Project Objectives
The objectives of this project are to provide operational improvements which will relieve congestion, reduce delays and improve the safety conditions at the Woodbury Toll Barrier. Specific objectives include:
- Providing four Highway Speed E-ZPass (65 mph) lanes, two in each direction, at the Woodbury Barrier;
- Relieving congestion, reducing delays and improving the level of service and mobility through the project area;
- Rehabilitating deteriorated mainline pavement sections, reconstructing the shoulders, and providing a smooth riding surface within the project limits; and
- Avoiding and minimizing environmental impacts.
Project Schedule
Contract 1:
Let: November, 2006
Completed: December 2007
Contract 2:
Let: November 2007
Scheduled Construction Completion: Summer 2010
|