35 & 34A  Bridge Construction
Long Range: Bridge Construction I-481 
East: Alternating right lane with the left lane,
MON-TUE 4AM-3PM, WED 4AM-2PM, THU 4AM-3PM, FRI 4AM-10AM, SAT 4AM-4PM

 
Minimal  Set up as needed 
34A & 36  Bridge Construction  West: Right lane,
MON-TUE 7AM-3PM

West: Left lane,
THU 7AM-3PM, FRI 7AM-2PM

 
Minimal  None 
35 & 37  Road Work  West: Right lane,
TUE-WED 7AM-2PM

 
Minimal  Weather permitting 
36 & 35  Bridge Construction  East: Left lane,
TUE 8AM-1PM, WED 8AM-2PM

East: Right lane,
THU 8AM-1PM

 
Minimal  None 
36 & 38  Road Work  West: Right lane,
THU 7AM-1PM

 
Minimal  Weather permitting 
42 & 40  Road Work  West: Alternating right lane with the left lane,
TUE 7PM-8AM, WED 7PM-9AM

East: Alternating right lane with the left lane,
MON 7PM-8AM, WED 7PM-9AM

 
Minimal  Mobile Closure 
44 & 41  Road Work  East: Alternating right lane with the left lane,
THU 6PM-8AM, FRI 8PM-9AM

 
Minimal  Mobile Closure 

Back to Top

Utica Region


For The Week Starting Monday 10/13/2025
Utica Region

Mainline I-90
Between Exits Work Description Lane Closure Information Likely Impacts Comments
27 & 28  Other  West: Alternating right shoulder or left shoulder,
Tuesday, 7:00AM - 5:00PM

West: Alternating right shoulder or left shoulder,
Tuesday, 7:00AM - 5:00PM

West: Alternating right shoulder or left shoulder,
Tuesday, 7:00AM - 5:00PM

 
Minimal  Weather Permitting 
27 & 28  Bridge Construction  West: Other,
WB traffic shifted to EB side of bridge until further notice.

 
Minimal  Weather Permitting 
27 & 28  Other  West: Alternating right shoulder or left shoulder,
Tuesday, 7:00AM - 5:00PM

 
Minimal  Weather Permitting 
28 & 29  Bridge Work  West: Right lane,
Tuesday - Friday, 7:00AM - 2:00PM

 
Minimal  Weather Permitting 
29A & 29  Guide Rail Installation  East: Left lane,
WED 6AM-5PM

 
Minor  None 
29A & 29  Road Work  West: Alternating right lane with the left lane,
THU 7AM-2PM, FRI 7AM-11AM

East: Alternating right lane with the left lane,
THU 7AM-2PM, FRI 7AM-1AM

 
Minimal  Weather permitting 
29 & 29A  Guide Rail Installation  West: Left lane,
THU 6AM-5PM, FRI 6AM-2PM

 
Minor  None 
29A & 29  Road Work  West: Alternating right lane with the left lane,
MON noon-2PM, TUE-THU 7AM-2PM

West: Right lane,
TUE-THU 7AM-2PM

West: Right lane,
MON 7AM-2PM

East: Right lane,
WED 7AM-2PM

East: Alternating right lane with the left lane,
MON noon-2PM, TUE-THU 7AM-2PM

 
Minimal  Weather permitting 
29A & 29  Guide Rail Installation  East: Left lane,
THU 6AM-5PM, FRI 6AM-2PM

 
Minor  None 
31 & 29A  Bridge Construction  East: Right lane,
THU 7AM-5PM

 
None  None 
30 & 31  Road Work  East: Left lane,
WED-THU 7AM-2PM

East: Right lane,
MON noon-2PM, TUE 7AM-2PM

West: Right lane,
FRI 7AM-11AM

 
Minimal  Weather permitting 
31 & 30  Bridge Construction  East: Right lane,
TUE-THU 7AM-5PM, FRI 7AM-2PM

 
Minimal  None 
31 & 32  Shoulder Work  West: Shoulder,
WED 7AM-5PM

 
Minimal  None 
31 & 32  Bridge Deck Rehabilitation  West: Right lane,
MON-SUN Continuous - WB ramp closed over N. Genesee. Detour in place. EB traffic shifted to rehabbed EB lane for stage 3

 
Minimal  None 
32 & 31  Road Work  East: Alternating right lane with the left lane,
FRI 7:30AM-10AM

 
Minimal  Weather permitting 
32 & 31  Bridge Construction  West: Alternating right lane with the left lane,
WED 6AM-7PM

East: Alternating right lane with the left lane,
WED 6AM-7PM

 
None  None 
33 & 34  Shoulder Work  West: Shoulder,
THU 7AM-5PM

 
Minimal  None 
34 & 33  Road Work  West: Right lane,
TUE-WED 6AM-1PM

East: Left lane,
THU-FRI 7:30AM-2PM

 
Minimal  Weather permitting 


For The Week Starting Monday 10/20/2025
Utica Region

Mainline I-90
Between Exits Work Description Lane Closure Information Likely Impacts Comments
27 & 28  Bridge Construction  West: Other,
WB traffic shifted to EB side of bridge until further notice.

 
Minimal  Weather Permitting 
29 & 29A  Guide Rail Installation  West: Left lane,
WED-THU 6AM-5PM

West: Right lane,
WED-THU 6AM-5PM

East: Right lane,
WED-THU 6AM-5PM

West: Left lane,
MON-THU 6AM-5PM

 
Minor  None 
29A & 29  Road Work  East: Right lane,
THU 7AM-2PM

 
Minimal  Weather permitting 
29A & 29  Guide Rail Installation  East: Left lane,
MON-WED 6AM-5PM

 
Minor  None 
29 & 30  Road Work  West: Left lane,
THU 7AM-2PM

 
Minimal  Weather permitting 
30 & 29A  Road Work  East: Right lane,
WED 7AM-2PM

 
Minimal  Weather permitting 
31 & 29A  Bridge Construction  East: Right lane,
TUE 7AM-5PM

 
Minimal  None 
31 & 30  Road Work  East: Right lane,
MON-TUE 7AM-2PM

 
Minimal  Weather permitting 
31 & 30  Bridge Construction  East: Right lane,
TUE-THU 7AM-5PM, FRI 7AM-2PM

 
Minimal  None 
31 & 32  Shoulder Work  West: Shoulder,
MON-WED 7AM-5PM

 
Minimal  None 
31 & 32  Bridge Deck Rehabilitation  West: Right lane,
MON-SUN Continuous - WB ramp closed over N. Genesee. Detour in place. EB traffic shifted to rehabbed EB lane for stage 3

 
Minimal  None 
32 & 31  Bridge Construction  West: Alternating right lane with the left lane,
WED 6AM-7PM

East: Alternating right lane with the left lane,
WED 6AM-7PM

 
None  None 
33 & 32  Road Work  East: Alternating right lane with the left lane,
FRI 7:30AM-10AM

 
Minimal  Weather permitting 
33 & 34  Road Work  West: Alternating right lane with the left lane,
MON-TUE 7:30AM-noon

 
Minimal  Weather permitting 
33 & 34  Shoulder Work  West: Shoulder,
THU 7AM-5PM

 
Minimal  None 
34 & 33  Road Work  West: Alternating right lane with the left lane,
TUE-WED 7:30AM-10AM

East: Left lane,
TUE-WED 7:30AM-10AM

 
Minimal  Weather permitting 

Back to Top

Albany Region


For The Week Starting Monday 10/13/2025
Albany Region

Berkshire I-90
Between Exits Work Description Lane Closure Information Likely Impacts Comments
B1 & 21A  Bridge Construction  East: Other,
Monday - Sunday, 12:00 MIDNIGHT - 12:00 Midnight *24-Hour Closure* EB traffic shifted to WB side of bridge until further notice.

West: Left lane,
Monday - Sunday, 12:00 Midnight - 12:00 Midnight *24-Hour Closure* EB traffic shifted to WB side of bridge until further notice.

 
Minimal  Weather Permitting 
B2 & B3  Other  East: Right lane,
Tuesday - Thursday, 7:00AM - 7:00AM *24 Hour Closure*; Friday, 7:00AM - 11:00AM

 
Minimal  Weather Permitting 

Mainline I-90
Between Exits Work Description Lane Closure Information Likely Impacts Comments
Interchange Work  Gantry Work  Direction: Interchange 25: Alternating right lane with the left lane,
Tuesday - Friday, 9:00PM - 2:00PM *Westbound*

Direction: Interchange 25A: Alternating right lane with the left lane,
Tuesday - Friday, 6:00AM - 4:00PM *Westbound*

Direction: Interchange 25: Alternating right lane with the left lane,
Tuesday - Friday, 10:00AM - 3:00PM *Eastbound*

Direction: Interchange 25A: Alternating right lane with the left lane,
Tuesday - Friday, 8:00AM - 5:00PM *Eastbound*

 
None  Weather Permitting 
Interchange Work  Ramp Work  Direction: Interchange 23: Ramp,
Tuesday, 7:00AM - 2:00PM *Mobile Maintenance*

 
Minor  Weather Permitting 

Mainline I-87
Between Exits Work Description Lane Closure Information Likely Impacts Comments
21 & 20  Bridge Inspection  North: Right shoulder,
Wednesday, 9:00AM - 11:00AM

South: Right shoulder,
Wednesday, 11:00AM - 12:00 Noon

North: Right shoulder,
Wednesday, 8:00AM - 9:00AM

South: Right shoulder,
Wednesday, 12:00 Noon - 2:00PM

 
Minimal  Weather Permitting 
20 & 21B  Bridge Inspection  North: Alternating right lane with the left lane,
Thursday, 8:00AM - 12:00 Noon

 
Minimal  Weather Permitting 

Mainline I-90
Between Exits Work Description Lane Closure Information Likely Impacts Comments
25 & 24  Ramp Work  East: Right lane,
Tuesday & Wednesday, 9:30AM - 1:00PM *Mobile Maintenance*

 
Minor  Weather Permitting 
24 & 25  Bridge Work  West: Right lane,
Thursday, 9:00AM - 1:00PM

 
Minor  Weather Permitting 
26 & 27  Other  West: Alternating right shoulder or left shoulder,
Tuesday, 7:00AM - 5:00PM

West: Alternating right shoulder or left shoulder,
Tuesday, 7:00AM - 5:00PM

 
Minimal  Weather Permitting 


For The Week Starting Monday 10/20/2025
Albany Region

Berkshire I-90
Between Exits Work Description Lane Closure Information Likely Impacts Comments
B1 & 21A  Bridge Construction  East: Other,
Monday - Sunday, 12:00 MIDNIGHT - 12:00 Midnight *24-Hour Closure* EB traffic shifted to WB side of bridge until further notice.

West: Left lane,
Monday - Sunday, 12:00 Midnight - 12:00 Midnight *24-Hour Closure* EB traffic shifted to WB side of bridge until further notice.

 
Minimal  Weather Permitting 
B2 & B3  Other  East: Right lane,
Tuesday - Thursday, 7:00AM - 7:00AM *24 Hour Closure*; Friday, 7:00AM - 11:00AM

 
Minimal  Weather Permitting 
B3 & B2  Guide Rail Installation  West: Alternating right lane with the left lane,
Thursday & Friday, 7:00AM - 2:00PM

 
Minimal  Weather Permitting 

Mainline I-90
Between Exits Work Description Lane Closure Information Likely Impacts Comments
Interchange Work  Gantry Work  Direction: Interchange 25: Alternating right lane with the left lane,
Monday - Friday, 10:00AM - 3:00PM *Eastbound*

Direction: Interchange 25: Alternating right lane with the left lane,
Monday - Friday, 9:00PM - 2:00PM *Westbound*

Direction: Interchange 25A: Alternating right lane with the left lane,
Monday - Friday, 6:00AM - 4:00PM *Westbound*

Direction: Interchange 25A: Alternating right lane with the left lane,
Monday - Friday, 8:00AM - 5:00PM *Eastbound*

 
None  Weather Permitting 

Mainline I-87
Between Exits Work Description Lane Closure Information Likely Impacts Comments
21 & 20  Road Work  North: Right lane,
Thursday, 7:00AM - 1:00PM; Friday, 7:00AM - 11:00AM *Mobile Maintenance*

South: Right lane,
Monday & Tuesday, 7:00AM - 2:00PM *Mobile Maintenance*

 
Minimal  Weather Permitting 
21A & 21B  Other  South: Right lane,
Tuesday, 7:00AM - 2:00PM

 
Minimal  Weather Permitting 

Mainline I-90
Between Exits Work Description Lane Closure Information Likely Impacts Comments
25 & 24  Guide Rail Installation  East: Right lane,
Monday & Tuesday, 9:30Am - 1:00PM

 
Minor  Weather Permitting 
25A & 25  Bridge Work  East: Left lane,
Tuesday, 9:00AM - 11:00AM

 
Minor  Weather Permitting 

Back to Top

Mid-Hudson Region


For The Week Starting Monday 10/13/2025
Mid-Hudson Region

Mainline I-87
Between Exits Work Description Lane Closure Information Likely Impacts Comments
17 & 18  Bridge Construction  North: Left lane,
Wed-Thurs 6am-2pm

 
Minor  None 
19 & 18  Bridge Construction  North: Right shoulder,
Tuesday - Friday, 7:00AM - 5:00PM

North: Both lanes,
NB traffic shifted to SB side of bridge until further notice.

South: Alternating right shoulder or left shoulder,
Tuesday - Friday, 7:00AM - 5:00PM

 
Minor  Weather Permitting 
19 & 18  Road Work  South: Alternating right lane with the left lane,
Tuesday - Thursday, 6:00AM - 2:00PM; Friday, 6:00AM - 10:00AM

 
Minimal  Weather Permitting 
19 & 20  Bridge Inspection  North: Alternating right lane with the left lane,
Wednesday, 6:00AM - 2:00PM

 
Minimal  Weather Permitting 
21 & 20  Bridge Inspection  North: Right shoulder,
Wednesday, 9:00AM - 11:00AM

South: Right shoulder,
Wednesday, 11:00AM - 12:00 Noon

North: Right shoulder,
Wednesday, 8:00AM - 9:00AM

South: Right shoulder,
Wednesday, 12:00 Noon - 2:00PM

 
Minimal  Weather Permitting 
20 & 21B  Bridge Inspection  North: Alternating right lane with the left lane,
Thursday, 8:00AM - 12:00 Noon

 
Minimal  Weather Permitting 


For The Week Starting Monday 10/20/2025
Mid-Hudson Region

Mainline I-87
Between Exits Work Description Lane Closure Information Likely Impacts Comments
17 & 18  Bridge Construction  North: Left lane,
Tues-Thurs 8pm-9am

 
Minor  None 
18 & 19  Road Work  North: Alternating right lane with the left lane,
Wednesday, 9:00AM - 11:00AM

 
Minimal  Weather Permitting 
19 & 18  Bridge Construction  North: Right shoulder,
Monday - Friday, 7:00AM - 5:00PM

North: Both lanes,
NB traffic shifted to SB side of bridge until further notice.

South: Alternating right shoulder or left shoulder,
Monday - Friday, 7:00AM - 5:00PM

 
Minor  Weather Permitting 
19 & 18  Road Work  South: Alternating right lane with the left lane,
Tuesday - Thursday, 6:00AM - 2:00PM; Friday, 6:00AM - 11:00AM

 
Minimal  Weather Permitting 
19 & 20  Bridge Inspection  North: Right lane,
Thursday, 6:00AM - 1:00PM

 
Minimal  Weather Permitting 
21 & 20  Road Work  North: Right lane,
Thursday, 7:00AM - 1:00PM; Friday, 7:00AM - 11:00AM *Mobile Maintenance*

South: Right lane,
Monday & Tuesday, 7:00AM - 2:00PM *Mobile Maintenance*

 
Minimal  Weather Permitting 

Back to Top

New York Region


For The Week Starting Monday 10/13/2025
New York Region

Cross Westchester I-287
Between Exits Work Description Lane Closure Information Likely Impacts Comments
6 & 9  Bridge Construction  East: Ramp,
Ramp C, D Sat-Tues 10pm-6am

 
None  None 
9 & 7  Bridge Construction  West: Left and center lanes,
Wed 10pm-6am

 
None  None 
9 & 10  Bridge Construction  East: Right shoulder,
Mon-Thur 8am-3pm Fri 8am-2pm

 
None  None 
10 & 8  Bridge Construction  West: Left and center lanes,
Tue 9pm-6am

 
None  None 
11 & 9A  Bridge Construction  West: Left and center lanes,
Mon 9pm-6am

West: Left and center lanes,
Sun 9pm-6am

 
None  None 
11 & 10  Bridge Construction  West: Right shoulder,
Mon-Thur 8am-3pm Fri 8am-2pm

 
None  None 
12 & 9A  Bridge Construction  West: Left and center lanes,
MP 10.5-7.5 Thurs 7pm-6am

 
None  None 

Mainline I-87
Between Exits Work Description Lane Closure Information Likely Impacts Comments
8 & 9  Bridge Inspection  North: Right 3 lanes,
RL, RAL, RSH Wed 9am-12pm

 
None  None 
10 & 9  Bridge Inspection  South: Right 3 lanes,
RL, RDL, RSH Tues 10am-1pm

South: Left lane,
Tues 1pm-4:30pm

 
None  None 
12 & 13  Bridge Construction  North: Right shoulder,
Tues 9am-12pm Wed-Thurs 9am-2pm Fri 9am-11am

 
None  None 
12 & 14  Bridge Work  North: Left and center lanes,
Tues 8pm-6am Wed-Fri 9pm-6am

North: Left lane,
Tue 8pm-6am Wed-Fri 9pm-6am

 
None  None 
14 & 13  Bridge Work  South: Left lane,
Thurs 8pm-6am Fri 9pm-6am

South: Right lane,
Tues-Thurs 8pm-6am Fri 9pm-6am

South: Alternating right lane with the left lane,
Mon-Tue 8pm-6am Wed-Fri 9pm-6am (Sat)

South: Left and center lanes,
Tues-Thurs 8pm-6am Fri 9pm-6am

 
None  None 
14B & 15  Shoulder Work  North: Alternating right lane with the left lane,
Mon-Wed 6am-1pm Thurs 6am-12pm Fri 6am-10am

North: Right shoulder,
Mon-Fri 6am-3pm

 
None  None 
15A & 14B  Shoulder Work  South: Right shoulder,
Mon-Fri 10am-3pm

 
None  None 
16 & 15A  Bridge Inspection  North: Right shoulder,
Wed 1:30pm-1:45pm

South: Right shoulder,
Wed 2pm-2:15pm

 
Minimal  None 

New England I-95
Between Exits Work Description Lane Closure Information Likely Impacts Comments
8B & 15  Road Work  North: Alternating right shoulder or left shoulder,
Night Tues-Wed 10pm-5:30am Thurs 10pm-5am Fri 10pm-6am Day Tues 10am-3pm Wed-Thurs 9am-3pm Fri 9am-1pm

 
None  None 
14 & 18A  Shoulder Work  North: Alternating right lane with the left lane,
Tues-Thurs 7pm-7am Fri 9pm-8am

North: Center lane,
Mon-Wed 11pm-5:30am Thurs 11pm-5am Fri 12am-6am

North: Right shoulder,
Tues-Fri 9am-3pm

 
None  None 
15 & 8B  Road Work  South: Alternating right shoulder or left shoulder,
Night Tues-Wed 10pm-5:30am Thurs 10pm-5am Fri 10pm-6am Day Tues 10am-3pm Wed-Thurs 9am-3pm Fri 9am-1pm

 
None  None 
18A & 14  Shoulder Work  North: Right shoulder,
Alt RT/LT shoulder closures: Exit 15 NB on-ramp & off-ramp Exit 16 NB on-ramp & off-ramp Exit 17 NB off-ramp River St on-ramp to 95NB Tues-Fri: 6pm-7am

South: Center lane,
Tues-Wed 11pm-5:30am Thurs 11pm-5am Fri 12am-6am

South: Right shoulder,
Alt RT/LT shoulder closures: Exit 15 NB on-ramp & off-ramp Exit 16 NB on-ramp & off-ramp Exit 17 NB off-ramp River St on-ramp to 95NB Tues-Fri 7pm-8am

South: Alternating right lane with the left lane,
Tues-Thurs 8pm-7am Fri 9pm-9am

 
None  None 


For The Week Starting Monday 10/20/2025
New York Region

Cross Westchester I-287
Between Exits Work Description Lane Closure Information Likely Impacts Comments
11 & 8  Bridge Construction  West: Right and center lanes,
Fri 10pm-6am

 
None  None 
10  Bridge Construction  East: Left lane,
Tues-Thurs 7pm-6am

 
None  None 
12 & 9A  Bridge Construction  West: Right and center lanes,
MP 10.8-7.5 Mon 7pm-6am

 
None  None 
11  Bridge Construction  East: Left shoulder,
Tues-Thurs 9am-10pm

 
None  None 
12 & 1  Bridge Construction  West: Left shoulder,
10.5-10.3 Tue-Thurs 6am-4pm

West: Left and center lanes,
Actual MP 10.8-7.5 Sun 9pm-6am Tues 7pm-6am Wed-Thurs 9pm-6am

 
None  None 

Mainline I-87
Between Exits Work Description Lane Closure Information Likely Impacts Comments
12 & 14  Bridge Work  North: Left and center lanes,
Mon-Wed 8pm-6am Thurs-Fri 9pm-6am

North: Left lane,
Mon-Tue 8pm-6am Wed-Fri 9pm-6am

 
None  None 
14 & 13  Bridge Work  South: Right lane,
Mon-Thurs 8pm-6am Fri 9pm-6am

South: Left lane,
Mon-Thurs 8pm-6am Fri 9pm-6am

South: Alternating right lane with the left lane,
Mon-Tue 8pm-6am Wed-Fri 9pm-6am (Sat)

South: Left and center lanes,
Mon-Thurs 8pm-6am Fri 9pm-6am

 
None  None 
14 & 14B  Bridge Inspection  North: Left 2 lanes,
LL, LSH Mon 9am-12pm

 
None  None 
14B & 14A  Bridge Inspection  South: Left 2 lanes,
LL, LSH Tues 11am-2pm

 
None  None 
14B & 15  Shoulder Work  North: Right shoulder,
Mon-Fri 6am-3pm

North: Alternating right lane with the left lane,
Mon-Wed 6am-1pm Thurs-Fri 6am-12pm

 
None  None 
15A & 14B  Shoulder Work  South: Right shoulder,
Mon-Fri 6am-3pm

 
None  None 

Mainline I-90
Between Exits Work Description Lane Closure Information Likely Impacts Comments
46 & 15  Shoulder Work  East: Right lane,
Wednesday 10/22/25 4:00am-2:00pm.

 
Minimal  None 

New England I-95
Between Exits Work Description Lane Closure Information Likely Impacts Comments
8B & 15  Road Work  North: Alternating right shoulder or left shoulder,
Night Mon-Wed 10pm-5:30am Thurs 10pm-5am Fri 10pm-6am Day Mon-Fri 7am-3pm

 
None  None 
14 & 18A  Shoulder Work  North: Alternating right lane with the left lane,
Sun 10pm-7am Mon-Thurs 7pm-7am Fri 9pm-8am

North: Center lane,
Sun 12am-5:30am Mon-Wed 11pm-5:30am Thurs 11pm-5am Fri 12am-6am

North: Right shoulder,
Tues-Fri 9am-3pm

 
None  None 
15 & 8B  Road Work  South: Alternating right shoulder or left shoulder,
Night Mon-Wed 10pm-5:30am Thurs 10pm-5am Fri 10pm-6am Day Mon-Fri 7am-3pm

 
None  None 
14 & 18A  Shoulder Work  North: Ramp,
Mon-Fri 9am-3pm

North: Right shoulder,
Alt RT/LT shoulder closures: Exit 15 NB on-ramp & off-ramp Exit 16 NB on-ramp & off-ramp Exit 17 NB off-ramp River St on-ramp to 95NB Mon-Fri: 6pm-7am

 
None  None 
15 & 16  Bridge Inspection  North: Left lane,
Wed 12pm-2pm

North: Right lane,
Wed 10am-12pm

 
None  None 
17 & 15  Bridge Inspection  South: Left lane,
Thurs 12pm-2pm

South: Right lane,
Thurs 10am-12pm

South: Deceleration lane,
RDL Thurs 10am-12pm

 
None  None 
18A & 14  Shoulder Work  South: Center lane,
Sun 11pm-5:30am Mon-Wed 11pm-5:30am Thurs 11pm-5am Fri 11pm-6am

South: Alternating right lane with the left lane,
Sun 10pm-7am Mon-Thurs 8pm-7am Fri 9pm-9am

South: Ramp,
Mon-Fri 7am-3pm

South: Right shoulder,
Alt RT/LT shoulder closures: Exit 15 NB on-ramp & off-ramp Exit 16 NB on-ramp & off-ramp Exit 17 NB off-ramp River St on-ramp to 95NB Sun 9pm-7am Mon-Fri 7pm-8am

 
None  None 

Back to Top