Scheduled Construction Lane Closures


For The Week Starting Monday 08/14/2017
New York Region

Cross Westchester I-287
Between Exits Work Description Lane Closure Information Likely Impacts Comments
1 & 2  Bridge Work  East: Alternating right lane with the left lane,
Sun Single Lane at 10PM, double at 11PM Mon-Thurs Single at 9PM, double at 11PM

 
Minimal  None 
6 & 5  Bridge Work  East: Alternating right lane with the left lane,
Sun: Single at 10PM, double at 11PM Mon-Thurs: 9PM; double at 11PM

West: Alternating right lane with the left lane,
Sun-Fri Single lane @ 9PM; double lane @ 11PM

 
Minimal  None 

Mainline I-87
Between Exits Work Description Lane Closure Information Likely Impacts Comments
1 & 5  Bridge Construction  North: Alternating right lane with the left lane,
Mon-Thurs 9AM-2PM Fri 9AM-12PM

 
Minimal  None 
6 & 4  Bridge Construction  South: Left lane,
Mon-Fri 8AM-3PM

 
Minimal  None 
7A & 7  Bridge Construction  South: Left lane,
Mon-Thurs 9AM-5PM

 
Minimal  None 
10 & 9  Road Work  North: Right lane,
Tues-Thurs 9AM-3PM Fri 9AM-1PM

South: Right lane,
Mon 9AM-3PM

 
Minor  None 
12 & 14  Bridge Construction  North: Alternating right lane with the left lane,
Fri 10PM-6AM

 
Minimal  None 
14 & 13  Bridge Construction  South: Alternating right lane with the left lane,
Mon-Wed 7PM-6AM Thurs-Fri 8PM-6AM

 
Minimal  None 
14B & 14  Bridge Construction  North: Right shoulder,
Mon-Wed 10AM-12PM

North: Left lane,
Mon-Thurs 8PM-7AM Fri 10PM-8AM

South: Ramp,
Mon-Fri 7AM-3:30PM

 
None  None 
14B & 14A  Bridge Construction  South: Left shoulder,
Mon-Wed 10AM-12PM

South: Left lane,
Mon-Wed 7PM-6AM Thurs-8PM-6AM Fri 8PM-8AM

 
None  None 
14A & 14B  Bridge Construction  North: Left and center lanes,
Wed 9PM-6AM Thurs 10PM-6AM Fri 11PM-6AM

 
None  None 
15 & 14A  Bridge Construction  South: Left and center lanes,
Wed 9PM-6AM Thurs 10PM-6AM Fri 10PM-6AM

 
None  None 
14B & 15A  Bridge Construction  North: Alternating right lane with the left lane,
Mon 10PM-5AM Tues-Wed 9PM-5AM Thurs 10PM-6AM Fri 9PM-7AM

 
Minimal  None 
15A & 17  Bridge Work  North: Right lane,
Thurs 8PM-6AM Fri 10PM-6AM

North: Left lane,
Mon 6PM-6AM Tues 7PM-6AM Wed 7PM-6AM

 
Minimal  None 

New England I-95
Between Exits Work Description Lane Closure Information Likely Impacts Comments
8B & 9  Bridge Construction  North: Left and center lanes,
Wed 12:30AM-2:30AM

North: Right lane,
Tues 12:30AM-2:30AM

 
None  None 
9 & 8B  Bridge Construction  South: Left lane,
Mon-Fri 9AM-4PM

 
None  None 
11 & 8C  Bridge Construction  South: Left and center lanes,
Tues 12:30AM-2:30AM

South: Right lane,
Mon 10PM-12AM

 
None  None 
14 & 15  Bridge Construction  North: Left and center lanes,
Thurs 12:30AM-2:30AM

North: Right lane,
Wed 10PM-12AM

 
None  None 
16 & 15  Bridge Construction  North: Right lane,
Fri 10PM-12AM

North: Left and center lanes,
Sat 12:30AM-2:30AM

South: Left and center lanes,
Fri 12:30AM-2:30AM

South: Right lane,
Thurs 10PM-12AM

 
None  None 


For The Week Starting Monday 08/21/2017
New York Region

Cross Westchester I-287
Between Exits Work Description Lane Closure Information Likely Impacts Comments
1 & 2  Bridge Work  East: Alternating right lane with the left lane,
Sun Single Lane at 10PM, double at 11PM Mon-Thurs Single at 9PM, double at 11PM

 
Minimal  None 
4 & 7  Bridge Construction  East: Right shoulder,
Mon 10AM-3PM

 
None  None 
4 & 8  Bridge Construction  East: Alternating right lane with the left lane,
Tues 9PM-5AM

 
None  None 
5 & 9A  Bridge Construction  East: Alternating right lane with the left lane,
Wed 9PM-5AM

 
None  None 
6 & 5  Bridge Work  East: Alternating right lane with the left lane,
Sun: Single at 10PM, double at 11PM Mon-Thurs: 9PM; double at 11PM

West: Alternating right lane with the left lane,
Sun-Fri Single lane @ 9PM; double lane @ 11PM

 
Minimal  None 
9A & 6  Bridge Construction  West: Alternating right shoulder or left shoulder,
Mon 10AM-3PM

West: Alternating right lane with the left lane,
Tues 9PM-5AM

 
None  None 
9 & 7  Bridge Construction  West: Right lane,
Wed 9PM-5AM

 
None  None 

Mainline I-87
Between Exits Work Description Lane Closure Information Likely Impacts Comments
1 & 5  Bridge Construction  North: Alternating right lane with the left lane,
Mon-Thurs 9AM-2PM Fri 9AM-12PM

 
Minimal  None 
6 & 4  Bridge Construction  South: Left lane,
Mon-Fri 8AM-3PM

 
Minimal  None 
6 & 5  Bridge Inspection  North: Left lane,
Wed 9:30AM-10:30AM

South: Left lane,
Wed 11AM-12PM

 
None  None 
7A & 7  Bridge Construction  South: Left lane,
Mon-Fri 9AM-5PM

 
Minimal  None 
8 & 10  Bridge Construction  North: Right lane,
Fri 9PM-11AM

North: Right 2 lanes,
Fri 9PM-8AM

North: Right 3 lanes,
Fri 11:30PM-6AM

 
Minimal  None 
9 & 10  Road Work  North: Right lane,
Mon-Thurs 9AM-3PM Fri 9AM-1PM

 
Minor  None 
10 & 9  Bridge Construction  South: Left lane,
Sat 7PM-10AM

 
Minimal  None 
12 & 9  Bridge Construction  South: Right lane,
Tues 10AM-3PM

 
Minimal  None 
12 & 14  Bridge Construction  North: Left lane,
Mon-Thurs 8PM-6AM Fri 10PM-6AM

 
Minimal  None 
14 & 13  Bridge Construction  South: Alternating right lane with the left lane,
Mon-Wed 7PM-6AM Thurs-Fri 8PM-6AM

 
Minimal  None 
14B & 14  Bridge Construction  North: Left and center lanes,
Mon-Fri 10PM-6AM

North: Right lane,
Mon-Fri 8PM-7AM

North: Left lane,
Mon-Fri 8PM-7AM

South: Right lane,
Mon-Wed 7PM-6AM Thurs-Fri 8PM-8AM

 
None  None 
14B & 14A  Bridge Construction  South: Left and center lanes,
Mon-Wed 11PM-5AM Thurs-Fri 11PM-6AM

South: Left lane,
Mon-Wed 7PM-6AM Thurs-Fri 8PM-8AM

 
None  None 
14B & 15A  Bridge Construction  North: Alternating right lane with the left lane,
Mon 10PM-5AM Tues-Wed 9PM-5AM Thurs 10PM-6AM Fri 9PM-7AM

 
Minimal  None 
15A & 16  Bridge Construction  North: Right lane,
Mon 9AM-10:30AM

North: Left lane,
Mon 11AM-12PM Mon 12:30PM-1:30PM

 
None  None 
15A & 17  Bridge Work  North: Left lane,
Tues 6AM-11AM Thurs 6AM-9AM

North: Right lane,
Mon 6AM-10AM Wed 6AM-10AM

 
Minimal  None 
17 & 16  Bridge Construction  South: Right lane,
Tues 9AM-10:30AM

South: Left lane,
Tues 11AM-12PM Tues 12:30PM-1:30PM

 
None  None 

New England I-95
Between Exits Work Description Lane Closure Information Likely Impacts Comments
8B & 15  Bridge Construction  North: Alternating right lane with the left lane,
Mon-Thurs 10PM-5AM

 
None  None 
9 & 8B  Bridge Construction  South: Right shoulder,
Mon-Fri 9AM-4PM

 
None  None 
15 & 8B  Bridge Construction  South: Alternating right lane with the left lane,
Mon-Thurs 10PM-5AM

 
None  None 

Back to Top

Traffic Maps & Alerts

Impact Key
Minimal
Traffic moving

Minor
Traffic delayed up to 5 min.

Moderate
Traffic delayed 5-20 min.

Severe
Traffic Delayed >= 20 min.