For Immediate Release: Friday, May 22, 2009

Thruway Authority to Continue Tappan Zee Bridge Deck Replacement Project

The New York State Thruway Authority announced deck replacement work on the Tappan Zee Bridge will continue the week of May 25, 2009.

On Tuesday, May 26 through Thursday, May 28, installation of new modular joints in the main span and the west deck truss will continue in the center lanes. 

On the evenings of Friday, May 29 and Saturday, May 30, the Authority’s contractor will be installing transition ramps of approximately 50 feet of asphalt leading up to steel plates on a modular joint on the west deck truss of the Tappan Zee Bridge. The transition ramps will cover the entire width of the bridge at each bridge joint location and will gradually thicken until the ramp is flush with the top of the roadway plate(s). It is anticipated the asphalt ramps will provide a smooth transition over the roadway plates thereby minimizing impacts to motorists. Additionally, the ramps are to encourage drivers to continue traveling at reasonable speeds.  In addition, the contractor will be removing one of the asphalt transition ramps on the west deck truss, where the center portion of the new bridge joint is completed.

All work is weather-dependent and subject to change.

Updates will be issued announcing any change in schedule. Lane closures during this operation:

Monday, May 25

There is no night work scheduled.

Tuesday May 26 through Wednesday, May 27

Work will begin at 8 p.m. resulting in the closure of two left southbound lanes, with an additional left southbound lane closing at 10 p.m., until 6 a.m. from Interchange 10 to the east deck truss on the Tappan Zee Bridge.

These lane closures are for the installation of new deck joints in the center lanes main span and west deck truss. All lanes are expected to be open by 6 a.m. the following day.

Thursday, May 28

Work will begin at 9 p.m. resulting in the closure of two left southbound lanes, with an additional left southbound lane closing at 10 p.m., until 6 a.m. from Interchange 10 to the east deck truss on the Tappan Zee Bridge.

These lane closures are for the installation of new deck joints in the center lanes main span and west deck truss. All lanes are expected to be open by 6 a.m. the following day.

During Tuesday through Thursday nights’ operations, two left lanes in the northbound direction from Interchange 8 to milepost 13 will also be closed from 10 p.m. until 6 a.m. as part of this work.

Due to the northbound lane closures, the entrance ramp from Broadway (southbound) in Tarrytown will also be closed from 10 p.m. until 6 a.m. All traffic will be detoured to the entrance ramp from Route 119.

Friday, May 29
Work will begin at 8 p.m. resulting in the closure of the right northbound lane, to three northbound lanes at 9:30 p.m., to four northbound at midnight until 8 a.m. from Interchange 8 to the east abutment on the Tappan Zee Bridge.

During Friday night’s operations, due to the northbound lane closures, the entrance ramp from Broadway (southbound) in Tarrytown will also be closed from 10 p.m. until 8 a.m. All traffic will be detoured to the entrance ramp from Route 119.

Two southbound left lanes will be closed from Interchange 10 to the west abutment from 8:30 p.m. until 8 a.m.

These lane closures are for the placement of a steel plate system with asphalt ramps for the installation of new deck joints on the northbound west deck truss. In addition, the contractor will be removing a steel plate system for an already completed joint on the west deck truss.  All lanes are expected to be open by 8 a.m. the following day.

Saturday, May 30

Work will begin at 8 p.m. resulting in the closure of two right southbound lanes, to three right southbound lanes at 10 p.m. until 10 a.m. from Interchange 10 to the east deck truss on the Tappan Zee Bridge.

During Saturday night’s operations, the southbound entrance at Interchange 10 will be closed and southbound traffic will be detoured on a posted detour route through Nyack to the entrance to the southbound roadway at Route 59 near Interchange 11.

Two left lanes in the northbound direction from Interchange 8 to milepost 13 will also be closed from 9 p.m. until 10 a.m. as part of this work.

Due to the northbound lane closures, the entrance ramp from Broadway (southbound) in Tarrytown will also be closed from 9 p.m. until 10 a.m. All traffic will be detoured to the entrance ramp from Route 119.

These lane closures are for the placement of a steel plate system with asphalt ramps for the installation of a new deck joint on the southbound west deck truss. In addition, the contractor will be removing a steel plate system for an already completed joint on the west deck truss.  All lanes are expected to be open by 10 a.m. the following day.

For the safety of the public and construction workers, motorists are urged to proceed with caution and obey posted work-zone speed limits. Work will proceed weather-permitting, and schedule updates will be announced as needed.

Traffic updates will be broadcast to motorists via Dynamic Message Signs along the highway and by Highway Advisory Radio, 530 AM in the Tappan Zee Bridge corridor, as well as 1610 AM in the Newburgh area.

Weather permitting, the deck replacement project is slated for completion by Fall 2009.