Project Schedule/Highlights
Project Schedule (Contract Awarded in 2006)
- Physical work on the bridge began on September 7, 2007, working out from the Rockland County shore.
- The project is 99% complete. The only remaining work includes various punch list items.
- It is anticipated that the project will be completed in the Summer of 2010.
Project Schedule (Contract Awarded in 2010)
- In 2010, the Contractor will initiate field measurements for the new panels.
- Replacement of road surface deck panels on the eastern portion of the Bridge (2010/2011).
- Installation of safety railings & relocation of the fiber optic lines crossing the Bridge (2010).
- Replacement of the movable barrier deployed to shift traffic flow during peak hours (2010/2011).
- It is anticipated that the overall project will be completed in the Winter of 2012.
Images from 2007 deck replacement project; courtesy of New York State Thruway Authority
|