Service Area Project Locations

Service Area Redesign and Redevelopment Project
Name Location Milepost Projected Opening Date Level Sq. Feet
ArdsleyNorthbound, Exit 6A (Yonkers Toll Gantry) & Exit 7 (Ardsley)6June 8, 20232A14,654
SloatsburgNorthbound, Exit 15A (Suffern Rt. 17N) & Exit 16 (Woodbury Toll Gantry)33Quarter 3 2024331,428
PlattekillNorthbound, Exit 17 (Newburgh I-84) & Exit 18 (New Paltz)65May 3, 2023320,145
MaldenNorthbound, Exit 20 (Saugerties) & Exit 21 (Catskill)103Quarter 4 20242A18,220
New BaltimoreNorthbound & Southbound, Exit 21B (Coxsackie) & Exit 21A (Berkshire Section/to Mass Pike)127June 29, 2023320,145
PattersonvilleWestbound, Exit 26 (Schenectady West) & Exit 27 (Amsterdam)168Quarter 3 20242B16,240
IroquoisWestbound, Exit 29 (Canajoharie) & Exit 29A (Little Falls)210February 14, 20232A14,654
SchuylerWestbound, Exit 30 (Herkimer) & Exit 31 (Utica)227October 30, 202313,896
ChittenangoWestbound, Exit 34 (Canastota) & Exit 34A (Syracuse I-481)266September 12, 202225,742
WarnersWestbound, Exit 39 (Syracuse West) & Exit 40 (Weedsport)292March 25, 20242A14,654
Junius PondsWestbound, Exit 41 (Waterloo) & Exit 42 (Geneva)324October 6, 202225,742
SenecaWestbound, Exit 44 (Canandaigua) & Exit 45 (Rochester I-490)350September 8, 202325,742
OntarioWestbound, Exit 46 (Rochester) & Exit 47 (Leroy)376Quarter 4 20242A18,220
ClarenceWestbound, Exit 48A (Pembroke) & Exit 49 (Depew)412June 28, 20232B14,654
AngolaEastbound & Westbound, Exit 57A (Eden-Angola) & Exit 58 (Silver Creek)447Quarter 1 2025320,145
PembrokeEastbound, Exit 48A (Pembroke) & Exit 48 (Batavia)397July 13, 20233B20,145
ScottsvilleEastbound, Exit 47 (Leroy) & Exit 46 (Rochester)366Quarter 3 202425,742
Clifton SpringsEastbound, Exit 43 (Manchester) & Exit 42 (Geneva)337March 28, 2023320,145
Port ByronEastbound, Exit 41 (Waterloo) & Exit 40 (Weedsport)310February 19, 202425,742
DeWittEastbound, Exit 36 (Syracuse I-81) & Exit 35 (Syracuse East)280Quarter 4 202413,896
OneidaEastbound, Exit 33 (Verona-Rome) & Exit 32 (Westmoreland-Rome)244January 10, 20242A14,654
Indian CastleEastbound, Exit 29A (Little Falls) & Exit 29 (Canajoharie)210August 26, 202225,742
MohawkEastbound, Exit 27 (Amsterdam) & Exit 26 (Schenectady West)172Quarter 1 202525,742
GuilderlandEastbound, Exit 25 (Schenectady East) & Exit 24 (Albany Northway)153Quarter 2 202425,742
UlsterSouthbound, Exit 20 (Saugerties) & Exit 19 (Kingston)96Quarter 4 20242B14,654
ModenaSouthbound, Exit 18 (New Paltz) & Exit 17 (Newburgh I-84)66Quarter 4 2025320,145
RamapoSouthbound, Exit 16 (Woodbury Toll Gantry) & Exit 15A (Suffern Rt. 17N)33Quarter 2 2024320,145

 

Service Areas

*Fuel services will remain available during construction at all Service Areas