Skip to Main Content
NYS Thruway Authority Home

New York State Thruway Authority

For more information call:
Media Relations and Communications
(518) 471-5300

Immediate Release: April 1, 2011

Thruway Authority to Continue with Tappan Zee Bridge Deck Replacement Project

Deck replacement work on the Tappan Zee Bridge will continue during the week of April 4, 2011, the New York State Thruway Authority announced.

The work will be done in sequential order, is weather-dependent, and is subject to change. Updates will be issued to announce any change in schedule.

Monday, April 4 through Thursday, April 7

Work will begin at 7 p.m. resulting in the closure of one right northbound lane until 4:30 a.m. from milepost 12.6 to milepost 16.5 on the Tappan Zee Bridge. At least three lanes southbound and three lanes northbound will be opened to traffic from 7 p.m. to 4:30 a.m.

During Monday through Thursday night operations, due to the northbound lane closure, the entrance ramp from Broadway (southbound) in Tarrytown will also be closed from 7  p.m. until 4:30 a.m. All traffic will be detoured to the entrance ramp from Route 119.

Friday, April 8

Work will begin at 8 p.m. resulting in the closure of one right northbound lane until 6 a.m. from milepost 12.6 to milepost 16.5 on the Tappan Zee Bridge. At least three lanes southbound and three lanes northbound will be opened to traffic from 8 p.m. to 6 a.m.

During Friday night operations, due to the northbound lane closure, the entrance ramp from Broadway (southbound) in Tarrytown will also be closed from 8 p.m. until 6 a.m. All traffic will be detoured to the entrance ramp from Route 119.

Saturday, April 9 and Sunday, April 10

No work scheduled.

These lane closures are required for the contractor to perform utility and electrical work along the northbound side of the bridge from milepost 13.3 to milepost 16.2.

For the safety of the public and construction workers, motorists are urged to proceed with caution and obey posted work-zone speed limits.

Traffic updates will be broadcast to motorists via Variable Message Signs along the highway and by Highway Advisory Radio 530 AM in the Tappan Zee Bridge corridor, as well as 1610 AM in the Newburgh area.

The second phase of the deck replacement project is slated for completion in the Winter of 2012.

-30-

Google Translate Disclaimer