Skip to Main Content
NYS Thruway Authority Home

New York State Thruway Authority

For more information call:
Media Relations and Communications
(518) 471-5300

For Immediate Release:  Monday, November 9, 2009

Thruway Authority to Continue Tappan Zee Bridge Deck Replacement Project
Revised Work Schedule for Monday, November 9 - Wednesday, November, 11

The New York State Thruway Authority announced that deck replacement work on the Tappan Zee Bridge will continue during the week of November 9, 2009

Please note the work scheduled to take place on Monday, November 9 through Wednesday, November 11 will now be taking place in the southbound direction. It was previously announced by the Authority on Thursday, November 5, that this work would take place in the northbound direction.

On Monday, November 9 through Saturday, November 14, the contractor will continue the installation of the main span joints in the center lanes from the southbound roadway. 

All work is weather-dependent and subject to change.

Updates will be issued announcing any change in schedule. Lane closures during this operation:

Monday, November 9

Work will begin at 8 p.m. resulting in the closure of two left southbound lanes, with an additional left southbound lanes closing at 9 p.m., and another southbound left at 11 p.m., until 6 a.m. from milepost 13.8 to the west abutment on the Tappan Zee Bridge. At least one lane southbound and two lanes northbound will be opened to traffic from 11 p.m. until 6 a.m.

These lane closures are for the installation of new deck joints in the center lanes of the main span. All lanes are expected to be open by 6 a.m. the following day.

During Monday nights’ operations, due to the southbound lane closures, the southbound entrance at Interchange 10 will be closed and southbound traffic will be detoured on a posted detour route through Nyack to the entrance to the southbound roadway at Route 59 near Interchange 11.

In addition, two left lanes in the northbound direction from Interchange 8 to milepost 13 will be closed from 8 p.m. until 6 a.m. as part of this work.

Due to the northbound lane closures, the entrance ramp from Broadway (southbound) in Tarrytown will also be closed from 8 p.m. until 6 a.m. All traffic will be detoured to the entrance ramp from Route 119.

Tuesday, November 10

Work will begin at 8 p.m. resulting in the closure of two left southbound lanes, with an additional left southbound lanes closing at 10 p.m., and another southbound left at 11 p.m., until 6 a.m. from milepost 13.8 to the west abutment on the Tappan Zee Bridge. At least one lane southbound and two lanes northbound will be opened to traffic from 11 p.m. until 6 a.m.

These lane closures are for the installation of new deck joints in the center lanes of the main span. All lanes are expected to be open by 6 a.m. the following day.

During Tuesday nights’ operations, due to the southbound lane closures, the southbound entrance at Interchange 10 will be closed and southbound traffic will be detoured on a posted detour route through Nyack to the entrance to the southbound roadway at Route 59 near Interchange 11.

In addition, two left lanes in the northbound direction from Interchange 8 to milepost 13 will be closed from 9 p.m. until 6 a.m. as part of this work.

Due to the northbound lane closures, the entrance ramp from Broadway (southbound) in Tarrytown will also be closed from 8 p.m. until 6 a.m. All traffic will be detoured to the entrance ramp from Route 119.

Wednesday, November 11

Work will begin at 8 p.m. resulting in the closure of one left southbound lanes, with an additional two left southbound lanes closing at 9 p.m., and another southbound left at 11 p.m., until 6 a.m. from milepost 13.8 to the west abutment on the Tappan Zee Bridge. At least one lane southbound and two lanes northbound will be opened to traffic from 11 p.m. until 6 a.m.

These lane closures are for the installation of new deck joints in the center lanes of the main span. All lanes are expected to be open by 6 a.m. the following day.

During Wednesday nights’ operations, due to the southbound lane closures, the southbound entrance at Interchange 10 will be closed and southbound traffic will be detoured on a posted detour route through Nyack to the entrance to the southbound roadway at Route 59 near Interchange 11.

In addition, two left lanes in the northbound direction from Interchange 8 to milepost 13 will be closed from 8 p.m. until 6 a.m. as part of this work.

Due to the northbound lane closures, the entrance ramp from Broadway (southbound) in Tarrytown will also be closed from 8 p.m. until 6 a.m. All traffic will be detoured to the entrance ramp from Route 119.

Thursday, November 12

Work will begin at 8 p.m. resulting in the closure of two left southbound lanes, with two additional left southbound lanes closing at 11 p.m., until 6 a.m. from milepost 13.8 to the west abutment on the Tappan Zee Bridge. At least one lane southbound and two lanes northbound will be opened to traffic from 11 p.m. until 6 a.m.

These lane closures are for the installation of new deck joints in the center lanes of the main span. All lanes are expected to be open by 6 a.m. the following day.

During Thursday nights’ operations, due to the southbound lane closures, the southbound entrance at Interchange 10 will be closed and southbound traffic will be detoured on a posted detour route through Nyack to the entrance to the southbound roadway at Route 59 near Interchange 11.

In addition, two left lanes in the northbound direction from Interchange 8 to milepost 13 will be closed from 10 p.m. until 6 a.m. as part of this work.

Due to the northbound lane closures, the entrance ramp from Broadway (southbound) in Tarrytown will also be closed from 10 p.m. until 6 a.m. All traffic will be detoured to the entrance ramp from Route 119.

Friday, November 13

Work will begin at 9 p.m. resulting in the closure of two left southbound lanes, with an additional left southbound lanes closing at 10 p.m. and another left southbound lane at 1 a.m., until 6 a.m. from milepost 13.8 to the west abutment on the Tappan Zee Bridge. At least one lane southbound and two lanes northbound will be opened to traffic from midnight until 6 a.m.

These lane closures are for the installation of new deck joints in the center lanes of the main span. All lanes are expected to be open by 9 a.m. the following day.

During Friday nights’ operations, due to the southbound lane closures, the southbound entrance at Interchange 10 will be closed and southbound traffic will be detoured on a posted detour route through Nyack to the entrance to the southbound roadway at Route 59 near Interchange 11.

In addition, two left lanes in the northbound direction from Interchange 8 to milepost 13 will be closed from 10 p.m. until 9 a.m. as part of this work.

Due to the northbound lane closures, the entrance ramp from Broadway (southbound) in Tarrytown will also be closed from 10 p.m. until 9 a.m. All traffic will be detoured to the entrance ramp from Route 119.

Saturday, November 14

Work will begin at 8 p.m. resulting in the closure of one left southbound lanes, with two additional left southbound lanes closing at 11 p.m., and another left southbound lane at 1 a.m., until 8 a.m. from milepost 13.8 to the west abutment on the Tappan Zee Bridge. At least one lane southbound and two lanes northbound will be opened to traffic from 11 p.m. until 8 a.m.

These lane closures are for the installation of new deck joints in the center lanes of the main span. All lanes are expected to be open by 10 a.m. the following day.

During Saturday nights’ operations, due to the southbound lane closures, the southbound entrance at Interchange 10 will be closed and southbound traffic will be detoured on a posted detour route through Nyack to the entrance to the southbound roadway at Route 59 near Interchange 11.

In addition, two left lanes in the northbound direction from Interchange 8 to milepost 13 will be closed from 8 p.m. until 9 a.m. as part of this work.

Due to the northbound lane closures, the entrance ramp from Broadway (southbound) in Tarrytown will also be closed from 8 p.m. until 9 a.m. All traffic will be detoured to the entrance ramp from Route 119.

For the safety of the public and construction workers, motorists are urged to proceed with caution and obey posted work-zone speed limits. Work will proceed weather-permitting, and schedule updates will be announced as needed.

Traffic updates will be broadcast to motorists via Dynamic Message Signs along the highway and by Highway Advisory Radio, 530 AM in the Tappan Zee Bridge corridor, as well as 1610 AM in the Newburgh area.

Weather permitting, the deck replacement project is slated for completion in the Fall of 2009.

-30-

Google Translate Disclaimer