Project Schedule (Fuel services will remain available during construction at all Service Areas)

Empire State Thruway Partners has proposed two phases of construction. Phase one includes 16 service areas with staged reconstruction scheduled to begin in 2021. Phase two includes 11 service areas with renovations scheduled to begin in January 2023.

  • Phase 1: July 2021-November 2023
    Service Areas: Indian Castle, Junius Ponds, Chittenango, Ardsley, Iroquois, Clarence, Plattekill, Clifton Springs, New Baltimore, Pembroke, Seneca, Oneida, Pattersonville, Sloatsburg, Scottsville, Ulster
  • Phase 2: January 2023-May 2025
    Service Areas: Schuyler, Ontario, Malden, Guilderland, Port Byron, Warners, Ramapo, Angola, Dewitt, Mohawk, Modena
Image here

Service Areas

*Fuel services will remain available during construction at all Service Areas