Skip to Main Content
Skip to Navigation
NY.gov Portal State Agency Listing

New York State Thruway Authority

All Projects

Planned Projects

  • Ardsley Service Area (MP 6.0 NB): Replace Aging Water Supply Main and Demolition of Obsolete Fire Water Supply System
  • Critical Facility Repairs and Rehabilitaiton - Statewide
    • Estimated Letting Year: NA
    • Approved Construction Amount: $4,000,000.00
  • MP 278.90: Tarbell Road Maintenance Building (M3341) - Reconfigure/Refurbish
    • Estimated Letting Year: 2017
    • Approved Construction Amount: $.00
  • MP 423.19: Walden Avenue Maintenance Facility - Replace Metal Buildings
    • Estimated Letting Year: 2018
    • Approved Construction Amount: $.00
  • MP 423.19: Walden Avenue Maintenance Facility - Construct / Expand Vehicle Wash Bay
    • Estimated Letting Year: 2018
    • Approved Construction Amount: $.00
  • MP 252.71 and MP 304.2: Verona and Weedsport Maintenance - Construct Municipal Sewer / Water Connections
    • Estimated Letting Year: 2016
    • Approved Construction Amount: $.00
  • MP 278.9: Syracuse Maintenance Facility - Replace Metal Building
    • Estimated Letting Year: 2019
    • Approved Construction Amount: $.00
  • Syracuse Division: Upgrade Waste Water Treatment Plants Division-Wide
    • Estimated Letting Year: 2019
    • Approved Construction Amount: $.00
  • MP 210.0: Iroquois Service Area: Roof Replacement
  • MP 103.0: Malden Service Area: Pitched Roof Replacement
  • MP's 45.2 and 607.7: Replacement of Deteriorated Roofs at the Harriman and Larchmont Maintenance Sections
    • Estimated Letting Year: 2017
    • Approved Construction Amount: $.00
  • MP 141.9: Albany Maintenance Facility - Replace Metal Building
    • Estimated Letting Year: 2018
    • Approved Construction Amount: $.00
  • MP 18.8: Nyack Maintenance - Construct Vehicle Wash Bay and Storage
    • Estimated Letting Year: 2018
    • Approved Construction Amount: $.00
  • MP 607.7: Larchmont Maintenance - Replace Existing Metal Building
    • Estimated Letting Year: 2019
    • Approved Construction Amount: $.00
  • MP 900.70 SB: Construction of New Salt Shed at Niagara Interchange
    • Estimated Letting Year: 2015
    • Approved Construction Amount: $.00
  • Harriman Maintenance Section and Toll Building (Exit 16, MP 45.2): Connect to Municipal Water and Sewer
  • MP 33: Ramapo and Sloatsburg Service Areas - Demolition of Aging Wastewater Facility and Construct Connection to Municipal System
    • Estimated Letting Year: 2015
    • Approved Construction Amount: $1,450,000.00
  • MP 91.4: Kingston Maintenance Section - Replace Salt Shed
  • Albany Maintenance Section: Replace Salt Shed
    • Estimated Letting Year: 2016
    • Approved Construction Amount: $500,000.00
  • MP's 210 WB and 266 WB: Iroquois and Chittenango Service Areas - Rehabilitate/Replace Wastewater Treatment Plants
    • Estimated Letting Year: 2016
    • Approved Construction Amount: $2,000,000.00
  • MP's 310 EB and 337 EB: Port Byron and Clifton Springs Service Areas - Rehabilitate/Replace Wastewater Treatment Plants
    • Estimated Letting Year: 2016
    • Approved Construction Amount: $2,000,000.00
  • MP's 227 WB, 280 EB, 292 WB and 310 EB: Replacement of Deteriorated Flat Roofs at the Schuyler, DeWitt, Warners and Port Byron Service Areas
    • Estimated Letting Year: 2015
    • Approved Construction Amount: $1,600,000.00
  • MP's 227 WB and 244 EB: Schuyler and Oneida Service Areas - Rehabilitate/Replace Wastewater Treatment Plants
    • Estimated Letting Year: 2015
    • Approved Construction Amount: $2,000,000.00
  • MP's 292 WB and 324 WB: Warners and Junius Ponds Service Areas - Rehabilitate/Replace Wastewater Treatment Plants
    • Estimated Letting Year: 2015
    • Approved Construction Amount: $2,000,000.00
  • Reconstruct Buildings at the Old Erie Canal Port Byron Lock Rest Area
    • Estimated Letting Year: 2014
    • Approved Construction Amount: $2,225,000.00
  • Construct Facilities at the Old Erie Canal Port Byron Rest Area
    • Estimated Letting Year: 2015
    • Approved Construction Amount: $1,500,000.00
  • MP 26.37: College Road (Almshouse Road) Bridge over Thruway - Replacement
  • MP 60.10: Newburgh Interchange Bridge (Exit 17) over Thruway - Replacement
  • MP 91.88: Sawkill Road (County Route 42) Bridge over Thruway - Replacement
  • MP NE7.72: Larchmont Station Plaza - Substructure Repairs
  • MP 140.98: Thruway Bridge over Route 9W - Rehabilitation
  • MP 150.81: Old State Road Bridge over Thruway - Replacement
  • MP 165.11: Rehabilitate or Replace Retaining Wall west of Exit 26
    • Estimated Letting Year: 2016
    • Approved Construction Amount: $15,000,000.00
  • MP BS16.26: Route 295 Bridge over Berkshire Thruway - Rehabilitation
  • MP 420.33, MP 420.34 and MP 420.36: I-90/I-290 Interchange (Exit 50) Bridges - Rehabilitations
  • MP 411.60: Ransom Road Bridge over Thruway - Replacement
  • MP NE5.76: North Avenue Bridge over I-95 (New England Thruway) (Phase 3): Replacement
  • MP 112.57: Leeds-Old Kings Highway Bridge over Thruway - Replacement
  • MP 306.72: Thruway over NYCRR - Rehabilitation
  • MP 380.57: West Bergen Road Bridge over Thruway - Replacement
  • Paint 2 New York Division Bridges with Poor Paint Condition Ratings - 2014
  • MP 914.35, MP 914.99, MP 920.35 and MP 921.12 North and South Grand Island Bridges: Retrofit / Repair Roller Bearings, Pins and Hangers
  • MP 453.46: Mile Strip Road and MP 454.31: Four Mile Level Road Bridges over Thruway - Replacements
  • Pre-Purchase Structural Steel for MP 454.31, Four Mile Level Road (Route 438) Bridge over Thruway - Replacement
  • MP 486.97, MP 476.17 and MP 476.18 Walker Road and Lake Avenue (Rt 380, Eastbound and Westbound) Bridges over Thuway: Rehabilitation
  • MP 238.22: Thruway Bridge over Oriskany Boulevard (Route 69) - Replacement
  • West Seneca (Exit 54, MP 427.9) to Lackawanna Toll Barrier (MP 430.6): Pavement Resurfacing, Replacement of Thruway Bridge over NYCRR & Penn RR (MP 430.05) and Rehabilitate Four Other Bridges
  • MP 906.58: Porter Avenue Bridge over Thruway - Replacement
  • MP 407.27: South Newstead Road Bridge over Thruway - Replacement
  • MP 256.78: Thruway Bridge over Lake Street - Removal
  • MP 420.70: Cleveland Drive Bridge over Thruway - Replacement
  • MP 210.62: Thruway Westbound Bridge over Little Falls Interchange Ramp (Exit 29A) - Deck Replacement
  • MP N15.46: Beaver Island State Parkway Bridge over I-190 Thruway - Replacement
  • MP 427.95: Route 400 Ramp Bridge over Harlem Road - Replacement (NYSDOT Project)
  • MP 225.48 & 225.49: Thruway Bridges over County Road 53 - Removal
  • MP 261.73: North Peterboro Street (Route 13) Bridge over Thruway - Replacement
  • MP 340.15: Manchester (Exit 43) Interchange Bridge - Replacement
  • MP 58.43: Thruway Bridge over Newburgh-Cambell Hall Road (Route 207) - Replacement
  • MP BS15.09: Taconic Parkway (Exit B2) Bridge over Berkshire Thruway - Replacement
  • MP NE9.55: Old White Plains Road Bridge over I-95 (New England Thruway) - Rehabilitation
  • MP 282.93: Interchange 36 Bridge Replacement and Ramp Realignment
  • I-95 (New England Thruway) Bridge Maintenance Cleaning for Steel Preservation - 2015
    • Estimated Letting Year: 2014
    • Approved Construction Amount: $700,000.00
  • Paint Six Albany Division Bridges with Poor Paint Condition Ratings
    • Estimated Letting Year: 2016
    • Approved Construction Amount: $.00
  • 222nd Street and Dyre Avenue Pedestrian Bridges and Baychester Road Bridge: Substructure Rehabilitation
  • Thruway over Hurley Ave. (MP 90:55) and Berkshire Spur over County Rd 19 (MP 805.22 and 805.23) - Rehabilitations
  • Paint New York Division Bridges with Poor Paint Condition Ratings - 2017
    • Estimated Letting Year: 2017
    • Approved Construction Amount: $.00
  • Syracuse Division: Bridge Substructure and Joint Repairs at Various Locations
    • Estimated Letting Year: 2017
    • Approved Construction Amount: $2,000,000.00
  • Paint 9 Syracuse Division Bridges with Poor Paint Condition Ratings - 2016
    • Estimated Letting Year: 2016
    • Approved Construction Amount: $2,500,000.00
  • Paint 10 Buffalo Division Bridges with Poor Paint Condition Ratings
    • Estimated Letting Year: 2014
    • Approved Construction Amount: $3,800,000.00
  • MP N20.35 and MP N21.12: North Grand Island Southbound and Northbound Bridges - Painting
  • North Grand Island Bridges - Steel Repairs
  • Repair/Replace Joints and Substructure and Fascia Repairs on Various Buffalo Division Bridges
    • Estimated Letting Year: 2015
    • Approved Construction Amount: $2,250,000.00
  • South Grand Island Bridges: Maintenance Cleaning for Steel Preservation - 2015
  • Buffalo Division Bridge Deck Rehabilitations at Various Locations
    • Estimated Letting Year: 2016
    • Approved Construction Amount: $2,000,000.00
  • MP 273.16 to MP 274.79: Rehabilitation of Six Bridges - Thruway over Chittenango Creek (EB/WB), Limestone Creek (EB/WB) and Butternut Creek (EB/WB)
  • Replace Four Sign Structures at MP 1.55, MP 1.88, MP 600.58 and MP 600.95
    • Estimated Letting Year: 2014
    • Approved Construction Amount: $1,750,000.00
  • Repairs to Deteriorated/Damaged Steel Members on Eight New York Division Bridges
    • Estimated Letting Year: 2014
    • Approved Construction Amount: $1,750,000.00
  • MP 23.09: Thruway over Pascack Road; MP 23.62: Scotland Hill Road over Thruway; and MP 25.10: Thruway over Saddle River Road Bridges: Rehab
  • Seismic Retrofits for Various Bridges Statewide
    • Estimated Letting Year: 2016
    • Approved Construction Amount: $4,000,000.00
  • Repair or Replacement of Substructure, Joints and other Bridge Elements for Various Bridges Statewide - 2016
    • Estimated Letting Year: 2016
    • Approved Construction Amount: $4,000,000.00
  • I-95 (New England Thruway) Bridge Maintenance Cleaning for Steel Preservation - 2016
    • Estimated Letting Year: 2016
    • Approved Construction Amount: $700,000.00
  • South Grand Island Bridges: Maintenance Cleaning for Steel Preservation - 2016
  • MP 485.59, MP 485.60 and MP 485.86: Pin & Hanger Evaluation/Repairs of Chautauqua Creek and Hawley Street Bridges
  • I-95 (New England Thruway) Bridge Maintenance Cleaning for Steel Preservation - 2018
    • Estimated Letting Year: 2018
    • Approved Construction Amount: $.00
  • MP 904.24: Niagara Viaduct Deck - Underdeck Repairs
  • MP 33.0: Sloatsburg Pedestrian Overpass - Roof Replacement
  • Syracuse Division: Bridge Joint Repair/Replace at Various Locations
    • Estimated Letting Year: 2016
    • Approved Construction Amount: $.00
  • Syracuse Division: Bridge Culvert Repairs at Various Locations
    • Estimated Letting Year: 2016
    • Approved Construction Amount: $.00
  • Albany Division: Joint Substructure Repairs at Various Locations
    • Estimated Letting Year: 2017
    • Approved Construction Amount: $.00
  • MP BS16.09 & MP BS16.10: Berkshire Thruway Bridge (eastbound and westbound) over Stony Kill Rehabilitations
  • Albany Division: Bridge Painting at Various Locations
    • Estimated Letting Year: 2018
    • Approved Construction Amount: $.00
  • Paint Syracuse Division Bridges with Poor Paint Condition Ratings - 2018
    • Estimated Letting Year: 2018
    • Approved Construction Amount: $.00
  • MP 131.90: Thruway over Coeymans Creek - Seismic Vulnerability
  • Albany Division: Bridge Joint Repair/Replace at Various Locations
    • Estimated Letting Year: 2019
    • Approved Construction Amount: $.00
  • MP 220.67: Thruway over Herkimer-Franklin and Route 5S and CSXRR and MP 238.09: Thruway over Main Street and CSXRR - Bridge Painting
  • Albany Division: Bridge Substructure/Concrete Repairs at Various Locations
    • Estimated Letting Year: 2019
    • Approved Construction Amount: $.00
  • Albany Division: Bridge Culvert Repairs at Various Locations
    • Estimated Letting Year: 2019
    • Approved Construction Amount: $.00
  • Albany Division: Bridge Scour Repairs at Various Locations
  • Albany Division: Bridge Steel Repairs/Pin and Hanger at Various Locations
    • Estimated Letting Year: 2019
    • Approved Construction Amount: $.00
  • MP 84.54: Thruway Bricge over County Road 73- Rehabilitation
  • New York Division: Bridge Joint Repair/Replace at Various Locations
    • Estimated Letting Year: 2016
    • Approved Construction Amount: $.00
  • MP 240.48: Judd Road over Thruway - Replacement
  • Syracuse Division: Bridge Joint Repair/Replace at Various Locations
    • Estimated Letting Year: 2019
    • Approved Construction Amount: $.00
  • Syracuse Division: Bridge Substructure/Concrete Repairs at Various Locations
    • Estimated Letting Year: 2019
    • Approved Construction Amount: $.00
  • MP 210.65: Thruway Ramp over Route 5S - Concrete Wearing Surface
  • MP 283.79: Electronics Parkway Interchange Ramp over Thruway - Replacement
  • MP 287.11: Thruway over Onondaga Parkway - Rehabilitation
  • MP 287.25: Thruway over Onondaga Lake Outlet - Rehabilitation
  • MP 327.54: Thruway over Canandiagua Outlet - Replacement
  • New York Division: Bridge Substructure/Concrete Repairs at Various Locations
    • Estimated Letting Year: 2016
    • Approved Construction Amount: $.00
  • MP 434.48 EB and 434.49 WB: Thruway over Erie RR - Rehabilitations
  • New York Division: Bridge Joint Repair/Replace at Various Locations
    • Estimated Letting Year: 2018
    • Approved Construction Amount: $.00
  • New York Division: Bridge Substructure/Concrete Repairs at Various Locations
    • Estimated Letting Year: 2018
    • Approved Construction Amount: $.00
  • MP 2.20: Cross County Parkway Ramp over Thruway - Replacement
  • Buffalo Division: Bridge Scour Remediation at Various Locations
    • Estimated Letting Year: 2017
    • Approved Construction Amount: $.00
  • MP 436.65: Camp Road Route 75 over Thruway - Rehabilitation
  • MP 467.11: South Roberts Road over Thruway - Rehabilitation
  • MP 477.55: Matthews Road over Thruway - Rehabilitation
  • Buffalo Division: Bridge Steel Repairs at Various Locations
    • Estimated Letting Year: 2018
    • Approved Construction Amount: $.00
  • Buffalo Division: Bridge Culvert Repairs at Various Locations
    • Estimated Letting Year: 2018
    • Approved Construction Amount: $.00
  • MP 397.67: Indian Falls - East Pembroke Road over Thruway - Rehabilitation
  • MP 416.12: Thruway Bridge over CSX Railroad - Removal
  • MP 434.85: South Park Ave. Route 62 over Thruway - Rehabilitation
  • MP 458.20: Hanover-Hanford CR93 over Thruway - Rehabilitation
  • MP 914.99: South Grand Island Bridge Southbound - Replace Sidewalk
  • Syracuse Division: Bridge Steel, Fascia and Rail Repair/Replace at Various Locations
    • Estimated Letting Year: 2018
    • Approved Construction Amount: $.00
  • Paint New York Division Bridges with Poor Paint Condition Ratings - 2019
    • Estimated Letting Year: 2019
    • Approved Construction Amount: $.00
  • Grand Island Bridges: Maintenance Cleaning for Steel Preservation - 2018
  • Grand Island Bridges: Maintenance Cleaning for Steel Preservation - 2019
  • I-95 (New England Thruway) Bridge Maintenance Cleaning for Steel Preservation - 2019
    • Estimated Letting Year: 2019
    • Approved Construction Amount: $.00
  • Buffalo Division: Bridge Concrete Repairs at Various Locations
    • Estimated Letting Year: 2019
    • Approved Construction Amount: $.00
  • Buffalo Division: Bridge Joint Repair/Replace at Various Locations
    • Estimated Letting Year: 2019
    • Approved Construction Amount: $.00
  • Paint Buffalo Division Bridges with Poor Paint Condition Ratings - 2019
    • Estimated Letting Year: 2019
    • Approved Construction Amount: $.00
  • MP 362.44: West Henrietta Interchange Bridge over Thruway - Replacement
  • MP 113.22: Catskill Creek Slope Stabilization
    • Estimated Letting Year: 2019
    • Approved Construction Amount: $.00
  • Buffalo Division: Bridge Scour Remediation at Various Locations
    • Estimated Letting Year: 2019
    • Approved Construction Amount: $.00
  • MP 449.17: Angola-Brant Road, Route 323 over Thruway - Deck Replacement
  • Repair or Replacement of Substructure, Joints and other Bridge Elements for Various Bridges Statewide - 2017
    • Estimated Letting Year: 2017
    • Approved Construction Amount: $.00
  • Repair or Replacement of Substructure, Joints and other Bridge Elements for Various Bridges Statewide - 2018
    • Estimated Letting Year: 2018
    • Approved Construction Amount: $.00
  • Repair or Replacement of Substructure, Joints and other Bridge Elements for Various Bridges Statewide - 2019
    • Estimated Letting Year: 2019
    • Approved Construction Amount: $.00
  • MP 46.42: Estrada Road Bridge over Thruway - Rehabilitation
  • MP 54.74: Thruway Bridge over NY Ont and West RR (Abandoned) - Removal
  • MP 904.13: Louisiana Street over Thruway - Rehabilitation
  • MP 366.42: Thruway Bridge over Scottsville Road - Replacement
  • MP N18.39: Bedell Road Bridge over I-190 (Niagara Thruway) and MP N12.84, I-190 Bridge over Route 324: Rehabilitations
  • MP BS8.93/.94 and MP BS9.50/.51: Mainline Bridges (EB & WB) over Route 203 and over County Road 38 - Rehabilitation
  • MP 191.32: Thruway Bridge over Flat Creek - Replacement
  • MP 85.33: Kingston High Falls Route 32 Bridge over Thruway - Rehabilitation
  • MP BS11.34 and MP BS11.35: Berkshire Thruway Bridges (eastbound and westbound) over Kinderhook Creek: Rehabilitations
  • Two Bridge Replacements at MP 284.80: Thruway Bridge over Vine Street and, MP 284.74: Thruway Bridge over CSX Railroad (Salina)
  • New York Division: On-Demand Infrastructure Repair Contract - 2014-2016
    • Estimated Letting Year: 2014
    • Approved Construction Amount: $2,000,000.00
  • New York Division: Substructure Repairs to 7 Bridges
    • Estimated Letting Year: 2015
    • Approved Construction Amount: $3,000,000.00
  • Buffalo Division: On-Demand Repair Contract - 2015-2016
    • Estimated Letting Year: 2014
    • Approved Construction Amount: $2,000,000.00
  • MP BS1.08: Castleton Bridge Truss Spans - Painting and Repair of Deteriorated Steel Members
  • MP 81.72: Thruway Bridge over Wallkill River - Rehabilitation
  • MP 369.85: Union Street Bridge over Thruway - Replacement
  • Albany Division: On-Demand Repair Contract - 2014-2016
    • Estimated Letting Year: 2014
    • Approved Construction Amount: $2,000,000.00
  • Syracuse Division: On-Demand Bridge Repair Contract - 2016-2017
    • Estimated Letting Year: 2015
    • Approved Construction Amount: $2,000,000.00
  • MP 920.35: North Grand Island Bridge Northbound - Bridge Deck Overlay
  • Buffalo Division: On-Demand Repair Contract - 2016-2018
    • Estimated Letting Year: 2016
    • Approved Construction Amount: $2,000,000.00
  • MP 475.25 and MP 475.26: I-90 Bridges over CSX & Norfolk Southern RR - Rehabilitation
  • New York Division: On-Demand Repair Contract - 2016-2018
    • Estimated Letting Year: 2016
    • Approved Construction Amount: $2,000,000.00
  • Albany Division: On-Demand Repair Contract - 2016-2018
    • Estimated Letting Year: 2016
    • Approved Construction Amount: $2,000,000.00
  • Syracuse Division: On-Demand Repair Contract - 2016-2018
    • Estimated Letting Year: 2016
    • Approved Construction Amount: $2,000,000.00
  • New York Division: On-Demand Repair Contract - 2018-2020
    • Estimated Letting Year: 2018
    • Approved Construction Amount: $2,000,000.00
  • Albany Division: On-Demand Repair Contract - 2018-2020
    • Estimated Letting Year: 2018
    • Approved Construction Amount: $2,000,000.00
  • Syracuse Division: On-Demand Repair Contract - 2018-2020
    • Estimated Letting Year: 2018
    • Approved Construction Amount: $2,000,000.00
  • Buffalo Division: On-Demand Repair Contract - 2018-2020
    • Estimated Letting Year: 2018
    • Approved Construction Amount: $2,000,000.00
  • MP 67.86: Route 32 Bridge over Thruway - Rehabilitation
  • MP 420.35: Wherle Drive over Thruway - Substructure and Fascia Repairs
  • MP 27.62: Airmont Road over Thruway -Rehabilitation
  • Thruway Bridges over Seven Lakes Drive (CR 106) (MP 38.60 SB and MP 38.61 NB): Rehabilitations
  • MP 74.17: Clintondale Road Bridge over Thruway - Rehabilitation
  • Brewerton: North Dock Wall - Rehabilitation, Oswego County
  • May's Point: Movable Dam 18 - Rehabilitation, Seneca County
  • Rochester: East Guard Lock - Rehabilitation, Monroe County
  • Pendleton: Guard Gate 18 - Rehabilitation, Niagara County
  • Lyons: Fabrication of New Gates for Lyons Section Dry Dock, Wayne County
    • Estimated Letting Year: 2016
    • Approved Construction Amount: $650,000.00
  • Utica Section: Indian Castle Guard Gate and Lock E-17 Lift Gate - Rehabilitation, Herkimer County
    • Estimated Letting Year: 2016
    • Approved Construction Amount: $13,000,000.00
  • Whitehall: Construction of a New Lock C-12 Utility Structure, Washington County
    • Estimated Letting Year: 2013
    • Approved Construction Amount: $750,000.00
  • Waterford: Lock E-2 South Approach Wall - Rehabilitation, Saratoga County
  • Three Rivers: Terminal Wall - Rehabilitation, Onondaga County
  • Lockport: Retaining Wall - Rehabilitation, Niagara County
  • Lock E-34: Shotcrete Wall - Rehabilitation, Niagara County
    • Estimated Letting Year: 2015
    • Approved Construction Amount: $.00
  • Medina: High Wall - Rehabilitation, Orleans County
    • Estimated Letting Year: 2016
    • Approved Construction Amount: $5,000,000.00
  • Oswego: Lock O-7 - Rehabilitation, Oswego County
    • Estimated Letting Year: 2016
    • Approved Construction Amount: $20,000,000.00
  • Statewide: Canal On-Demand Repair and Vessel Recovery Contract 2015 - 2016
    • Estimated Letting Year: 2014
    • Approved Construction Amount: $2,000,000.00
  • Palmyra: Ganargua Creek Aqueduct Rehabilitation, Wayne County
    • Estimated Letting Year: 2016
    • Approved Construction Amount: $3,000,000.00
  • Scotia: Rehabilitation of Lock E-8 Breast Wall/Floor, Movable Dam 4 and Lock E-8 Southeast Approach Wall
  • Newark: Military Run Stream Culvert - Replacement, Wayne County
  • Monroe County: Erie Canal Lock 32 Bypass Culvert - Repairs, Monroe County (funded with 2005 Transportation Bond Act funds)
  • Amsterdam: Guy Park Manor Repairs at Lock E-11, Montgomery County (Tropical Storms Irene and Lee Recovery Project - Partial FEMA Eligible)
    • Estimated Letting Year: 2015
    • Approved Construction Amount: $4,200,000.00
  • Syracuse: Inner Harbor Upland Disposal Site, Onondaga County
    • Estimated Letting Year: 2015
    • Approved Construction Amount: $800,000.00
  • St. Johnsville: Lock E-16 June 2013 Storm Recovery Work, Montgomery County and Improvements to the Rocky Rift Movable Dam, Herkimer County
    • Estimated Letting Year: 2015
    • Approved Construction Amount: $2,000,000.00
  • Eastern Division: Scour Repairs at Various Locations
    • Estimated Letting Year: 2014
    • Approved Construction Amount: $2,000,000.00
  • Newark: Replace Lower Miter Gates at Lock E-28B, Wayne County
  • Statewide: Canal On-Demand Repair and Vessel Recovery Contract 2017 - 2018
    • Estimated Letting Year: 2016
    • Approved Construction Amount: $.00
  • Statewide: Canal On-Demand Repair and Vessel Recovery Contract 2019 - 2020
    • Estimated Letting Year: 2018
    • Approved Construction Amount: $.00
  • MP 12.85: Improvements to I-87 Interchange 9 Ramp Intersection with Route 9
  • I-95 (New England Thruway), Port Chester to Connecticut State Line: Pavement Reconstruction, Ramp Work, 2 Bridge Replacements and 1 Bridge Rehabilitation
  • Statewide: Various Culvert Rehabilitations/Replacements - 2016
    • Estimated Letting Year: 2016
    • Approved Construction Amount: $3,000,000.00
  • Statewide: Various Culvert Rehabilitations/Replacements -2017
    • Estimated Letting Year: 2017
    • Approved Construction Amount: $3,000,000.00
  • Statewide: Various Culvert Rehabilitations/Replacements -2018
    • Estimated Letting Year: 2018
    • Approved Construction Amount: $3,000,000.00
  • Statewide: Various Culvert Rehabilitations/Replacements - 2019
    • Estimated Letting Year: 2019
    • Approved Construction Amount: $3,000,000.00
  • Statewide: Flood Mitigation and Drainage Improvements
    • Estimated Letting Year: 2018
    • Approved Construction Amount: $.00
  • Statewide: Miscellaneous Pavement Repairs at Various Locations
    • Estimated Letting Year: 2017
    • Approved Construction Amount: $.00
  • Statewide: Miscellaneous Pavement Repairs at Various Locations
    • Estimated Letting Year: 2019
    • Approved Construction Amount: $.00
  • Berkshire Thruway MP 805.7 to MP 815.0 and MP 818.2 to MP 824.3 and MP 814.25 Rock Removal
  • Slope Stabilization from MP 184.5 to MP 184.7 WB, west of Fonda (Exit 28)
  • Niagara Thruway (I-190), East of South Ogden Street (MP 900.0) to Tonawanda (Exit 17, MP 914.2) Various Interchanges: Pavement Resurfacing
  • Ripley Toll Barrier (MP 494.51): Concrete Pavement Restoration/ Resurfacing
    • Estimated Letting Year: 2016
    • Approved Construction Amount: $2,000,000.00
  • Northway (Exit 24, MP 148.1) to West of Schenectady (Exit 25, MP 154.4): Pavement Rehabilitation
  • West of Batavia (MP 393.7) to West of Pembroke (MP 404.7): Pavement Resurfacing
  • MP 419.69: Williamsville Toll Barrier - Operational Improvements
    • Estimated Letting Year: 2014
    • Approved Construction Amount: $7,000,000.00
  • Canandaigua (Exit 44, MP 347.1) to Rochester (Exit 45, MP 350.6): Concrete Pavement Restoration
  • Little Falls (Exit 29A, MP 210.3) to Herkimer (Exit 30, MP 220.0): Pavement Resurfacing
  • I-190 (Niagara Section), North of Church Street (Exit 7, MP N5.5) to Peace Bridge (Exit 9, MP N6.6): Pavement Resurfacing
  • I-190 (Niagara Section), East of South Ogden Street (MP N0.0) to South Street (Exit 6, MP N4.2):Pavement Resurfacing and Concrete Pavement Restoration
  • West of Pembroke (MP 404.7) to Depew (Exit 49, MP 416.9): Pavement Resurfacing
  • MP 421.57: Buffalo Airport Route 33 EB ( Exit 51): Lengthen Eastbound Merge Lane
  • Angola Interchange (Exit 57A, MP 444.87): Ramp Pavement Rehabilitation and Angola Interchange Bridge Rehabilitation
  • I-95 (New England Thruway), Pelham Parkway (MP NE0.0, Exit 8B) to Port Chester (MP NE14.1, Exit 22): Concrete Pavement Restoration, including New Rochelle Toll Plaza Pavement Repairs and Kings Highway, Cross County Connection and Cedar Street Bridges Rehabilitations
  • Garden State Parkway Connector (MP GS0.00 - MP GS2.40): Pavement Resurfacing and Safety Upgrades
  • East of Silver Creek (MP 451.5) to Silver Creek (Exit 58, MP 455.2): Pavement Rehabilitation and MP 454.47 Thruway over Cattaraugus Creek Bridge Rehabilitaion
  • East of Rome (MP 240.0) to Verona (Exit 33, MP 252.2): Pavement Resurfacing and Safety Upgrades
  • New York Division: Pavement Safety Striping - 2015
    • Estimated Letting Year: 2014
    • Approved Construction Amount: $700,000.00
  • Albany Division: Pavement Safety Striping - 2015
    • Estimated Letting Year: 2014
    • Approved Construction Amount: $800,000.00
  • Syracuse Division: Pavement Safety Striping - 2015
    • Estimated Letting Year: 2014
    • Approved Construction Amount: $800,000.00
  • Buffalo Division: Pavement Safety Striping - 2015
    • Estimated Letting Year: 2014
    • Approved Construction Amount: $850,000.00
  • MP 187: Construct Rest Area with Amenities and Truck Parking west of Fultonville near Erie Canal Lock 13
  • East of Williamsville Toll Barrier and West Seneca to the vicinity of the Hamburg Interchange (Exit 57): Pavement Resurfacing
  • Major Deegan Expressway (MP 0.01) to Cross Westchester Expressway (Exit 8, MP 11.3): Pavement Resurfacing and Safety Upgrades
  • Berkshire Thruway, I-87 (Exit 21A, MP B0.0) to I-90 (Exit B1, MP B5.7): Pavement Resurfacing
  • Victor (Exit 45, MP 351.0) to I-390 (Exit 46, MP 362.3): Pavement Resurfacing with Resurfacing of Interchanges 45 and 46
  • MP 6.0: Ardsley Service Area - Pavement Rehabilitation
    • Estimated Letting Year: 2015
    • Approved Construction Amount: $1,500,000.00
  • New York Division Culvert Repairs
    • Estimated Letting Year: 2014
    • Approved Construction Amount: $3,200,000.00
  • Schenectady (Exit 25, MP 154.4) to Rotterdam (Exit 26, MP 163.3): Pavement Resurfacing with Resurfacing of Exit 25A Tandem Lot
  • South of Harriman (Exit 16) to North of Woodbury Toll Barrier: Pavement Resurfacing
  • Rock Slope Projects Statewide - 2013
    • Estimated Letting Year: NA
    • Approved Construction Amount: $.00
  • Buffalo Division: Pavement Safety Striping, MP 452.34 to MP 455.06 - 2013
  • Waterloo (Exit 41, MP 320.70) to Geneva (Exit 42, MP 327.54): Pavement Resurfacing
  • Rotterdam (Exit 26, MP 163.3) to East of Amsterdam (MP 170.0): Pavement Resurfacing including the Pattersonville Service Area
  • South of Saugerties (MP 100.8) to North of Saugerties (MP 109.3): Pavement Resurfacing with Resurfacing of Malden Service Area
  • New Paltz (Exit 18, MP 76.5) to South of Kingston (MP 86.8): Pavement Resurfacing
  • I-287 (MP 11.00) to Tappan Zee Bridge Toll Barrier (MP 13.0): Pavement Resurfacing
  • New York Division: Pavement Safety Striping - 2017
    • Estimated Letting Year: 2016
    • Approved Construction Amount: $850,000.00
  • Albany Division: Pavement Safety Striping - 2017
    • Estimated Letting Year: 2016
    • Approved Construction Amount: $850,000.00
  • Syracuse Division: Pavement Safety Striping - 2017
    • Estimated Letting Year: 2016
    • Approved Construction Amount: $850,000.00
  • Buffalo Division: Pavement Safety Striping - 2017
    • Estimated Letting Year: 2016
    • Approved Construction Amount: $900,000.00
  • New York Division: Pavement Safety Striping - 2016
    • Estimated Letting Year: 2015
    • Approved Construction Amount: $700,000.00
  • Albany Division: Pavement Safety Striping - 2016
    • Estimated Letting Year: 2015
    • Approved Construction Amount: $850,000.00
  • Syracuse Division: Pavement Safety Striping - 2016
    • Estimated Letting Year: 2015
    • Approved Construction Amount: $850,000.00
  • Buffalo Division: Pavement Safety Striping - 2016
    • Estimated Letting Year: 2015
    • Approved Construction Amount: $900,000.00
  • Woodbury Toll Barrier (MP 46.0) to Newburgh (Exit17, MP 60.1): Pavement Resurfacing
  • North of Garden State Parkway Connector (MP 24.0) to North of Airmont Road (MP 29.4): Pavement Resurfacing
  • North of Sloatsburg (MP 38.7) to South of Harriman (MP 43.0): Pavement Resurfacing
  • East of Amsterdam (MP 170.0) to East of Fultonville (MP 180.0): Pavement Resurfacing
  • North of Kingston (MP 93.8) to South of Saugerties (MP 100.8): Pavement Resurfacing
  • Buffalo Division Culvert Repairs
    • Estimated Letting Year: 2015
    • Approved Construction Amount: $3,000,000.00
  • Taconic State Parkway (Exit B-2, MP BS15.0) to east of Canaan Toll Barrier (MP BS18.2): Pavement Resurfacing, and Canaan Toll Barrier Pavement Rehab
  • West of Utica (MP 233.5) to east of Westmoreland (MP 240.9): Pavement Resurfacing
  • West of Canastota (MP 268.0) to West of Syracuse (MP 279.3): Pavement Resurfacing
  • Herkimer (Exit 30, MP 220.0) to West of Utica (MP 233.5): Pavement Resurfacing
  • Weedsport (Exit 40, MP 304.5) to East of Waterloo (MP 313.8): Pavement Resurfacing
  • Lackawanna Toll Barrier (MP 430.51) to West of Hamburg (MP 438.4): Pavement Resurfacing
  • Tonawanda Toll Barrier (MP N14.90) to Niagara Toll Barrier (MP N20.22): Pavement Resurfacing with Resurfacing of Interchanges
  • Westfield (Exit 60, MP 485.0) to Pennsylvania State Line (MP 496.0) Westbound: Pavement Resurfacing
  • East of Silver Creek (MP 455.2) to Dunkirk (Exit 59, MP 467.2): Pavement Resurfacing and Interchange 58 Resurfacing
  • Northway (Exit 24, MP 148.15) & Schenectady (Exit 25, MP 153.83) - Interchange Rehabilitations with Capacity Improvements
  • Interchange 23 (Albany/I-787, MP 141.92): Pavement Rehabilitation
  • North of Catskill (MP 115.6 to MP 116.0 SB and MP 115.3 to MP 116.0 NB): Rock Removal
  • New Facilities for All Electronic Toll Collection at Yonkers (MP 5.47) and Harriman (MP 45.2) Toll Barriers
    • Estimated Letting Year: 2014
    • Approved Construction Amount: $26,000,000.00
  • MP 418.33 WB, MP N0.35 NB, MP N6.2 NB and MP N11.87 NB: Replacement of Four Outdated Dynamic Message Signs in Buffalo Division
    • Estimated Letting Year: 2014
    • Approved Construction Amount: $2,000,000.00
  • Replacement and New Installation of ITS Equipment in New York Division
    • Estimated Letting Year: 2019
    • Approved Construction Amount: $.00
  • Replacement and New Installation of ITS Equipment in Albany Division
    • Estimated Letting Year: 2017
    • Approved Construction Amount: $.00
  • Replacement and New Installation of ITS Equipment in Syracuse Division
    • Estimated Letting Year: 2018
    • Approved Construction Amount: $.00
  • Fort Edward to Fort Ann: Canalway Trail, Washington County (funded with 2005 Transportation Bond Act funds)
    • Estimated Letting Year: 2015
    • Approved Construction Amount: $4,410,000.00
  • Amherst to Lockport Canalway Trail with Trail Repairs at Amherst
    • Estimated Letting Year: 2014
    • Approved Construction Amount: $5,000,000.00
  • MP 141.92: New York State Transportation Resource Center
    • Estimated Letting Year: NA
    • Approved Construction Amount: $.00

Go to Top | Bottom

Under Construction Projects

  • MP 45.03: Repair Deteriorating Utility Tunnels at Woodbury Toll Barrier in New York Division
    • Letting Date: 11/06/2013
    • Estimated Completion Year: 2014
    • Low Bid Amount: $512,928.00
    • Contract Number: TANY 13-59A/D214265
    • Contractor: Jorrey Excavating, Inc.
  • Construction of Wind Turbines at 5 Locations to Provide Energy to Buffalo Division Facilities
    • Letting Date: 01/16/2013
    • Estimated Completion Year: 2014
    • Low Bid Amount: $7,875,000.00
    • Contract Number: TAB 12-37A/D214167
    • Contractor: Kandey Co., Inc.
  • Installation of Authority supplied Generators at Indian Castle Service Area
    • Letting Date: 10/23/2013
    • Estimated Completion Year: 2014
    • Low Bid Amount: $215,212.00
    • Contract Number: TAS 13-62A/D214270
    • Contractor: Power Line Constructors, Inc.
    • View Project on Map
  • Installation of Authority supplied Generator at Chittenango Service Area
    • Letting Date: 10/23/2013
    • Estimated Completion Year: 2014
    • Low Bid Amount: $214,445.00
    • Contract Number: TAS 13-63A/D214271
    • Contractor: Power Line Constructors, Inc.
    • View Project on Map
  • Installation of Authority supplied Generator at Clifton Springs Service Area
    • Letting Date: 10/23/2013
    • Estimated Completion Year: 2014
    • Low Bid Amount: $261,348.00
    • Contract Number: TAS 13-64A/D214272
    • Contractor: O'Connell Electric Company
    • View Project on Map
  • Sloatsburg Service Area (MP 33.0) and Modena Service Area (MP 66.0): Replacement of Deteriorated Roofs
    • Letting Date: 12/18/2013
    • Estimated Completion Year: 2014
    • Low Bid Amount: $1,131,200.00
    • Contract Number: TANY 13-60A/D214266
    • Contractor: A to Z Coatings, Inc.
    • View Project on Map
  • MP's 227 WB and MP 280 EB: Replacement of Deteriorated Pitched Roofs at the Schuyler and DeWitt Service Areas
    • Letting Date: 05/14/2014
    • Estimated Completion Year: 2014
    • Low Bid Amount: $962,000.00
    • Contract Number: TAS 14-16A/D214303
    • Contractor: New Britan Roofing Co., Inc.
  • MP's 292 WB and 310 EB: Replacement of Deteriorated Pitched Roofs at the Warners and Port Byron Service Areas
    • Letting Date: 05/14/2014
    • Estimated Completion Year: 2014
    • Low Bid Amount: $821,000.00
    • Contract Number: TAS 14-17A/D214304
    • Contractor: New Britan Roofing Co., Inc.
  • MP 210.0: Iroquois Service Area - Rehabilitate/Replace Aging Water System
    • Letting Date: 03/19/2014
    • Estimated Completion Year: 2015
    • Low Bid Amount: $979,500.00
    • Contract Number: TAS 14-3A/D214253
    • Contractor: W.M. Schultz Construction Inc.
    • View Project on Map
  • 4 Bridge Rehabilitations - MP 458.5 and MP 458.81 - Thruway Bridges over Silver Creek and MP 459.9 and MP 459.91 Thruway Bridges over Walnut Creek
    • Letting Date: 10/16/2013
    • Estimated Completion Year: 2015
    • Low Bid Amount: $15,649,366.11
    • Contract Number: TAB 13-41B/D214237
    • Contractor: Cold Spring Construction Company
    • View Project on Map
  • MP 173.59: Amsterdam Interchange (Exit 27) Bridge over Thruway - Replacement
    • Letting Date: 02/27/2013
    • Estimated Completion Year: 2014
    • Low Bid Amount: $7,127,781.00
    • Contract Number: TAA 13-21B/D214025
    • Contractor: Bette & Cring, LLC.
    • View Project on Map
  • MP 921.12: North Grand Island Bridge Southbound - Deck Replacement
    • Letting Date: 07/03/2013
    • Estimated Completion Year: 2015
    • Low Bid Amount: $55,360,128.45
    • Contract Number: TAN 13-10B/D214198
    • Contractor: Cianbro Corporation
    • View Project on Map
  • MP 337.53: Thruway Bridge (Westbound) over Canandaigua Outlet - Replacement
    • Letting Date: 12/18/2013
    • Estimated Completion Year: 2014
    • Low Bid Amount: $4,059,188.05
    • Contract Number: TAS 13-43B/D214238
    • Contractor: Cold Spring Construction Company
    • View Project on Map
  • Syracuse Division: Concrete Repairs to 3 Major Culverts
    • Letting Date: 11/27/2013
    • Estimated Completion Year: 2014
    • Low Bid Amount: $756,396.00
    • Contract Number: TAS 13-57B/D214263
    • Contractor: Economy Paving Co., Inc.
    • View Project on Map
  • Buffalo Division: On-Demand Repair Contract - 2013-2014
    • Letting Date: 03/20/2013
    • Estimated Completion Year: 2015
    • Low Bid Amount: $1,985,600.00
    • Contract Number: TAB 13-20B/D214214
    • Contractor: C.P. Ward, Inc.
  • MP 901.56 to MP 906.92: Replace Non-Functional Joints on 12 I-190 (Niagara Thruway) Bridges and Substructure and Bearing Repairs to 6 I-190 Bridges in Buffalo Division
    • Letting Date: 05/29/2013
    • Estimated Completion Year: 2014
    • Low Bid Amount: $6,323,201.80
    • Contract Number: TAN 13-37B/D214140
    • Contractor: Oakgrove Construction, Inc.
    • View Project on Map
  • I-95 (New England Thruway) Bridge Maintenance Cleaning for Steel Preservation - 2014
    • Letting Date: 12/04/2013
    • Estimated Completion Year: 2014
    • Low Bid Amount: $591,000.00
    • Contract Number: TANE 13-55B/D214261
    • Contractor: Dandrow's Painting, Inc.
  • South Grand Island Bridges: Maintenance Cleaning for Steel Preservation - 2014
    • Letting Date: 02/05/2014
    • Estimated Completion Year: 2014
    • Low Bid Amount: $172,271.00
    • Contract Number: TAN 14-9B/D214286
    • Contractor: Union Concrete and Construction Corporation
    • View Project on Map
  • MP 276.58: I-481/Collamer Interchange (Exit 34A) Bridge - Rehabilitation
    • Letting Date: 11/20/2013
    • Estimated Completion Year: 2014
    • Low Bid Amount: $320,866.40
    • Contract Number: TAS 13-71B/D214268
    • Contractor: Economy Paving Co., Inc.
    • View Project on Map
  • MP 53.10: Pleasant Hill Road Bridge over Thruway - Rehabilitation
    • Letting Date: 04/02/2014
    • Estimated Completion Year: 2014
    • Low Bid Amount: $1,727,000.00
    • Contract Number: TANY 14-6B/D214289
    • Contractor: HVB Construction, Inc.
    • View Project on Map
  • New York Division: On-Demand Repair Contract for Damaged and Flagged Bridges - 2012-2013
    • Letting Date: 02/22/2012
    • Estimated Completion Year: 2014
    • Low Bid Amount: $562,000.00
    • Contract Number: TANY 12-5B/D214123
    • Contractor: E. Daskal Corporation
  • MP 455.54 & MP 460.74 & MP 467.74: Silver Creek Interchange, Fredonia-Silver Creek Rd (Route 20) and Dunkirk-Fredonia Interchange - Bridge Rehabilitations
    • Letting Date: 10/30/2013
    • Estimated Completion Year: 2014
    • Low Bid Amount: $3,569,275.50
    • Contract Number: TAB 13-14B/D214207
    • Contractor: Oakgrove Construction, Inc.
    • View Project on Map
  • MP N14.99: South Grand Island Bridge Southbound - Deck Rehabilitation, Miscellaneous Bridge Repairs and 2013 North Grand Island Bridge Washing
    • Letting Date: 03/28/2012
    • Estimated Completion Year: 2013
    • Low Bid Amount: $13,764,051.50
    • Contract Number: TAN 12-16B/D214067
    • Contractor: Union Concrete & Construction Corporation
    • View Project on Map
  • New York Division: On-Demand Repair Contract - 2014-2015
    • Letting Date: 11/13/2013
    • Estimated Completion Year: 2015
    • Low Bid Amount: $1,947,000.00
    • Contract Number: TANY 13-53B/D214259
    • Contractor: E. Daskal Corporation.
  • Albany Division: On-Demand Repair Contract - 2014-2015
    • Letting Date: 10/30/2013
    • Estimated Completion Year: 2015
    • Low Bid Amount: $1,945,000.00
    • Contract Number: TAA 13-40B/D214235
    • Contractor: D.A. Collins Construction Co., Inc.
  • Syracuse Division: On-Demand Repair Contract - 2014-2015
    • Letting Date: 11/13/2013
    • Estimated Completion Year: 2015
    • Low Bid Amount: $1,932,000.00
    • Contract Number: TAS 13-56B/D214262
    • Contractor: Slate Hill Constructors, Inc.
  • MP 111.13 & 113.22: Thruway Bridges over Kaaterskill Creek and Catskill Creek: Railing/Fascia Repairs
    • Letting Date: 09/25/2013
    • Estimated Completion Year: 2014
    • Low Bid Amount: $2,056,000.00
    • Contract Number: TAA 13-45B/D214242
    • Contractor: Reale Construction Co., Inc.
    • View Project on Map
  • MP BS0.00: Exit 21A Ramp Bridge Over Thruway and MP BS0.10: Berkshire Thruway Bridge over CSX RR - Deck Rehabilitations, and Joint Replacements/Substructure Repairs to 17 Other Bridges
    • Letting Date: 10/16/2013
    • Estimated Completion Year: 2014
    • Low Bid Amount: $6,290,783.00
    • Contract Number: TAA 13-69B/D214280
    • Contractor: Bette & Cring, LLC
  • Repair/Rehabilitate 4 Large Culverts on the Mainline and Berkshire Spur in Albany Division
    • Letting Date: 03/12/2014
    • Estimated Completion Year: 2014
    • Low Bid Amount: $836,692.27
    • Contract Number: TAA 14-7B/D214293
    • Contractor: Prime Highway Contractors, LLC.
  • Lysander: Section 5 Office and Shop - Roof and Insulation Repairs, Onondaga County
    • Letting Date: 12/02/2009
    • Estimated Completion Year: 2011
    • Low Bid Amount: $1,788,143.00
    • Contract Number: TAS 09-56C/D213910
    • Contractor: Contracting Management, Inc.
    • View Project on Map
  • Lysander: Canal Section 5 Office & Shop - Roof Replacement, Onondaga County
    • Letting Date: 07/10/2013
    • Estimated Completion Year: 2014
    • Low Bid Amount: $1,297,900.00
    • Contract Number: TAS 13-42C/D214236
    • Contractor: E.L. Ames, Inc. dba R.J. Ortlieb Construction
    • View Project on Map
  • Crescent: Guard Gates 1 & 2 and Crocker's Reef: Guard Gate - Replace Cables and Rollers, Saratoga, Washington Counties
    • Letting Date: 11/14/2012
    • Estimated Completion Year: 2014
    • Low Bid Amount: $4,885,308.45
    • Contract Number: TAA 12-34C/D214162
    • Contractor: D.A. Collins Construction Co., Inc.
  • Utica: Taintor Gate and Dam - Rehabilitation, Oneida County
    • Letting Date: 11/28/2012
    • Estimated Completion Year: 2016
    • Low Bid Amount: $9,635,661.70
    • Contract Number: TAS 12-35C/D214068
    • Contractor: Tioga Construction Co., Inc.
    • View Project on Map
  • Statewide: Canal On-Demand Repair and Vessel Recovery Contract
    • Letting Date: 11/21/2012
    • Estimated Completion Year: 2014
    • Low Bid Amount: $1,674,560.00
    • Contract Number: TA 12-22C/D214161
    • Contractor: Tioga Construction Co., Inc.
  • Fairport: Spillway Wall - Rehabilitation, Monroe County
    • Letting Date: 09/18/2013
    • Estimated Completion Year: 2014
    • Low Bid Amount: $2,715,930.80
    • Contract Number: TAB 13-46C/D214243
    • Contractor: Keeler Construction Co., Inc.
    • View Project on Map
  • Amsterdam: Movable Dam 7 at Lock E-11 - Rehabilitation, Montgomery County
    • Letting Date: 11/13/2013
    • Estimated Completion Year: 2017
    • Low Bid Amount: $21,464,462.00
    • Contract Number: TAA 13-50C/D214251
    • Contractor: D.A.Collins Construction Co., Inc.
    • View Project on Map
  • Yosts: Movable Dam 9 at Lock E-13 - Rehabilitation, Montgomery County
    • Letting Date: 09/15/2010
    • Estimated Completion Year: 2014
    • Low Bid Amount: $15,514,331.25
    • Contract Number: TAA 10-2C/D213874
    • Contractor: Tioga Construction Co., Inc.
    • View Project on Map
  • Crescent: Dredge Erie Canal in the Area of Lock E-6, Saratoga Cty (Tropical Storms Irene & Lee Recovery Project - Partial FEMA Reimbursable)
    • Letting Date: 09/25/2013
    • Estimated Completion Year: 2014
    • Low Bid Amount: $1,416,647.50
    • Contract Number: TAA 13-17C/D214212
    • Contractor: Tioga Construction Co., Inc.
    • View Project on Map
  • Cranesville: Spillway and Sitework at Lock E-10, Montgomery County (Tropical Storms Irene and Lee Recovery Project - Partial FEMA Eligible)
    • Letting Date: 04/03/2013
    • Estimated Completion Year: 2014
    • Low Bid Amount: $5,198,000.00
    • Contract Number: TAA 13-11C/D214202
    • Contractor: James H. Maloy, Inc.
    • View Project on Map
  • Scotia & Rotterdam: Spillway & Sitework at Locks E-8 & E-9, Schenectady Cty (Tropical Storms Irene & Lee Recovery Project - Partial FEMA Eligible)
    • Letting Date: 05/15/2013
    • Estimated Completion Year: 2014
    • Low Bid Amount: $9,569,569.56
    • Contract Number: TAA 13-12C/D214204
    • Contractor: Harrison & Burrowes Bridge Constructors, Inc.
  • Amsterdam: Sitework at Lock E-11, Montgomery County (Tropical Storms Irene and Lee Recovery Project - Partial FEMA Eligible)
    • Letting Date: 02/20/2013
    • Estimated Completion Year: 2014
    • Low Bid Amount: $1,935,847.50
    • Contract Number: TAA 13-6C/D214192
    • Contractor: W.M. Schultz Construction, Inc.
    • View Project on Map
  • Tribes Hill: Approach Wall Repair/Replacement at Lock E-12, Montgomery Cty (Tropical Storms Irene & Lee Recovery Project - Partial FEMA Eligible)
    • Letting Date: 09/11/2013
    • Estimated Completion Year: 2015
    • Low Bid Amount: $8,105,564.20
    • Contract Number: TAA 13-34C/D214228
    • Contractor: D.A. Collins Construction
    • View Project on Map
  • Upright & Lighting Repairs to MD 5, 6 & 7 at Locks E-9,10 & 11, Schenectady & Montgomery Co. (Tropical Storm Recovery Project - Partial FEMA Eligible)
    • Letting Date: 06/27/2012
    • Estimated Completion Year: 2015
    • Low Bid Amount: $7,173,649.60
    • Contract Number: TAA 12-11C/D214138
    • Contractor: C.D. Perry LLC
    • View Project on Map
  • Upright & Lighting Repairs to MD 4, 8, 10 & 11, Schenectady & Montgomery Counties (Tropical Storm Recovery Project - Partial FEMA Eligible)
    • Letting Date: 06/27/2012
    • Estimated Completion Year: 2015
    • Low Bid Amount: $7,413,203.66
    • Contract Number: TAA 12-12C/D214139
    • Contractor: C.D. Perry LLC
  • Albany Division: Mule Rehabilitation at Movable Dams 4 - 11 at Lock E-8 - E-15, Schenectady & Montgomery Cty (Tropical Storm Recovery - Partial FEMA)
    • Letting Date: 04/24/2013
    • Estimated Completion Year: 2016
    • Low Bid Amount: $5,719,200.00
    • Contract Number: TAA 13-9C/D214146
    • Contractor: C.D. Perry, LLC
  • Tribes Hill & Fort Plain: Truss Repairs at Movable Dams 8 & 11 at Locks E-12 & E15 and Painting at Movable Dam 11 at Lock E-15, Montgomery County
    • Letting Date: 08/21/2013
    • Estimated Completion Year: 2014
    • Low Bid Amount: $7,272,843.00
    • Contract Number: TAA 13-36C/D214229
    • Contractor: Piasecki Steel Construction Corp.
  • Eastern Division: Scour Repairs at Locks E-9, E-10 and E-12
    • Letting Date: 02/19/2014
    • Estimated Completion Year: 2014
    • Low Bid Amount: $850,127.20
    • Contract Number: TAA 14-13C/D214300
    • Contractor: C.D. Perry LLC
  • LeRoy (Exit 47, MP 378.2) to west of Batavia (MP 393.7): Pavement Resurfacing
    • Letting Date: 06/12/2013
    • Estimated Completion Year: 2014
    • Low Bid Amount: $15,417,234.75
    • Contract Number: TAB 13-27/D214220
    • Contractor: Suit-Kote Corporation
    • View Project on Map
  • LeRoy (Exit 47, MP 378.2) to west of Batavia (MP 393.7): Safety Upgrades
    • Letting Date: 10/09/2013
    • Estimated Completion Year: 2014
    • Low Bid Amount: $2,195,830.50
    • Contract Number: TAB 13-49/D214248
    • Contractor: Keeler Construction Co., Inc
    • View Project on Map
  • South of I-190 (MP 425.8) to West Seneca/East Aurora (Exit 54, MP 427.7): Concrete Pavement Restoration
    • Letting Date: 04/10/2013
    • Estimated Completion Year: 2013
    • Low Bid Amount: $6,904,696.60
    • Contract Number: TAB 13-16/D214107
    • Contractor: Union Concrete and Construction
    • View Project on Map
  • Verona (Exit 33, MP 252.2) to Canastota (Exit 34, MP 262.0): Pavement Resurfacing and Safety Upgrades
    • Letting Date: 12/18/2013
    • Estimated Completion Year: 2014
    • Low Bid Amount: $8,627,688.80
    • Contract Number: TAS 13-48/D214247
    • Contractor: Hanson Aggregates New York, LLC.
    • View Project on Map
  • Electronics Parkway (Exit 37, MP 284.0) to I-690 (Exit 39, MP 289.3), Including Interchange 38: Safety Upgrades
    • Letting Date: 10/02/2013
    • Estimated Completion Year: 2014
    • Low Bid Amount: $1,371,895.75
    • Contract Number: TAS 13-19/D214145
    • Contractor: Villager Construction, Inc.
    • View Project on Map
  • I-95 Northbound (New England Thruway), Bartow Avenue (Exit 11, MP NE1.11): Ramp and Safety Upgrades
    • Letting Date: 10/23/2013
    • Estimated Completion Year: 2014
    • Low Bid Amount: $3,398,838.00
    • Contract Number: TANE 13-44/D213711
    • Contractor: Beaver Concrete Construction Co., Inc.
    • View Project on Map
  • MP 308: Construct Rest Area west of Weedsport near the Old Erie Canal Port Byron Lock (Lock 52)
    • Letting Date: 04/30/2014
    • Estimated Completion Year: 2014
    • Low Bid Amount: $3,246,546.65
    • Contract Number: TAS 14-11/D214246
    • Contractor: Cold Spring Construction Company
    • View Project on Map
  • New York Division Culverts: Remove Sediment, Restore Capacity and Inspect for Needed Repairs
    • Letting Date: 06/12/2013
    • Estimated Completion Year: 2013
    • Low Bid Amount: $163,493.25
    • Contract Number: TANY 13-39/D214074
    • Contractor: Bricco Plumbing & HVAC, Inc.
  • I-287/Route 17S (Exit 15) to North of Suffern (Exit 15A): Pavement Resurfacing, Exits 15/15A Ramp Concrete Pavement Restoration and 2 Bridge Rehabilitations at MP 31.78 and MP 31.79
    • Letting Date: 12/04/2013
    • Estimated Completion Year: 2015
    • Low Bid Amount: $28,762,000.00
    • Contract Number: TANY 13-51/D214240
    • Contractor: Ecco III Enterprises, Inc.
    • View Project on Map
  • West of Canajoharie (Exit 29, MP 197.9) to Little Falls (Exit 29A, MP 210.3): Pavement Resurfacing
    • Letting Date: 12/12/2012
    • Estimated Completion Year: 2013
    • Low Bid Amount: $10,086,659.67
    • Contract Number: TAS 12-3/D214110
    • Contractor: Kubricky Construction Corp.
    • View Project on Map
  • I-90, West of Pembroke (MP 404.7) to West of William Street (MP 425.9) and I-190, North of Church Street (MP N5.5) to Peace Bridge: Safety Upgrades
    • Letting Date: 05/22/2013
    • Estimated Completion Year: 2014
    • Low Bid Amount: $4,655,454.90
    • Contract Number: TAB 13-25/D214219
    • Contractor: Keeler Construction Co., Inc.
  • Syracuse Division Culvert Repairs
    • Letting Date: 09/04/2013
    • Estimated Completion Year: 2014
    • Low Bid Amount: $3,995,105.20
    • Contract Number: TAS 13-15/D214209
    • Contractor: Slate Hill Constructors, Inc.
  • New York Division: Pavement Safety Striping - 2014
    • Letting Date: 12/11/2013
    • Estimated Completion Year: 2014
    • Low Bid Amount: $399,294.27
    • Contract Number: TANY 13-65/D214273
    • Contractor: Safety Marketing, Inc.
  • Albany Division: Pavement Safety Striping - 2014
    • Letting Date: 12/11/2013
    • Estimated Completion Year: 2014
    • Low Bid Amount: $512,034.51
    • Contract Number: TAA 13-66/D214274
    • Contractor: .Straight Line Industries, Inc.
  • Syracuse Division: Pavement Safety Striping - 2014
    • Letting Date: 12/11/2013
    • Estimated Completion Year: 2014
    • Low Bid Amount: $324,727.85
    • Contract Number: TAS 13-67/D214275
    • Contractor: Accent Stripe, Inc.
  • Buffalo Division: Pavement Safety Striping - 2014
    • Letting Date: 12/11/2013
    • Estimated Completion Year: 2014
    • Low Bid Amount: $795,218.32
    • Contract Number: TAB 13-68/D214276
    • Contractor: Accent Stripe, Inc.
  • South of Nyack (MP 16.00) to North of Garden State Parkway Connector (MP 24.00): Pavement Rehabilitation and Resurfacing
    • Letting Date: 05/21/2014
    • Estimated Completion Year: 2015
    • Low Bid Amount: $16,170,507.38
    • Contract Number: TANY 14-27/D214324
    • Contractor: Tilcon New York, Inc.
    • View Project on Map
  • North of Newburgh (MP 62.0 NB, MP 68.0 SB) to south of New Paltz (MP 74.5): Pavement Rehabilitation
    • Letting Date: 05/08/2013
    • Estimated Completion Year: 2014
    • Low Bid Amount: $28,938,888.28
    • Contract Number: TANY 13-18/D214213
    • Contractor: Tetra Tech Construction, Inc.
    • View Project on Map
  • Dunkirk (Exit 59, MP 467.0) to Westfield (Exit 60, MP 485.5) and Exit 59: Pavement Resurfacing
    • Letting Date: 03/06/2013
    • Estimated Completion Year: 2014
    • Low Bid Amount: $16,388,664.00
    • Contract Number: TAB 13-32/D214131
    • Contractor: Oakgrove Construction Co., Inc.
    • View Project on Map
  • Replacement of Three Outdated Dynamic Message Signs, Closed Circuit Cameras and other ITS Equipment in New York Division
    • Letting Date: 04/16/2014
    • Estimated Completion Year: 2015
    • Low Bid Amount: $3,066,173.26
    • Contract Number: TANY 14-8I/D214284
    • Contractor: Power Line Constructors, Inc.
  • Amsterdam: Mohawk Valley Gateway Overlook - New Construction, Montgomery County (funded with 2005 Transportation Bond Act funds)
    • Letting Date: 11/06/2013
    • Estimated Completion Year: 2016
    • Low Bid Amount: $14,627,943.64
    • Contract Number: TAA 13-33C/D214226
    • Contractor: Kubricky Construction Corporation
  • Lockport: Rehabilitation of Historic Locks E-69 and E-70 at Flight of Five, Niagara County
    • Letting Date: 07/10/2013
    • Estimated Completion Year: 2014
    • Low Bid Amount: $1,742,444.86
    • Contract Number: TAB 13-26C/D214201
    • Contractor: Hohl Industrial Services, Inc.
  • Gryziec Park to Stanwix: Canalway Trail, Oneida County (funded with 2005 Transportation Bond Act funds)
    • Letting Date: 11/27/2013
    • Estimated Completion Year: 2014
    • Low Bid Amount: $1,753,031.90
    • Contract Number: TAS 13-23C/D214217
    • Contractor: Slate Hill Constructors, Inc.
  • Pittsford to Fairport: Canalway Trail - Rehabilitation, Monroe County (funded with 2005 Transportation Bond Act funds)
    • Letting Date: 06/26/2013
    • Estimated Completion Year: 2014
    • Low Bid Amount: $2,146,448.83
    • Contract Number: TAB 13-2C/D214186
    • Contractor: Ramsey Constructors, Inc.

Go to Top | Bottom

Completed Projects

  • Plattekill Service Area: Rehabilitate/Replace Water Treatment Equipment (Pumphouse and Water Storage Tank)
    • Letting Date: 12/19/2007
    • Completion Date: 08/22/2008
    • Construction Amount: $419,015.33
    • Contract Number: TANY 07-18AR/D213467
    • Contractor: Roehrs Construction, Inc.
    • View Project on Map
  • MP 168.0: Pattersonville Service Area - Rehabilitation of Water and Wastewater Treatment Systems
    • Letting Date: 12/13/2006
    • Completion Date: 03/31/2008
    • Construction Amount: $849,469.07
    • Contract Number: TAA 06-57A/D213612
    • Contractor: Blue Heron Construction Co., LLC
  • Little Falls (Exit 29A, MP 210.6): Construct New Hi-Arch Salt Storage Building
    • Letting Date: 05/03/2006
    • Completion Date: 09/21/2007
    • Construction Amount: $1,567,569.50
    • Contract Number: TAS 06-5A/D213518
    • Contractor: Park Lane Construction & Development Corporation
  • MP 423.19: Walden Avenue Maintenance Building - Install New Overhead Doors
    • Letting Date: 10/26/2005
    • Completion Date: 10/19/2006
    • Construction Amount: $170,561.80
    • Contract Number: TAB 05-29A/D213335
    • Contractor: Miller Enterprises, Inc.
  • MP 423.19: Walden Avenue Maintenance Building - Replace Heating System
    • Letting Date: 01/25/2006
    • Completion Date: 08/31/2006
    • Construction Amount: $342,279.70
    • Contract Number: TAB 05-25AR/D213336
    • Contractor: Hoot Mechanical and Electrical Inc.
  • MP 96.00 and MP 127.00: Ulster and New Baltimore Service Areas - Waste Water Treatment Plant Rehabilitation
    • Letting Date: 12/13/2006
    • Completion Date: 07/31/2008
    • Construction Amount: $1,071,235.85
    • Contract Number: TAA 06-58A/D213613
    • Contractor: Blue Heron Construction Co., LLC
  • MP 421.5: Buffalo State Police Zone Headquarters - Construct New Building Adjacent to Existing Building
    • Letting Date: 12/16/2009
    • Completion Date: 07/16/2012
    • Construction Amount: $2,844,357.55
    • Contract Number: TAB 09-55A/D213754
    • Contractor: Pepe Construction Co., Inc.
  • Kingston, Catskill and Berkshire Maintenance Sections: Salt Shed Structural Rehabilitation and Roof Replacements
    • Letting Date: 04/04/2007
    • Completion Date: 10/03/2007
    • Construction Amount: $273,891.73
    • Contract Number: TAA 07-22A/D213673
    • Contractor: Gudabri, Inc.
  • MP 141.92: Central Sign Shop - Improve HVAC System
    • Letting Date: 09/14/2005
    • Completion Date: 07/14/2006
    • Construction Amount: $180,500.00
    • Contract Number: TAA 05-21A/D213509
    • Contractor: DiGesare Mechanical, Inc.
  • MP 279.5: Syracuse Section Maintenance Facility, Thompson Road Division Complex - Install Fire Alarm System
    • Letting Date: 12/12/2007
    • Completion Date: 01/06/2009
    • Construction Amount: $85,911.26
    • Contract Number: TAS 07-35A/D213707
    • Contractor: Life Safety Engineered Systems, Inc.
  • MP 279.5: Syracuse Section Maintenance Facility, Thompson Road Complex - Renovate HVAC System
    • Letting Date: 12/12/2007
    • Completion Date: 02/09/2010
    • Construction Amount: $1,797,473.52
    • Contract Number: TAS 07-36A/D213708
    • Contractor: J & K Plumbing and Heating Co., Inc.
  • I-84, East Fishkill (MP 54.96) and Stormville (MP 55.57) Rest Areas: Wastewater Treatment System - Rehabilitation
    • Letting Date: 02/13/2008
    • Completion Date: 08/21/2009
    • Construction Amount: $1,199,000.00
    • Contract Number: TANY 08-17A/D213697
    • Contractor: C.A Phillips Construction Corporation
  • MP 141.92: Thruway Building at 337 Southern Boulevard - Repair Exterior Concrete Walls and Loading Dock Roof, and Replace Windows
    • Letting Date: 12/15/2010
    • Completion Date: 12/20/2011
    • Construction Amount: $581,162.67
    • Contract Number: TAA 10-53A/D214000
    • Contractor: Rosch Brothers, Inc.
  • MP 266.00: Chittenango Service Area - Roof Replacement
    • Letting Date: 03/22/2006
    • Completion Date: 11/15/2006
    • Construction Amount: $440,622.74
    • Contract Number: TAS 06-6A/D213559
    • Contractor: Henderson-Johnson Company, Inc.
    • View Project on Map
  • MP 244.00: Oneida Service Area - Roof Replacement
    • Letting Date: 03/22/2006
    • Completion Date: 12/13/2006
    • Construction Amount: $465,929.58
    • Contract Number: TAS 06-7A/D213558
    • Contractor: Henderson-Johnson Company, Inc.
    • View Project on Map
  • Seneca Service Area: Roof Replacement
    • Letting Date: 12/14/2005
    • Completion Date: 06/28/2006
    • Construction Amount: $201,006.63
    • Contract Number: TAS 05-41A/D213546
    • Contractor: Henderson-Johnson Company, Inc.
    • View Project on Map
  • MP 430.51: Lackawanna Barrier Toll Utility Building - Sewer Connection Project
    • Letting Date: 10/26/2005
    • Completion Date: 05/12/2006
    • Construction Amount: $79,957.56
    • Contract Number: TAB 05-22A/D213534
    • Contractor: Milherst Construction, Inc.
    • View Project on Map
  • New Baltimore Service Area: Roof Replacement - Pitched Roof Area Only
    • Letting Date: 02/21/2007
    • Completion Date: 08/09/2007
    • Construction Amount: $240,058.00
    • Contract Number: TAA 07-12A/D213649
    • Contractor: WB Roofing & Sheetmetal, Inc.
  • Malden and New Baltimore Service Areas Roof Replacements - Flat Roof Areas Only
    • Letting Date: 11/14/2007
    • Completion Date: 12/04/2008
    • Construction Amount: $422,890.43
    • Contract Number: TAA 07-17A/D213671
    • Contractor: Everfoam Instulation Systems, Inc.
  • MP 96.0, MP 153.0, MP 168.0 and MP 172.0: Ulster, Guilderland, Pattersonville and Mohawk Service Areas - Flat Roof Replacements
    • Letting Date: 03/04/2009
    • Completion Date: 01/29/2010
    • Construction Amount: $704,767.23
    • Contract Number: TAA 09-4A/D213836
    • Contractor: Henderson-Johnson Company, Inc.
  • MP 162.2, MP 173.6 and MP 187.0: Salt Sheds - Complete Repairs and Replace Roofs
    • Letting Date: 01/28/2009
    • Completion Date: 10/23/2009
    • Construction Amount: $306,592.39
    • Contract Number: TAA 08-48A/D213820
    • Contractor: BCI Construction, Inc.
    • View Project on Map
  • MP 96.0: Ulster Service Area - Pitched Roof Replacement
    • Letting Date: 02/04/2009
    • Completion Date: 03/08/2010
    • Construction Amount: $111,100.00
    • Contract Number: TAA 09-3A/D213818
    • Contractor: Louis Guglielmetti dba Catskill Park Construction
    • View Project on Map
  • MP BS15.1: Berkshire Maintenance Section - Replace Salt Shed
    • Letting Date: 04/15/2009
    • Completion Date: 10/29/2009
    • Construction Amount: $702,981.00
    • Contract Number: TABS 09-2A/D213835
    • Contractor: Park Lane Construction & Development Corporation
  • MP 141.92: Install New Air Conditioning Unit for Main Computer Room at the Administrative Headquarters Building
    • Letting Date: 12/13/2006
    • Completion Date: 07/05/2007
    • Construction Amount: $64,998.55
    • Contract Number: TAA 06-59A/D213656
    • Contractor: General Mechanical Systems, Inc.
  • MP 141.92: 337 Southern Boulevard Data Center - Install New Air Conditioning System Unit
    • Letting Date: 07/25/2007
    • Completion Date: 02/29/2008
    • Construction Amount: $202,230.23
    • Contract Number: TAA 07-50A/D213733
    • Contractor: Family Danz Heating & Air Conditioning, Inc.
  • MP 365.7 and MP 447.1: Scottsville and Angola Service Areas - Emergency Generator Replacements and Upgrades
    • Letting Date: 03/24/2010
    • Completion Date: 12/31/2010
    • Construction Amount: $703,775.99
    • Contract Number: TAB 10-4A/D213830
    • Contractor: Power & Construction Group, Inc.
  • MP 141.92: Rehabilitation of the Administrative Headquarters Building Freight Elevator
    • Letting Date: 09/30/2009
    • Completion Date: 04/29/2010
    • Construction Amount: $236,488.91
    • Contract Number: TAA 09-32AR/D213872
    • Contractor: Downey-Goodlein Elevator Corporation
  • MP 141.92 : Administrative Headquarters Building - Modernization of Fire Alarm System
    • Letting Date: 03/11/2009
    • Completion Date: 07/09/2009
    • Construction Amount: $30,892.53
    • Contract Number: TAA 09-16A/D213840
    • Contractor: Life Safety Engineered Systems, Inc.
  • MP 304.2: Weedsport Maintenance Section Salt Storage Shed - Replacement
    • Letting Date: 12/16/2009
    • Completion Date: 09/23/2010
    • Construction Amount: $520,509.62
    • Contract Number: TAS 09-51A/D213912
    • Contractor: Guidabri, Inc.
    • View Project on Map
  • MP 18.8: Nyack Maintenance Garage - Replacement of Deteriorated Roof
    • Letting Date: 03/23/2011
    • Completion Date: 11/29/2011
    • Construction Amount: $1,076,698.75
    • Contract Number: TANY 11-16A/D214035
    • Contractor: NUA Construction Corporation
  • MP 103.0: Malden Service Area Remediation
    • Letting Date: 07/01/2009
    • Completion Date: 05/14/2010
    • Construction Amount: $1,295,134.10
    • Contract Number: TAA 09-20/D213859
    • Contractor: Op-Tech Environmental Services, Inc.
    • View Project on Map
  • MP 141.92: Central Sign Shop (Building M2347) - Roof Replacement
    • Letting Date: 11/04/2009
    • Completion Date: 05/05/2010
    • Construction Amount: $104,761.32
    • Contract Number: TAA 09-54A/D213891
    • Contractor: Best Roofing of New Jersey, Inc.
  • MP 210: Replacement of Deteriorated Flat Roof at the Indian Castle Service Area
    • Letting Date: 03/13/2013
    • Completion Date: 10/30/2013
    • Construction Amount: $387,740.00
    • Contract Number: TAS 13-1A/D214154
    • Contractor: Henderson-Johnson Co., Inc.
    • View Project on Map
  • MP 210: Replacement of Deteriorated Pitched Roof at the Indian Castle Service Area
    • Letting Date: 10/24/2012
    • Completion Date: 08/30/2013
    • Construction Amount: $357,811.00
    • Contract Number: TAS 12-7A/D214127
    • Contractor: Mid-State Industries, Ltd.
    • View Project on Map
  • MP 324W and MP 337E: Replacement of Deteriorated Pitched Roofs at the Junius Ponds and Clifton Springs Service Areas
    • Letting Date: 03/27/2013
    • Completion Date: 10/30/2013
    • Construction Amount: $703,950.28
    • Contract Number: TAS 13-28A/D214188
    • Contractor: S & L Roofing & Sheet Metal
  • MP 324W and MP 337E: Replacement of Deteriorated Flat Roofs at the Junius Ponds and Clifton Springs Service Areas
    • Letting Date: 06/12/2013
    • Completion Date: 11/30/2013
    • Construction Amount: $645,870.00
    • Contract Number: TAS 13-35A/D214189
    • Contractor: Henderson Johnson Co., Inc.
  • MP 447: Angola Service Area Restaurant - Replace Flat Roof
    • Letting Date: 06/23/2010
    • Completion Date: 10/29/2010
    • Construction Amount: $269,740.00
    • Contract Number: TAB 10-25A/D213950
    • Contractor: Henderson-Johnson Co., Inc.
    • View Project on Map
  • MP BS1.08: Castelton Bridge over Hudson River - Rehabilitation
    • Letting Date: 11/29/2006
    • Completion Date: 11/21/2008
    • Construction Amount: $30,805,004.52
    • Contract Number: TABS 06-54B/D213648
    • Contractor: D.A. Collins Construction Co., Inc.
    • View Project on Map
  • MP BS6.58 & BS6.59: Post Road (Exit B1) Bridges over Berkshire Thruway - Replacements
    • Letting Date: 07/09/2008
    • Completion Date: 11/20/2009
    • Construction Amount: $6,383,837.22
    • Contract Number: TABS 08-36B/D213745
    • Contractor: Kubricky Construction Corporation
    • View Project on Map
  • MP BS24.09: Route 102 Bridge over Berkshire Thruway - Replacement
    • Letting Date: 10/31/2007
    • Completion Date: 11/26/2008
    • Construction Amount: $6,380,594.67
    • Contract Number: TABS 07-56B/D213238
    • Contractor: Bette & Cring, LLC
  • MP 213.96 and MP 213.97: Thruway Bridges over Paines Hollow Road - Replacement
    • Letting Date: 11/23/2005
    • Completion Date: 11/08/2007
    • Construction Amount: $5,508,820.51
    • Contract Number: TAS 05-26B/D213397
    • Contractor: Bette & Cring, LLC
    • View Project on Map
  • MP NE5.76: North Avenue over I-95 Thruway - Construct New Bridge for Utilities
    • Letting Date: 01/30/2008
    • Completion Date: 05/13/2010
    • Construction Amount: $2,368,030.13
    • Contract Number: TANE 08-19B/D213705
    • Contractor: ELQ Industries, Inc.
    • View Project on Map
  • MP NE5.76: North Avenue Bridge over New England Thruway - Utilities Transfer (Phase 2)
    • Letting Date: 10/19/2011
    • Completion Date: 05/24/2013
    • Construction Amount: $5,283,843.95
    • Contract Number: TANE 11-24BR/D213904
    • Contractor: Perfetto Contracting Co., Inc.
    • View Project on Map
  • MP N14.35: South Grand Island Bridge (Northbound) Deck Replacement, and Substructure and Bearing Rehabilitation to the Northbound and Southbound Bridges
    • Letting Date: 07/23/2008
    • Completion Date: 02/18/2011
    • Construction Amount: $45,999,898.25
    • Contract Number: TAN 08-30B/D213701
    • Contractor: American Bridge Company
    • View Project on Map
  • MP 277.39: Fly Road Bridge over Thruway - Replacement
    • Letting Date: 11/30/2005
    • Completion Date: 11/17/2006
    • Construction Amount: $2,966,946.19
    • Contract Number: TAS 05-20B/D213026
    • Contractor: Economy Paving Co., Inc.
    • View Project on Map
  • MP GS40.38: Scotland Hill Road Bridge over the Garden State Parkway Connection - Rehabilitation
    • Letting Date: 02/14/2007
    • Completion Date: 11/16/2007
    • Construction Amount: $1,967,539.94
    • Contract Number: TAGS 07-3B/D213305
    • Contractor: Harrison & Burrowes Bridge Constructors, Inc.
    • View Project on Map
  • MP 34.03 and MP 34.04: Thruway Bridges over Sloatsburg-Sebago Lake Road and MP 36.13: East Village Road - Replacements and MP 36.14: East Village Road - Removal
    • Letting Date: 07/07/2010
    • Completion Date: 09/26/2013
    • Construction Amount: $30,320,787.63
    • Contract Number: TANY 10-19B/D213702
    • Contractor: A. Servidone, Inc.
    • View Project on Map
  • MP 283.04: Buckley Rd (CR 48) Bridge over Thruway - Replacement
    • Letting Date: 10/10/2007
    • Completion Date: 08/31/2009
    • Construction Amount: $5,848,766.72
    • Contract Number: TAS 07-54B/D213401
    • Contractor: Tioga Construction Co.,Inc.
    • View Project on Map
  • MP 286.36: Cold Spring-Liverpool (Route 370) Bridge over Thruway - Replacement
    • Letting Date: 07/08/2009
    • Completion Date: 11/02/2011
    • Construction Amount: $5,242,737.32
    • Contract Number: TAS 09-14B/D213800
    • Contractor: Economy Paving Co., Inc.
    • View Project on Map
  • North and South Grand Island Bridges - Bridge Washing 2007
    • Letting Date: 10/18/2006
    • Completion Date: 06/15/2007
    • Construction Amount: $435,000.00
    • Contract Number: TAN 06-53B/D213626
    • Contractor: JRT Concrete, Inc.
    • View Project on Map
  • MP 362.12 to MP 434.85: Install Protective Screening on 10 Bridges in Buffalo Division
    • Letting Date: 07/27/2005
    • Completion Date: 01/20/2006
    • Construction Amount: $281,297.47
    • Contract Number: TAB 05-12B/D213392
    • Contractor: Rommel Fence, LLC
  • MP 401.72: Pembroke/Route 77 (Exit 48A) Thruway Bridge over Ramps - Rehabilitation
    • Letting Date: 12/21/2005
    • Completion Date: 11/17/2006
    • Construction Amount: $2,356,675.70
    • Contract Number: TAB 05-42B/D213554
    • Contractor: Oakgrove Construction, Inc.
    • View Project on Map
  • MP 430.84: Thruway Bridge over Abbott Road - Rehabilitation
    • Letting Date: 11/22/2006
    • Completion Date: 12/03/2007
    • Construction Amount: $2,959,739.27
    • Contract Number: TAB 06-39B/D213629
    • Contractor: Oakgrove Construction, Inc.
    • View Project on Map
  • MP 210.63 and MP 233.45: Thruway Bridges over Little Falls (Exit 29A) and Horatio Street Ramp - Rehabilitation
    • Letting Date: 07/19/2006
    • Completion Date: 10/31/2007
    • Construction Amount: $1,165,327.63
    • Contract Number: TAS 06-35B/D213521
    • Contractor: Vector Construction Corporation
    • View Project on Map
  • MP N20.35 (Northbound) and MP N21.12 (Southbound): North Grand Island Bridges - Washing 2010
    • Letting Date: 11/04/2009
    • Completion Date: 06/05/2010
    • Construction Amount: $310,200.00
    • Contract Number: TAN 09-60B/D213919
    • Contractor: Dandrow's Painting, Inc.
    • View Project on Map
  • North and South Grand Island Bridges: Bridge Washing - 2006
    • Letting Date: 11/23/2005
    • Completion Date: 06/06/2006
    • Construction Amount: $388,000.00
    • Contract Number: TAN 05-32B/D213400
    • Contractor: JRT Concrete, Inc.
    • View Project on Map
  • MP 182.17: Fultonville Interchange (Exit 28) Bridge over Thruway - Replacement
    • Letting Date: 04/29/2009
    • Completion Date: 12/03/2010
    • Construction Amount: $3,382,352.51
    • Contract Number: TAA 09-15B/D213795
    • Contractor: Bette & Cring LLC
    • View Project on Map
  • MP 327.54: Thruway Bridge over Canandaigua Outlet - Deck Rehabilitation
    • Letting Date: 07/14/2010
    • Completion Date: 12/03/2010
    • Construction Amount: $650,870.38
    • Contract Number: TAS 10-39B/D213985
    • Contractor: Economy Paving Co., Inc.
    • View Project on Map
  • MP 384.61 and MP 384.62: Thruway Bridges over Black Creek - Bridge and Deck Rehabilitations
    • Letting Date: 02/25/2009
    • Completion Date: 11/20/2009
    • Construction Amount: $1,938,419.77
    • Contract Number: TAB 09-11B/D213799
    • Contractor: Crane-Hogan Structural Systems, Inc.
    • View Project on Map
  • MP 415.92: Thruway Bridges over Harris Hill Road and Transit Road (Rte. 78) (MP 416.94) - Rehabilitations
    • Letting Date: 02/06/2013
    • Completion Date: 11/18/2013
    • Construction Amount: $1,838,865.44
    • Contract Number: TAB 13-13B/D214091
    • Contractor: Oakgrove Construction, Inc.
    • View Project on Map
  • MP 17.93: Mountain View Avenue Bridge over Thruway - Rehabilitation
    • Letting Date: 10/29/2008
    • Completion Date: 11/13/2009
    • Construction Amount: $2,013,457.17
    • Contract Number: TANY 08-7B/D213756
    • Contractor: Eastern States Construction, Inc.
    • View Project on Map
  • MP 237.33: Thruway Bridge over Mohawk River - Superstructure Replacement and MP 219.26 Thruway over Barge Canal and Route 5S - Impact Damage Repairs
    • Letting Date: 09/15/2010
    • Completion Date: 12/17/2012
    • Construction Amount: $8,067,949.17
    • Contract Number: TAS 10-49B/D213980
    • Contractor: Tioga Construction Co., Inc.
    • View Project on Map
  • MP 14.67: Tappan Zee Bridge - Phase II Steel Repairs to East Deck Truss and Causeway Spans
    • Letting Date: 09/17/2008
    • Completion Date: 04/12/2011
    • Construction Amount: $30,544,474.26
    • Contract Number: TANY 08-41B/D213657
    • Contractor: Skanska Koch Inc.
    • View Project on Map
  • New York Division: On-Demand Bridge Repair Contract 2006-2008
    • Letting Date: 03/01/2006
    • Completion Date: 08/11/2008
    • Construction Amount: $1,378,053.51
    • Contract Number: TANY 06-12B/D213562
    • Contractor: E. Daskal Corporation
  • Albany Division: On-Demand Bridge Repair Contract 2005-2007
    • Letting Date: 08/24/2005
    • Completion Date: 08/24/2007
    • Construction Amount: $150,111.03
    • Contract Number: TAA 05-16B/D213453
    • Contractor: D.A. Collins Construction Co., Inc.
  • MP N20.35: North Grand Island Bridge Northbound - Repair/Replace Sidewalk
    • Letting Date: 04/12/2006
    • Completion Date: 03/28/2007
    • Construction Amount: $1,450,516.21
    • Contract Number: TAN 06-11B/D213403
    • Contractor: Oakgrove Construction, Inc.
    • View Project on Map
  • MP N14.99: South Grand Island Bridge Southbound - Repair/Replace Sidewalk
    • Letting Date: 04/18/2007
    • Completion Date: 10/16/2007
    • Construction Amount: $1,316,794.60
    • Contract Number: TAN 07-11B/D213642
    • Contractor: Oakgrove Construction, Inc.
    • View Project on Map
  • I-90 (Thruway Mainline) and I-190 (Niagara Section) Culverts: Repairs
    • Letting Date: 12/20/2006
    • Completion Date: 12/06/2007
    • Construction Amount: $1,614,727.87
    • Contract Number: TAB 06-62B/D213641
    • Contractor: Kandey Company, Inc.
  • MP 224.81, MP 228.54, MP 228.73 and MP 230.59: Repairs to 4 Culverts
    • Letting Date: 12/20/2006
    • Completion Date: 08/07/2007
    • Construction Amount: $573,360.63
    • Contract Number: TAS 06-61B/D213610
    • Contractor: Slate Hill Constructors, Inc.
    • View Project on Map
  • Paint 11 Buffalo Division Bridges in Genesee, Erie and Chautauqua Counties
    • Letting Date: 11/09/2005
    • Completion Date: 11/20/2006
    • Construction Amount: $2,765,920.01
    • Contract Number: TAB 05-34BP/D213435
    • Contractor: Atlas Painting & Sheeting Corporation
  • Albany Division: Install Protective Screening on 4 Bridges
    • Letting Date: 07/20/2005
    • Completion Date: 11/18/2005
    • Construction Amount: $105,185.00
    • Contract Number: TAA 05-11B/D213480
    • Contractor: New York State Fence, Inc.
  • MP 1.77 and MP 2.20: Painting of Two New York Division Bridges
    • Letting Date: 04/11/2007
    • Completion Date: 10/03/2007
    • Construction Amount: $1,165,000.00
    • Contract Number: TANY 07-21B/D213680
    • Contractor: Allied Painting, Inc.
    • View Project on Map
  • MP 235.01 to MP 342.42: Install Protective Screening on 14 Bridges in Syracuse Division
    • Letting Date: 07/12/2006
    • Completion Date: 05/01/2007
    • Construction Amount: $197,978.64
    • Contract Number: TAS 06-37B/D213614
    • Contractor: Rommel Fence, LLC
  • New York Division: On-Demand Bridge Repair Contract 2008-2010
    • Letting Date: 07/30/2008
    • Completion Date: 11/26/2010
    • Construction Amount: $1,390,156.89
    • Contract Number: TANY 08-15B/D213768
    • Contractor: E. Daskal Corporation
  • Albany Division: On-Demand Bridge Repair Contract 2007-2009
    • Letting Date: 07/11/2007
    • Completion Date: 09/14/2009
    • Construction Amount: $25,000.00
    • Contract Number: TAA 07-30B/D213700
    • Contractor: D.A. Collins Construction Co., Inc.
  • Syracuse Division: On-Demand Bridge Repair Contract 2006-2007
    • Letting Date: 01/18/2006
    • Completion Date: 03/26/2007
    • Construction Amount: $556,611.62
    • Contract Number: TAS 06-13B/D213560
    • Contractor: C. P. Ward, Inc.
  • Buffalo Division: On-Demand Bridge Repair Contract 2006-2007
    • Letting Date: 03/01/2006
    • Completion Date: 10/18/2007
    • Construction Amount: $919,594.26
    • Contract Number: TAB 06-15B/D213561
    • Contractor: C. P. Ward, Inc.
  • MP NE5.09: I-95 (New England Thruway) Viaduct (New Rochelle) - Partial Painting and Steel Repairs
    • Letting Date: 02/02/2011
    • Completion Date: 11/14/2012
    • Construction Amount: $2,167,006.70
    • Contract Number: TANE 11-5BP/D214020
    • Contractor: Ahern Painting Contractors, Inc.
    • View Project on Map
  • MP 16.75 to MP 42.30: Install Protective Screening on Ten Bridges over the Thruway in New York Division
    • Letting Date: 03/02/2011
    • Completion Date: 02/29/2012
    • Construction Amount: $322,259.09
    • Contract Number: TANY 11-14B/D214008
    • Contractor: Carjen Fence Co., Inc.
    • View Project on Map
  • MP N20.35 and MP N21.12: North Grand Island Bridges - Washing 2008
    • Letting Date: 10/03/2007
    • Completion Date: 06/07/2008
    • Construction Amount: $342,000.00
    • Contract Number: TAN 07-53B/D213699
    • Contractor: JRT Concrete, Inc.
    • View Project on Map
  • MP 388.73 to MP 477.55: Install Protective Screening on 20 Bridges
    • Letting Date: 12/17/2008
    • Completion Date: 10/29/2009
    • Construction Amount: $509,447.96
    • Contract Number: TAB 08-37B/D213741
    • Contractor: Rommel Fence, LLC
  • New York Division: On-Demand Repair Contract for Damaged and Flagged Bridges - 2010-2011
    • Letting Date: 04/07/2010
    • Completion Date: 12/15/2011
    • Construction Amount: $479,984.21
    • Contract Number: TANY 10-21B/D213959
    • Contractor: Hudson Valley Bridge Construction, Inc.
  • Albany Division: On-Demand Repair Contract for Damaged and Flagged Bridges - 2009-2011
    • Letting Date: 08/05/2009
    • Completion Date: 11/18/2011
    • Construction Amount: $732,710.90
    • Contract Number: TAA 09-42B/D213896
    • Contractor: Harrison & Burrowes Bridge Constructors, Inc.
    • View Project on Map
  • Syracuse Division: On-Demand Bridge Repair Contract 2007-2009
    • Letting Date: 06/27/2007
    • Completion Date: 10/15/2009
    • Construction Amount: $859,221.92
    • Contract Number: TAS 07-41B/D213719
    • Contractor: C.P. Ward, Inc.
  • Buffalo Division: On-Demand Bridge Repair Contract 2007-2009
    • Letting Date: 06/27/2007
    • Completion Date: 09/17/2009
    • Construction Amount: $542,583.21
    • Contract Number: TAB 07-42B/D213720
    • Contractor: C.P.Ward, Inc.
  • I-95 Thruway: Bridge Washing - 2009
    • Letting Date: 01/28/2009
    • Completion Date: 06/23/2009
    • Construction Amount: $536,259.00
    • Contract Number: TANE 09-5B/D213827
    • Contractor: Dandrow's Painting, Inc.
  • MP N20.35 and N21.12: North Grand Island Bridge Washing - 2009
    • Letting Date: 12/17/2008
    • Completion Date: 06/05/2009
    • Construction Amount: $335,000.00
    • Contract Number: TAN 08-52B/D213784
    • Contractor: JRT Concrete, Inc.
    • View Project on Map
  • I-95 (New England Thruway): Bridge Maintenance Cleaning for Steel Preservation - 2013
    • Letting Date: 11/14/2012
    • Completion Date: 05/14/2013
    • Construction Amount: $537,300.00
    • Contract Number: TANE 12-40B/D214193
    • Contractor: Dandrow's Painting, Inc.
  • MP 30.18 (Northbound): Exit 15 Northbound Off Ramp - Bridge Railing/Barrier Extension and Safety Upgrades
    • Letting Date: 03/03/2010
    • Completion Date: 12/30/2010
    • Construction Amount: $404,946.86
    • Contract Number: TANY 10-12B/D213942
    • Contractor: J. Fletcher Creamer & Son, Inc.
    • View Project on Map
  • Repair 11 Large Culverts on the Berkshire Spur in Albany Division
    • Letting Date: 12/01/2010
    • Completion Date: 03/26/2012
    • Construction Amount: $1,548,019.95
    • Contract Number: TABS 10-56/D214028
    • Contractor: Ketco, Inc.
  • MP 30.80 and MP NE3.19: Replacement of Two New York Division Sign Structures
    • Letting Date: 02/20/2013
    • Completion Date: 04/28/2014
    • Construction Amount: $1,627,203.20
    • Contract Number: TANY 13-30B/D214221
    • Contractor: Mohegan Associates, Inc
  • MP 113.22: Thruway Bridge over Catskill Creek - Emergency Slope and Scour Repairs (Tropical Storm Recovery)
    • Letting Date: 11/09/2011
    • Completion Date: 05/11/2012
    • Construction Amount: $1,401,542.56
    • Contract Number: TAA 11-53B/D214126
    • Contractor: The Delaney Group dba Tetra Tech Construction
    • View Project on Map
  • MP N1.88: I-190 Thruway Bridge over Bailey Avenue and Norfolk Southern Railroad - Pier/Bearing Repair
    • Letting Date: 04/26/2006
    • Completion Date: 01/10/2007
    • Construction Amount: $242,067.33
    • Contract Number: TAN 06-23B/D213574
    • Contractor: Nichols, Long and Moore Construction
    • View Project on Map
  • MP 63.16: Union Avenue Bridge over Thruway - Rehabilitation
    • Letting Date: 02/07/2007
    • Completion Date: 10/19/2007
    • Construction Amount: $1,281,349.79
    • Contract Number: TANY 07-6B/D213652
    • Contractor: I & OA Slutzky, Inc.
    • View Project on Map
  • MP 366.27 and MP 366.28: Thruway Bridges over the Genesee River - Deck Replacements; MP 367.38: Thruway Bridge over B&O RR - Substructure Repairs; MP 367.49: Thruway Bridge over Reed Road - Rehabilitation; MP 366.42: Thruway Bridge over Scottsville Road - Deck Rehabilitation; MP 366.28 to MP 366.42, Pavement Rehabilitation; and MP 366.0 to MP 367.6, Pavement Resurfacing
    • Letting Date: 12/23/2009
    • Completion Date: 12/08/2011
    • Construction Amount: $12,668,779.89
    • Contract Number: TAB 09-53B/D213879
    • Contractor: Sealand Constructors Corporation
    • View Project on Map
  • MP 14.67: Tappan Zee Bridge - Rehabilitation of Deck and Substructure & Replacement of Electrical Transfer Switch
    • Letting Date: 12/14/2005
    • Completion Date: 07/14/2011
    • Construction Amount: $178,825,898.30
    • Contract Number: TANY 05-31B/D213533
    • Contractor: Perini Corporation/Tutor-Saliba, JV
    • View Project on Map
  • MP 14.67: Tappan Zee Bridge - Deck Rehabilitation Contract No. 2
    • Letting Date: 03/10/2010
    • Completion Date: 08/16/2013
    • Construction Amount: $150,684,406.45
    • Contract Number: TANY 10-9B/D213881
    • Contractor: Tutor Perini Corporation
    • View Project on Map
  • I-95 Thruway: Bridge Washing - 2010
    • Letting Date: 11/18/2009
    • Completion Date: 04/24/2010
    • Construction Amount: $511,860.00
    • Contract Number: TANE 09-61B/D213920
    • Contractor: Dandrow's Painting, Inc.
  • Six I-95 (New England Thruway) Bridge Rehabilitations: MP NE0.41, I-95 Bridge over Erskine Place; MP NE0.55 and NE0.56, I-95 Bridges over Hutchinson River Parkway Ext; MP NE5.39, Centre Ave Bridge over I-95; MP NE2.37, Conner Street Bridge over I-95; and MP NE4.63: I-95 Bridge over Boston Post Road
    • Letting Date: 11/24/2010
    • Completion Date: 04/27/2012
    • Construction Amount: $13,282,068.91
    • Contract Number: TANE 10-52B/D213999
    • Contractor: DeFoe Corporation
    • View Project on Map
  • Install Protective Screening on 9 Albany Division Bridges
    • Letting Date: 03/14/2007
    • Completion Date: 11/28/2007
    • Construction Amount: $248,834.52
    • Contract Number: TAA 07-15B/D213653
    • Contractor: Rommel Fence, LLC
  • Albany Division: On-Demand Repair Contract for Damaged and Flagged Bridges - 2012-2013
    • Letting Date: 09/28/2011
    • Completion Date: 11/01/2013
    • Construction Amount: $575,568.04
    • Contract Number: TAA 11-48B/D214111
    • Contractor: D.A. Collins
    • View Project on Map
  • Syracuse Division: On-Demand Bridge Repair Contract for Damaged and Flagged Bridges 2009-2011
    • Letting Date: 06/10/2009
    • Completion Date: 02/29/2012
    • Construction Amount: $1,117.20
    • Contract Number: TAS 09-36B/D213877
    • Contractor: C.P. Ward, Inc.
  • Buffalo Division: On-Demand Repair Contract for Damaged and Flagged Bridges - 2010-2011
    • Letting Date: 11/04/2009
    • Completion Date: 09/16/2011
    • Construction Amount: $2,115,218.73
    • Contract Number: TAB 09-58B/D213924
    • Contractor: C.P. Ward, Inc.
    • View Project on Map
  • MP 352.36 to MP 434.03: Paint 11 Buffalo Division Bridges
    • Letting Date: 01/14/2009
    • Completion Date: 07/12/2010
    • Construction Amount: $6,556,808.12
    • Contract Number: TAB 08-49BP/D213792
    • Contractor: Atlas Painting & Sheeting Corporation
  • MP 206.61 to MP 337.47: Syracuse Division Bridge Painting - 7 Bridges
    • Letting Date: 09/24/2008
    • Completion Date: 11/18/2009
    • Construction Amount: $2,019,596.01
    • Contract Number: TAS 08-33BP/D213698
    • Contractor: P.S. Bruckel, Inc.
  • MP 197.93 to MP 232.97: Syracuse Division Bridge Painting - 12 Bridges
    • Letting Date: 12/22/2010
    • Completion Date: 11/16/2011
    • Construction Amount: $8,681,293.88
    • Contract Number: TAS 10-58BP/D214012
    • Contractor: Liberty-Alpha JV, LLC
    • View Project on Map
  • MP 125.45 to MP 194.10 and MP BS0.00: Painting of Six Albany Division Bridges
    • Letting Date: 02/11/2009
    • Completion Date: 12/18/2009
    • Construction Amount: $3,148,910.44
    • Contract Number: TAA 09-6BP/D213837
    • Contractor: Erie Painting and Maintenance, Inc.
  • Rehabilitation/Repair of 3 Bridges at MP 352.59, Thruway Bridge over Abandoned NYCRR; MP 363.95, Thruway Bridge over Livonia, Avon & Lakeville RR; and MP 364.74, East River Road Bridge over Thruway; and Culvert Replacement at MP 363.12, West of I-390 (Exit 46)
    • Letting Date: 03/31/2010
    • Completion Date: 10/31/2011
    • Construction Amount: $5,565,010.58
    • Contract Number: TAB 10-10B/D213933
    • Contractor: Slate Hill Constructors, Inc.
  • MP BS1.08: Castleton Bridge Deck Rehabilitation
    • Letting Date: 04/29/2009
    • Completion Date: 11/13/2009
    • Construction Amount: $2,931,004.08
    • Contract Number: TABS 09-18B/D213853
    • Contractor: Harrison & Burrowes Bridge Constructors, Inc.
    • View Project on Map
  • Buffalo Division: Steel Repairs of 4 Bridges
    • Letting Date: 06/03/2009
    • Completion Date: 11/02/2009
    • Construction Amount: $648,878.21
    • Contract Number: TAB 09-13B/D213780
    • Contractor: Hohl Industrial Services, Inc.
  • Syracuse Division: On-Demand Repair Contract for Damaged and Flagged Bridges - 2012-2013
    • Letting Date: 02/22/2012
    • Completion Date: 07/12/2012
    • Construction Amount: $212,380.00
    • Contract Number: TAS 12-6B/D214124
    • Contractor: D.A. Collins Construction Co.
  • Buffalo Division: On-Demand Repair Contract for Damaged and Flagged Thruway and Canal Structures - 2012-2013
    • Letting Date: 11/23/2011
    • Completion Date: 12/12/2012
    • Construction Amount: $7,425.48
    • Contract Number: TAB 11-49B/D214118
    • Contractor: C.P. Ward, Inc.
  • MP N14.35 Northbound and N14.99 Southbound: South Grand Island Bridges - Maintenance Cleaning for Steel Preservation - 2011
    • Letting Date: 02/09/2011
    • Completion Date: 06/09/2011
    • Construction Amount: $265,000.00
    • Contract Number: TAN 11-2B/D214002
    • Contractor: JRT Concrete, Inc.
    • View Project on Map
  • MP N14.99, MP N20.35 and MP N21.12: Grand Island Bridges - Gusset Plate and Steel Repairs
    • Letting Date: 08/25/2010
    • Completion Date: 06/25/2012
    • Construction Amount: $5,848,702.34
    • Contract Number: TAN 10-40B/D213992
    • Contractor: Piasecki Steel Construction Group
    • View Project on Map
  • MP 23.09 to MP 29.54: Deck Rehabilitation of 8 Bridges in New York Division
    • Letting Date: 06/17/2009
    • Completion Date: 12/15/2009
    • Construction Amount: $1,899,255.39
    • Contract Number: TANY 09-37B/D213854
    • Contractor: Tilcon New York, Inc.
    • View Project on Map
  • MP 104.04 to MP 179.38 and MP BS7.77 to MP BS23.27: Albany Division Bridge Painting - 13 Bridges
    • Letting Date: 12/22/2010
    • Completion Date: 08/31/2012
    • Construction Amount: $8,516,605.25
    • Contract Number: TAA 10-59BP/D214022
    • Contractor: P.S. Bruckel, Inc.
  • I-95 (New England Thruway) Bridge Maintenance Cleaning for Steel Preservation - 2011
    • Letting Date: 12/22/2010
    • Completion Date: 04/26/2011
    • Construction Amount: $539,360.00
    • Contract Number: TANE 10-57B/D214001
    • Contractor: Dandrow's Painting, Inc.
  • MP 801.08: Castleton Bridge - Repair Gusset Plates
    • Letting Date: 04/11/2012
    • Completion Date: 08/30/2012
    • Construction Amount: $1,042,998.73
    • Contract Number: TABS 11-11BR/D214014
    • Contractor: Piasecki Steel Construction Corporation
    • View Project on Map
  • MP BS0.19: Impact Damage Repairs to Route 144 Bridge
    • Letting Date: 05/12/2010
    • Completion Date: 08/23/2010
    • Construction Amount: $184,704.00
    • Contract Number: TABS 10-29B/D213974
    • Contractor: Tioga Construction Company, Inc.
    • View Project on Map
  • MP 278.93, MP 283.79 and MP 337.47: Impact Damage Repairs to 3 Syracuse Division Bridges
    • Letting Date: 08/03/2011
    • Completion Date: 07/25/2012
    • Construction Amount: $404,201.47
    • Contract Number: TAS 11-44B/D214102
    • Contractor: Tioga Construction Co., Inc.
  • MP 177.47, MP 182.76, MP 811.35 and MP 103.16: Steel Repairs to 4 Albany Division Bridges
    • Letting Date: 12/15/2010
    • Completion Date: 09/22/2011
    • Construction Amount: $284,554.80
    • Contract Number: TAA 10-48B/D214005
    • Contractor: Tioga Construction Co., Inc.
  • Buffalo Division Bridge Painting - 6 Bridges
    • Letting Date: 11/24/2010
    • Completion Date: 06/29/2012
    • Construction Amount: $2,667,100.00
    • Contract Number: TAB 10-55BP/D214013
    • Contractor: Erie Painting and Maintenance, Inc.
  • MP 413.65 - MP 494.93 and MP 911.55 - MP 915.77: Buffalo Division - Installation of Protective Screening on 27 Bridges
    • Letting Date: 12/02/2009
    • Completion Date: 07/02/2010
    • Construction Amount: $647,064.17
    • Contract Number: TAB 09-59B/D213928
    • Contractor: Rommel Fence, LLC.
  • New York Division: Repair 2 Bridges and 4 Culverts
    • Letting Date: 07/28/2010
    • Completion Date: 10/03/2011
    • Construction Amount: $1,175,154.10
    • Contract Number: TANY 10-24B/D213940
    • Contractor: Sun Up Enterprises, Inc.
  • MP 17.42 to MP 52.57: Painting of Six New York Division Bridges
    • Letting Date: 04/15/2009
    • Completion Date: 11/20/2009
    • Construction Amount: $2,339,059.88
    • Contract Number: TANY 09-29BP/D213822
    • Contractor: Matsos Contracting Corporation
    • View Project on Map
  • Rehabilitate Four I-95 (New England Thruway) Bridges: MP NE10.52, West Street Bridge over I-95 - Deck Rehabilitation; MP NE8.8, Rockland Avenue Bridge over I-95 - Deck Resurfacing; MP NE12.94, Central Avenue Bridge over I-95 - Deck Rehabilitation; and MP NE9.14, I-95 Bridge over Fenimore Road - Deck Joint and Substructure Repairs
    • Letting Date: 10/26/2011
    • Completion Date: 09/27/2012
    • Construction Amount: $2,989,939.93
    • Contract Number: TANE 11-35B/D214084
    • Contractor: DeFoe Corporation
    • View Project on Map
  • Paint 13 New York Division Bridges
    • Letting Date: 06/02/2010
    • Completion Date: 07/15/2011
    • Construction Amount: $6,191,493.18
    • Contract Number: TANY 10-30BP/D213973
    • Contractor: Matsos Contracting Corporation
  • MP 42.30: Arden Station Road Bridge over Thruway - Rehabilitation
    • Letting Date: 02/10/2010
    • Completion Date: 12/31/2010
    • Construction Amount: $1,657,394.34
    • Contract Number: TANY 10-1B/D213905
    • Contractor: Harrison & Burrowes Bridge Constructors, Inc.
    • View Project on Map
  • MP GS1.64 & MP GS1.65: Garden State Parkway Connector Bridges over Williams Road - Rehabilitation
    • Letting Date: 12/15/2010
    • Completion Date: 06/30/2012
    • Construction Amount: $1,756,121.08
    • Contract Number: TAGS 10-61B/D213994
    • Contractor: Unicorn Construction Enterprises, Inc.
    • View Project on Map
  • MP 2.20: Cross County Parkway Bridge over Thruway - Deck and Joint Repairs and MP 7.84 Thruway over Route 9A - Deck Rehabilitation and Bearing Replacement
    • Letting Date: 08/04/2010
    • Completion Date: 09/23/2011
    • Construction Amount: $2,742,509.05
    • Contract Number: TANY 10-46B/D213961
    • Contractor: McNamee Construction Corporation
    • View Project on Map
  • Waterford: Lock E-4 - Miter Gate Replacement, Saratoga County
    • Letting Date: 05/10/2006
    • Completion Date: 04/19/2007
    • Construction Amount: $1,558,821.64
    • Contract Number: TAA 06-24C/D213588
    • Contractor: James H. Maloy, Inc.
    • View Project on Map
  • Phoenix: Lock O-1 Southwest Approach Wall - Rehabilitation, Oswego County
    • Letting Date: 06/08/2011
    • Completion Date: 05/18/2012
    • Construction Amount: $824,049.89
    • Contract Number: TAS 11-13C/D214046
    • Contractor: Tioga Construction Co., Inc.
    • View Project on Map
  • Albany Division: Locks E-9, E-11, E-14, E-15 - Electrical Rehabilitation (2006 Flood), Schenectady & Montgomery Counties
    • Letting Date: 12/20/2006
    • Completion Date: 06/04/2007
    • Construction Amount: $1,369,631.40
    • Contract Number: TAA 06-60C/D213665
    • Contractor: LaCorte Companies, Inc.
  • Albany Division: Locks E-12, E-13 - Electrical Rehabilitation (2006 Flood), Montgomery County
    • Letting Date: 01/31/2007
    • Completion Date: 10/19/2007
    • Construction Amount: $667,299.88
    • Contract Number: TAA 07-7C/D213664
    • Contractor: O'Connell Electric Company
  • Albany Division: Locks E-9, E-13, E-14, E-15 - Site Rehabilitation & Buildings (2006 Flood), Schenectady & Montgomery Counties
    • Letting Date: 06/27/2007
    • Completion Date: 08/29/2008
    • Construction Amount: $1,682,863.76
    • Contract Number: TAA 07-9C/D213667
    • Contractor: Harrison & Burrows Bridge Constructors, Inc.
  • Albany Division: Locks E-8, E-9, E-11, E-12, E-13, E-14, E-15 - Steel & Concrete Repairs (2006 Flood), Schenectady & Montgomery Counties
    • Letting Date: 04/25/2007
    • Completion Date: 06/30/2008
    • Construction Amount: $4,346,531.98
    • Contract Number: TAA 07-8C/D213666
    • Contractor: Harrison & Burrows Bridge Constructors, Inc.
  • Statewide: Installation of Fall Protection Systems at 10 Dams - Schenectady, Montgomery, Herkimer and Seneca Counties
    • Letting Date: 08/11/2010
    • Completion Date: 08/31/2012
    • Construction Amount: $1,957,647.47
    • Contract Number: TAA 10-26C/D213970
    • Contractor: Piasecki Steel Construction Corporation
  • Lockport: Rock Slope - Remediation, Niagara County
    • Letting Date: 10/07/2009
    • Completion Date: 11/18/2010
    • Construction Amount: $789,852.00
    • Contract Number: TAB 09-40CR/D213887
    • Contractor: Nichols Long & Moore Construction Corporation
  • Statewide: Marine Vessel - When/Where Recovery Contract
    • Letting Date: 06/16/2010
    • Completion Date: 12/21/2012
    • Construction Amount: $252,720.20
    • Contract Number: TA 10-32C/D213982
    • Contractor: Tioga Construction Co., Inc.
  • Waterford: OCC Stone Retaining Wall - Replacement, Saratoga County
    • Letting Date: 07/07/2010
    • Completion Date: 06/20/2011
    • Construction Amount: $191,078.99
    • Contract Number: TAA 10-14C/D213949
    • Contractor: Bette & Cring, LLC
  • Seneca Falls: Lock C&S-2 - Lower Miter Gate Replacement, Seneca County
    • Letting Date: 12/01/2010
    • Completion Date: 04/11/2012
    • Construction Amount: $1,439,339.82
    • Contract Number: TAS 10-50C/D214004
    • Contractor: Tioga Construction Co., Inc.
    • View Project on Map
  • Palatine Bridge & Indian Castle: Lock E-14 & Rocky Rift Movable Dam - Railing Installation, Montgomery & Herkimer Counties
    • Letting Date: 10/10/2012
    • Completion Date: 11/15/2013
    • Construction Amount: $859,499.00
    • Contract Number: TAA 12-2C/D214100
    • Contractor: Tioga Construction Co., Inc.
  • Pittsford: Replace Lower Miter Gates at Lock E-32, Monroe County
    • Letting Date: 06/15/2011
    • Completion Date: 05/22/2012
    • Construction Amount: $1,334,949.14
    • Contract Number: TAB 11-37C/D214087
    • Contractor: BVR Construction Company, Inc.
    • View Project on Map
  • Crescent: Lock E-6 - Rehabilitation, Saratoga County
    • Letting Date: 06/11/2008
    • Completion Date: 04/15/2011
    • Construction Amount: $15,132,402.76
    • Contract Number: TAA 08-35C/D213750
    • Contractor: Kubricky Construction Corporation
    • View Project on Map
  • Clyde: Lock E-26 Taintor Gate and Dam - Rehabilitation, Wayne County
    • Letting Date: 07/19/2006
    • Completion Date: 06/10/2008
    • Construction Amount: $7,608,753.83
    • Contract Number: TAS 06-32C/D213513
    • Contractor: Tioga Construction Co., Inc.
  • Minetto: Lock O-5 - Rehabilitation and Lock O-8 Concrete Repairs, Oswego County
    • Letting Date: 10/22/2008
    • Completion Date: 08/31/2010
    • Construction Amount: $10,217,170.15
    • Contract Number: TAS 08-8C/D213758
    • Contractor: Tioga Construction Co., Inc.
    • View Project on Map
  • Cranesville: Lock E-10 - Emergency Repairs (2006 Flood), Montgomery County
    • Letting Date: 04/15/2009
    • Completion Date: 06/10/2010
    • Construction Amount: $1,219,557.50
    • Contract Number: TAA 09-7C/D213844
    • Contractor: James H. Maloy, Inc.
  • Oswego: Lock O-7/O-8 Walls - Repairs, Oswego County
    • Letting Date: 03/15/2006
    • Completion Date: 04/23/2007
    • Construction Amount: $978,597.57
    • Contract Number: TAS 06-9C/D213496
    • Contractor: Tuscarora Construction Co., Inc.
  • Pittsford: Cartersville Waste Weir - Rehabilitation, Monroe County
    • Letting Date: 07/26/2006
    • Completion Date: 01/09/2008
    • Construction Amount: $925,296.84
    • Contract Number: TAB 06-34C/D213615
    • Contractor: C.P. Ward, Inc.
    • View Project on Map
  • St. Johnsville: Lock E-16 Approach Wall - Rehabilitation, Montgomery County
    • Letting Date: 07/20/2005
    • Completion Date: 06/22/2006
    • Construction Amount: $231,127.25
    • Contract Number: TAA 05-1C/D213418
    • Contractor: Tioga Construction Co., Inc.
    • View Project on Map
  • Rochester: West Guard Lock - Rehabilitation, Monroe County
    • Letting Date: 06/30/2010
    • Completion Date: 10/06/2011
    • Construction Amount: $4,237,852.50
    • Contract Number: TAB 10-11C/D213945
    • Contractor: The Pike Company, Inc.
    • View Project on Map
  • Fort Miller: Lock C-6 - Miter Gate Replacement, Washington County
    • Letting Date: 11/15/2006
    • Completion Date: 05/20/2008
    • Construction Amount: $1,793,733.40
    • Contract Number: TAA 06-55C/D213643
    • Contractor: C. D. Perry & Sons, Inc.
    • View Project on Map
  • Canajoharie: Movable Dam 10 at Lock E-14 - Rehabilitation, Montgomery County
    • Letting Date: 03/21/2007
    • Completion Date: 05/21/2010
    • Construction Amount: $17,204,894.65
    • Contract Number: TAA 07-20C/D213616
    • Contractor: Tioga Construction Co., Inc.
    • View Project on Map
  • Cayuga Lake: Range Tower - Replacement, Seneca County and Lyons: Lower Yard Sheeting - Replacement, Wayne County
    • Letting Date: 11/02/2005
    • Completion Date: 07/19/2007
    • Construction Amount: $546,499.67
    • Contract Number: TAS 05-19C/D213442
    • Contractor: Economy Paving Co., Inc.
    • View Project on Map
  • Orleans County: Bank and Culvert Repair Work
    • Letting Date: 08/10/2011
    • Completion Date: 10/11/2012
    • Construction Amount: $1,340,833.57
    • Contract Number: TAB 11-22C/D213703
    • Contractor: C.P. Ward Inc.
  • Tribes Hill: Movable Dam 8 at Lock E-12 - Painting, Montgomery County
    • Letting Date: 09/23/2009
    • Completion Date: 08/31/2012
    • Construction Amount: $4,228,856.45
    • Contract Number: TAA 09-50C/D213748
    • Contractor: Erie Painting and Maintenance
    • View Project on Map
  • Statewide: Dredging - Initiative Phase 4, Fabrication
    • Letting Date: 11/07/2007
    • Completion Date: 03/11/2009
    • Construction Amount: $1,097,861.00
    • Contract Number: TAS 07-58C/D213752
    • Contractor: BVR Construdtion Co.
  • Utica Harbor: Remediation - Phase 1, Oneida County
    • Letting Date: 01/21/2009
    • Completion Date: 09/23/2009
    • Construction Amount: $1,976,228.95
    • Contract Number: TAS 09-10C/D213458
    • Contractor: Tioga Construction Co., Inc.
    • View Project on Map
  • Utica Harbor: Remediation - Phase 2, Oneida County
    • Letting Date: 03/15/2006
    • Completion Date: 09/08/2006
    • Construction Amount: $761,616.97
    • Contract Number: TAS 06-1C/D213563
    • Contractor: D.H. Smith Company, Inc.
    • View Project on Map
  • Canajoharie: Installation of Required Railroad Crossing Signal System on Access Road to Lock E-14, Montgomery County
    • Letting Date: 02/06/2013
    • Completion Date: 05/10/2013
    • Construction Amount: $224,319.35
    • Contract Number: TAA 12-38C/D214174
    • Contractor: Rifenburg Construction, Inc.
    • View Project on Map
  • Fort Edward: Section 1 Office & Shop - Roof Replacement, Washington County
    • Letting Date: 01/18/2006
    • Completion Date: 06/02/2006
    • Construction Amount: $78,434.00
    • Contract Number: TAA 06-4C/D213540
    • Contractor: T.P. Monahan, Inc.
    • View Project on Map
  • Rotterdam: Movable Dam 5 at Lock E-9 - Steel Repairs, Schenectady County and Amsterdam: Movable Dam 7 at Lock E-11- Steel & Scour Repairs (2006 Flood)
    • Letting Date: 09/06/2006
    • Completion Date: 05/29/2007
    • Construction Amount: $1,005,216.88
    • Contract Number: TAA 06-40C/D213617
    • Contractor: C. D. Perry & Sons, Inc.
  • Little Falls: Lock E-17 Lower Approach Wall and Tribes Hill: Lock E-12 NE & NW Approach Walls - Scour Repairs (2006 Flood)
    • Letting Date: 11/01/2006
    • Completion Date: 06/18/2007
    • Construction Amount: $327,544.49
    • Contract Number: TAS 06-52C/D213646
    • Contractor: Slate Hill Constructors, Inc.
  • Tribes Hill: Lock E-12 NW Approach Wall - Scour Repairs (2006 Flood), Phase 2, Montgomery County
    • Letting Date: 01/07/2009
    • Completion Date: 07/02/2009
    • Construction Amount: $69,895.50
    • Contract Number: TAA 09-1C/D213833
    • Contractor: Tioga Construction Co., Inc.
    • View Project on Map
  • Waterford: Dry Dock - Electrical Repairs, Saratoga County
    • Letting Date: 11/29/2006
    • Completion Date: 09/18/2007
    • Construction Amount: $346,471.36
    • Contract Number: TAA 06-25C/D213589
    • Contractor: Northwild Systems, Inc.
    • View Project on Map
  • Pendleton: Slope - Restoration & Associated Dredging, Niagara County
    • Letting Date: 11/08/2006
    • Completion Date: 08/10/2007
    • Construction Amount: $1,746,695.10
    • Contract Number: TAB 06-14CR/D213572
    • Contractor: Pinto Construction Services, Inc.
  • Herkimer County: Bank Repairs, Herkimer County
    • Letting Date: 11/28/2007
    • Completion Date: 06/06/2008
    • Construction Amount: $545,253.16
    • Contract Number: TAS 07-55C/D213742
    • Contractor: Tioga Construction Co., Inc.
  • Medina: Bank Failure Restoration, Orleans County
    • Letting Date: 01/24/2007
    • Completion Date: 05/04/2007
    • Construction Amount: $327,992.64
    • Contract Number: TAB 07-19C/D213689
    • Contractor: Nichols Long & Moore Construction
  • Waterford: Lock E-4 - Emergency Repairs and Lock E-5 - Emergency Repairs and Miter Gate Replacement, Saratoga County
    • Letting Date: 11/30/2005
    • Completion Date: 04/28/2006
    • Construction Amount: $2,003,216.00
    • Contract Number: TAA 05-43C/D213568
    • Contractor: C. D. Perry & Sons, Inc.
    • View Project on Map
  • Scotia & Rotterdam: Lighting Repairs to MD 4 at Lock E-8 and Partial Upright and Lighting Repairs to MD 5 at Lock E-9, Schenectady Co. (Partial FEMA)
    • Letting Date: 01/11/2012
    • Completion Date: 06/08/2012
    • Construction Amount: $1,176,431.92
    • Contract Number: TAA 11-55CR/D214136
    • Contractor: Tioga Construction Co., Inc.
  • Emergency Replacement of Grade Control Structures at Lock E-8 and Lock E-9 (Tropical Storm Recovery)
    • Letting Date: 12/23/2011
    • Completion Date: 05/25/2012
    • Construction Amount: $1,598,425.36
    • Contract Number: TAA 11-54C/D214135
    • Contractor: The Delaney Group, Inc.
    • View Project on Map
  • Tribes Hill: Dredge Erie Canal in the Area of Lock E-12, Montgomery County (Tropical Storms Irene and Lee Recovery Project - Partial FEMA Eligible)
    • Letting Date: 03/13/2013
    • Completion Date: 09/05/2013
    • Construction Amount: $982,200.00
    • Contract Number: TAA 13-3C/D214166
    • Contractor: Tioga Construction Co., Inc.
    • View Project on Map
  • Cranesville & Tribes Hill: Bearing Rehabilitation at Movable Dams 6 & 8 at Locks E-10 & E-12, Montgomery County
    • Letting Date: 12/12/2012
    • Completion Date: 04/12/2013
    • Construction Amount: $359,107.10
    • Contract Number: TAA 12-41C/D214197
    • Contractor: Piasecki Steel Construction Corporation
  • I-95, Port Chester (MP NE14.1) to Connecticut State Line (MP NE15.0): Pavement Resurfacing, and Byram River Bridge (MP NE14.93) - Resurface Deck and Painting
    • Letting Date: 01/26/2011
    • Completion Date: 02/06/2013
    • Construction Amount: $17,530,364.44
    • Contract Number: TANE 10-60B/D213847
    • Contractor: Tully Construction Co., Inc.
    • View Project on Map
  • South of Harriman (MP 38.7 to MP 43.5): Safety Upgrades
    • Letting Date: 10/22/2008
    • Completion Date: 08/28/2009
    • Construction Amount: $1,037,505.48
    • Contract Number: TANY 08-21/D213773
    • Contractor: J. Fletcher Creamer & Son, Inc.
    • View Project on Map
  • South of Harriman (MP 38.7 to MP 43.5): Pavement Resurfacing
    • Letting Date: 09/05/2008
    • Completion Date: 10/31/2008
    • Construction Amount: $1,452,415.79
    • Contract Number: NO TA/PC63882
    • View Project on Map
  • I-787 (Exit 23, MP 141.2) to South of Northway (MP 146.0): Pavement Resurfacing and Paving of Interchanges 23, 24, 25, 25A and 26
    • Letting Date: 06/17/2009
    • Completion Date: 11/18/2009
    • Construction Amount: $4,475,041.44
    • Contract Number: TAA 09-24/D213863
    • Contractor: Callanan Industries, Inc.
    • View Project on Map
  • Newburgh, I-84/I-87 (Exit 17, MP 60.10): Interchange Reconstruction, Direct Connection and New Bridges - Contract 3
    • Letting Date: 11/29/2006
    • Completion Date: 01/08/2010
    • Construction Amount: $69,018,707.23
    • Contract Number: TANY 06-51/D213405
    • Contractor: A Servidone, Inc/B Anthony Construction Corp
    • View Project on Map
  • Tappan Zee Bridge to Nyack (MP 18.0) and North of Spring Valley (MP 23.0) to South of Suffern (MP 29.4): Pavement Rehabilitation and other Miscellaneous Work
    • Letting Date: 05/10/2006
    • Completion Date: 08/29/2008
    • Construction Amount: $22,630,888.49
    • Contract Number: TANY 06-27/D213481
    • Contractor: Intercounty Paving Associates, LLC
    • View Project on Map
  • West of Canastota (MP 268.0) to Thompson Road (Exit 35, MP 279.3): Pavement Resurfacing including Interchange Ramps
    • Letting Date: 06/27/2007
    • Completion Date: 05/30/2008
    • Construction Amount: $4,963,481.86
    • Contract Number: TAS 07-40/D213714
    • Contractor: Dolomite Products Company, Inc. dba Ulster Paving Company
    • View Project on Map
  • West of Canastota (MP 268.0) to Thompson Road (Exit 35, MP 279.3): Safety Upgrades
    • Letting Date: 06/11/2008
    • Completion Date: 01/27/2009
    • Construction Amount: $2,323,742.06
    • Contract Number: TAS 08-5/D213753
    • Contractor: Slate Hill Constructors, Inc.
    • View Project on Map
  • Victor (Exit 45, MP 350.99) and Henrietta (Exit 46, MP 362.44): Plaza and Ramp Resurfacing
    • Letting Date: 05/27/2009
    • Completion Date: 11/23/2009
    • Construction Amount: $2,903,201.78
    • Contract Number: TAB 09-31/D213871
    • Contractor: Sealand Contractors Corporation
    • View Project on Map
  • East of Henrietta (MP 359.6) to LeRoy (Exit 47, MP 378.2): Pavement Resurfacing and Safety Upgrades
    • Letting Date: 06/03/2009
    • Completion Date: 11/05/2010
    • Construction Amount: $12,067,219.28
    • Contract Number: TAB 09-17/D213856
    • Contractor: Keeler Construction Co. Inc.
    • View Project on Map
  • I-190 (MP N0.0) to Ontario Street (Exit N14, MP N10.0): Portland Cement Concrete Joint Repair/Resealing & Grinding at Various Locations
    • Letting Date: 04/01/2009
    • Completion Date: 12/24/2010
    • Construction Amount: $9,755,903.57
    • Contract Number: TAN 09-19/D213660
    • Contractor: Oakgrove Construction, Inc.
    • View Project on Map
  • Nyack (Exit 11, MP 18.0) to Spring Valley (Exit 14, MP 23.0): Pavement Resurfacing and Ramp Resurfacing
    • Letting Date: 08/03/2005
    • Completion Date: 12/08/2005
    • Construction Amount: $7,935,623.60
    • Contract Number: TANY 05-18/D213532
    • Contractor: Yonker's Contracting Co., Inc.
    • View Project on Map
  • West of Pembroke (MP 404.7) to Depew (Exit 49, MP 416.9): Pavement Resurfacing
    • Letting Date: 07/20/2011
    • Completion Date: 08/29/2012
    • Construction Amount: $9,019,444.36
    • Contract Number: TAB 11-8/D214034
    • Contractor: Union Concrete & Construction Corporation
    • View Project on Map
  • Weedsport (Exit 40, MP 304.5) to East of Waterloo (MP 313.8): Pavement Resurfacing and Installation of Median Guiderail
    • Letting Date: 03/18/2009
    • Completion Date: 12/22/2009
    • Construction Amount: $6,596,528.97
    • Contract Number: TAS 09-9/D213762
    • Contractor: Villager Construction, Inc.
    • View Project on Map
  • New York Division: Pavement Striping - 2006
    • Letting Date: 01/11/2006
    • Completion Date: 07/21/2006
    • Construction Amount: $646,119.94
    • Contract Number: TANY 05-37/D213542
    • Contractor: Safety Marking, Inc.
  • Albany Division: Pavement Striping - 2006
    • Letting Date: 01/11/2006
    • Completion Date: 07/28/2006
    • Construction Amount: $317,918.77
    • Contract Number: TAA 05-36/D213543
    • Contractor: Straight Line Industries, Inc.
  • Syracuse Division: Pavement Striping - 2006
    • Letting Date: 12/14/2005
    • Completion Date: 07/24/2006
    • Construction Amount: $652,052.60
    • Contract Number: TAS 05-40/D213544
    • Contractor: Straight Line Industries, Inc.
  • Buffalo Division: Pavement Striping - 2006
    • Letting Date: 12/14/2005
    • Completion Date: 07/31/2006
    • Construction Amount: $669,874.28
    • Contract Number: TAB 05-35/D213545
    • Contractor: Accent Stripe, Inc.
  • New York Division: Pavement Striping - 2007
    • Letting Date: 11/01/2006
    • Completion Date: 07/17/2007
    • Construction Amount: $623,010.56
    • Contract Number: TANY 06-48/D213637
    • Contractor: Safety Marking, Inc.
  • Albany Division: Pavement Striping - 2007
    • Letting Date: 11/01/2006
    • Completion Date: 07/19/2007
    • Construction Amount: $461,285.73
    • Contract Number: TAA 06-47/D213636
    • Contractor: Straight Line Industries, Inc.
  • Syracuse Division: Pavement Striping - 2007
    • Letting Date: 11/29/2006
    • Completion Date: 07/26/2007
    • Construction Amount: $324,367.80
    • Contract Number: TAS 06-50/D213639
    • Contractor: Accent Stripe, Inc.
  • Buffalo Division: Pavement Striping - 2007
    • Letting Date: 11/29/2006
    • Completion Date: 06/27/2007
    • Construction Amount: $612,446.89
    • Contract Number: TAB 06-49/D213638
    • Contractor: Accent Stripe, Inc.
  • MP 0.0 to MP 11.3: Installation of Triple Drop Epoxy Pavement Markings in New York Division
    • Letting Date: 04/13/2011
    • Completion Date: 10/05/2011
    • Construction Amount: $397,454.89
    • Contract Number: TANY 11-30/D214079
    • Contractor: Safety Marketing, Inc.
    • View Project on Map
  • MP 145.41 to MP 161.0: Installation of Triple Drop Epoxy Pavement Markings in Albany Division
    • Letting Date: 04/13/2011
    • Completion Date: 09/26/2011
    • Construction Amount: $197,264.24
    • Contract Number: TAA 11-31/D214080
    • Contractor: Straight Line Industries, Inc.
    • View Project on Map
  • MP 268.0 to 279.3: Installation of Triple Drop Epoxy Pavement Markings in Syracuse Division
    • Letting Date: 04/20/2011
    • Completion Date: 07/12/2011
    • Construction Amount: $332,331.00
    • Contract Number: TAS 11-32/D214081
    • Contractor: Straight Line Industries, Inc.
    • View Project on Map
  • MP 350.6 to 362.0 and MP 416.0 to 419.4: Installation of Triple Drop Epoxy Pavement Markings in Buffalo Division
    • Letting Date: 04/20/2011
    • Completion Date: 08/28/2011
    • Construction Amount: $395,401.40
    • Contract Number: TAB 11-33/D214082
    • Contractor: Accent Stripe, Inc.
  • Emergency Slope Repairs - MP 83.0 to MP 83.1(SB) and MP 83.1 to MP 83.3 (NB) (Tropical Storm Recovery)
    • Letting Date: 10/12/2011
    • Completion Date: 12/09/2011
    • Construction Amount: $360,472.41
    • Contract Number: TAA 11-52/D214125
    • Contractor: Callanan Industries, Inc.
    • View Project on Map
  • Little Falls (Exit 29A, MP 210.3) to Herkimer (Exit 30, MP 220.0): Pavement Resurfacing with Safety Upgrades
    • Letting Date: 08/08/2007
    • Completion Date: 10/08/2008
    • Construction Amount: $7,653,088.38
    • Contract Number: TAS 07-28/D213694
    • Contractor: Hanson Aggregates New York, Inc.
    • View Project on Map
  • South of Catskill (MP 109.3) to South of Coxsackie (MP 121.2): Pavement Resurfacing and Safety Upgrades with Coxsackie Plaza (Exit 21B, MP 124.5) and Saugerties (Exit 20E, MP 101.25) Ramp Repairs
    • Letting Date: 09/07/2005
    • Completion Date: 11/10/2006
    • Construction Amount: $7,420,859.19
    • Contract Number: TAA 05-10/D213251
    • Contractor: Callanan Industries, Inc.
    • View Project on Map
  • East of Westmoreland (MP 240.9) to Canastota (Exit 34, MP 262.6): Safety Upgrades
    • Letting Date: 08/24/2005
    • Completion Date: 08/18/2006
    • Construction Amount: $2,490,106.04
    • Contract Number: TAS 05-15/D213412
    • Contractor: Slate Hill Constructors, Inc.
    • View Project on Map
  • MP 432.45: Blasdell (Exit 56) Interchange Rehabilitation with E-ZPass Improvements and Replacement of the Ramp Bridge over Thruway
    • Letting Date: 06/07/2006
    • Completion Date: 09/24/2007
    • Construction Amount: $8,276,518.90
    • Contract Number: TAB 06-29/D213590
    • Contractor: UCC Constructors, Inc.
    • View Project on Map
  • I-190 Thruway (MP N5.62 - MP N6.6): Drainage Improvements near Porter Ave/Peace Bridge and MP N8.0: Black Rock Toll Barrier Plaza Resurfacing
    • Letting Date: 07/12/2006
    • Completion Date: 09/27/2007
    • Construction Amount: $1,791,077.38
    • Contract Number: TAN 06-20/D213552
    • Contractor: Strock Contracting, Inc.
    • View Project on Map
  • Herkimer (Exit 30, MP 219.70) to Utica Area (MP 233.50): Pavement Resurfacing and Safety Upgrades including Schuyler Service Area Ramps
    • Letting Date: 07/19/2006
    • Completion Date: 11/15/2007
    • Construction Amount: $8,858,918.53
    • Contract Number: TAS 06-42/D213631
    • Contractor: Hanson Aggregates New York, Inc.
    • View Project on Map
  • LeRoy (Exit 47, MP 378.56): Ramps Pavement Rehabilitation and a Higher Speed E-ZPass Lane
    • Letting Date: 01/09/2008
    • Completion Date: 10/14/2008
    • Construction Amount: $1,812,859.59
    • Contract Number: TAB 07-60/D213751
    • Contractor: Villager Construction, Inc.
  • Garden State Parkway Connector (MP GS0.00 - MP GS2.40): Pavement Resurfacing and Safety Upgrades
    • Letting Date: 11/25/2009
    • Completion Date: 09/29/2010
    • Construction Amount: $4,136,246.01
    • Contract Number: TAGS 09-39/D213821
    • Contractor: Tilcon New York, Inc.
    • View Project on Map
  • Berkshire Thruway, I-90 (MP BS5.70) to Canaan Toll Barrier (MP BS17.80): Pavement Resurfacing with Safety Upgrades
    • Letting Date: 10/18/2006
    • Completion Date: 09/21/2007
    • Construction Amount: $7,728,731.56
    • Contract Number: TABS 06-45/D213634
    • Contractor: Callanan Industries, Inc.
    • View Project on Map
  • Sloatsburg Service Area (MP 33.2): Pavement Resurfacing and Parking Garage Repairs
    • Letting Date: 12/02/2009
    • Completion Date: 09/23/2011
    • Construction Amount: $5,331,084.56
    • Contract Number: TANY 09-52B/D213857
    • Contractor: Sun Up Enterprises, Inc.
    • View Project on Map
  • Rotterdam (Exit 26, MP 163.3) to East of Amsterdam (MP 170.0): Pavement Resurfacing (including Pattersonville Service Area Ramps) and Safety Upgrades
    • Letting Date: 08/31/2005
    • Completion Date: 08/09/2006
    • Construction Amount: $3,417,221.60
    • Contract Number: TAA 05-5/D213504
    • Contractor: Callanan Industries, Inc.
    • View Project on Map
  • Hamburg (Exit 57, MP 436.22): Ramp and Toll Plaza Pavement Rehabilitation
    • Letting Date: 01/06/2010
    • Completion Date: 07/15/2010
    • Construction Amount: $737,859.03
    • Contract Number: TAB 10-6/D213929
    • Contractor: Oakgrove Construction, Inc.
    • View Project on Map
  • Hamburg (Exit 57, MP 438.5) to East of Silver Creek (MP 451.5): Pavement Rehabilitation, 4 Bridge Rehabilitations and Painting of 4 Bridges
    • Letting Date: 04/28/2010
    • Completion Date: 12/14/2012
    • Construction Amount: $89,320,562.65
    • Contract Number: TAB 10-8/D213939
    • Contractor: Union Concrete and Construction Corporation
    • View Project on Map
  • West of Westfield (MP 485.6) to Pennsylvania State Line (MP 496.0): Westbound Pavement Resurfacing with Safety Upgrades
    • Letting Date: 11/02/2005
    • Completion Date: 12/21/2006
    • Construction Amount: $4,716,715.00
    • Contract Number: TAB 05-23/D213529
    • Contractor: UCC Constructors, Inc.
    • View Project on Map
  • East of Westfield (MP 483.0) to Pennsylvania State Line (MP 496.0) Eastbound: Pavement Rehabilitation of the Mainline, Westfield (Exit 60) and Shortman Road (Exit 61) Interchange Ramps and Rehabilitation of the Westfield Interchange Bridge
    • Letting Date: 07/14/2010
    • Completion Date: 11/11/2011
    • Construction Amount: $17,419,167.40
    • Contract Number: TAB 10-15/D213951
    • Contractor: Oakgrove Construction, Inc.
    • View Project on Map
  • I-95 (New England Thruway) Pelham Parkway (Exit 8A, MP NE0.0) to New Rochelle Barrier (MP NE6.8): Concrete Pavement Repairs, Rehabilitation of 3 Bridges and 2 traffic count stations
    • Letting Date: 06/07/2006
    • Completion Date: 01/21/2009
    • Construction Amount: $26,804,387.30
    • Contract Number: TANE 06-21/D213514
    • Contractor: Ecco III Enterprises, Inc.
    • View Project on Map
  • South of Route 17S/I-287S (MP 28.4) to North of Sloatsburg Service Area (MP 39.8): Pavement Resurfacing and Safety Upgrades, and MP 38.60/38.61: Thruway Bridges over Seven Lakes Drive - Replace Joints
    • Letting Date: 07/26/2006
    • Completion Date: 09/27/2007
    • Construction Amount: $12,644,918.53
    • Contract Number: TANY 06-43/D213632
    • Contractor: Tilcon New York, Inc.
    • View Project on Map
  • East of Amsterdam (MP 170.0) to East of Fultonville (MP 180.0): Pavement Resurfacing including Mohawk Service Area
    • Letting Date: 07/19/2006
    • Completion Date: 12/04/2006
    • Construction Amount: $4,426,483.84
    • Contract Number: TAA 06-41/D213630
    • Contractor: Lancaster Development, Inc.
    • View Project on Map
  • Waterloo (Exit 41, MP 320.7) to Geneva (Exit 42, MP 327.5): Pavement Resurfacing
    • Letting Date: 06/20/2007
    • Completion Date: 06/09/2008
    • Construction Amount: $4,221,050.42
    • Contract Number: TAS 07-37/D213709
    • Contractor: Green Island Contracting, LLC
    • View Project on Map
  • Waterloo (Exit 41, MP 320.7) to Geneva (Exit 42, MP 327.5): Safety Upgrades
    • Letting Date: 09/24/2008
    • Completion Date: 09/03/2009
    • Construction Amount: $1,189,080.20
    • Contract Number: TAS 08-23/D213781
    • Contractor: Villager Construction, Inc.
    • View Project on Map
  • Utica (MP 233.5) to East of Westmoreland (MP 240.9): Pavement Resurfacing and Safety Upgrades
    • Letting Date: 10/25/2006
    • Completion Date: 11/19/2007
    • Construction Amount: $6,216,382.12
    • Contract Number: TAS 06-38/D213584
    • Contractor: Hanson Aggregates New York, Inc.
    • View Project on Map
  • Canastota (Exit 34, MP 262.0) to East of I-481 (MP 268.0): Pavement Rehabilitation
    • Letting Date: 11/01/2006
    • Completion Date: 09/04/2008
    • Construction Amount: $15,269,941.54
    • Contract Number: TAS 06-31/D213597
    • Contractor: Barrett Paving Materials, Inc.
    • View Project on Map
  • I-690 (Exit 39, MP 289.3) to Weedsport (Exit 40, MP 304.5): Pavement Reconstruction, Safety, Drainage and Miscellaneous Work including 4 Bridges
    • Letting Date: 08/20/2008
    • Completion Date: 08/31/2012
    • Construction Amount: $131,378,684.65
    • Contract Number: TAS 08-1/D213738
    • Contractor: Cold Spring Construction Company
    • View Project on Map
  • Lackawanna Toll Barrier (MP 430.6) to West of Hamburg (MP 438.5): Pavement Resurfacing and Safety Upgrades
    • Letting Date: 11/30/2005
    • Completion Date: 11/22/2006
    • Construction Amount: $5,989,817.54
    • Contract Number: TAB 05-27/D213477
    • Contractor: UCC Constructors, Inc.
    • View Project on Map
  • West of Hamburg (MP 438.0) to West of Angola (MP 451.0) and Silver Creek (Exit 58, MP 455.2) to Dunkirk (Exit 59, MP 467.0): Pavement Resurfacing
    • Letting Date: 06/28/2006
    • Completion Date: 11/16/2007
    • Construction Amount: $16,690,857.86
    • Contract Number: TAB 06-19/D213571
    • Contractor: Oakgrove Construction, Inc.
    • View Project on Map
  • Newburgh (Exit 17, MP 60.10) to North of Kingston (MP 93.8): Pavement Resurfacing with Selective Full Depth Repairs
    • Letting Date: 02/22/2006
    • Completion Date: 11/22/2006
    • Construction Amount: $4,941,731.34
    • Contract Number: TAA 06-3/D213437
    • Contractor: Callanan Industries, Inc.
    • View Project on Map
  • New Paltz (Exit 18, MP 76.5) to North of Kingston (MP 93.8): Safety Upgrades
    • Letting Date: 08/13/2008
    • Completion Date: 09/23/2009
    • Construction Amount: $2,952,936.03
    • Contract Number: TAA 08-13/D213747
    • Contractor: Callanan Industries, Inc
    • View Project on Map
  • North of New Paltz (MP 81.23) to North of Kingston (MP 97.2): Culvert Rehabilitation and Miscellaneous Drainage Improvements
    • Letting Date: 12/23/2009
    • Completion Date: 09/03/2010
    • Construction Amount: $1,793,675.58
    • Contract Number: TAA 09-57/D213922
    • Contractor: Argenio Brothers, Inc.
    • View Project on Map
  • West of Weedsport (MP 313.75) to Waterloo (Exit 41, MP 320.7): Pavement Resurfacing and Installation of Median Guiderail (MP 316 to MP 320)
    • Letting Date: 04/21/2010
    • Completion Date: 12/17/2010
    • Construction Amount: $5,973,887.71
    • Contract Number: TAS 10-17/D213860
    • Contractor: Hanson Aggregates New York, LLC
    • View Project on Map
  • Electronics Parkway (Exit 37, MP 284.1) to I-690 (Exit 39, MP 289.3): Pavement Resurfacing
    • Letting Date: 07/20/2011
    • Completion Date: 11/20/2012
    • Construction Amount: $7,630,225.86
    • Contract Number: TAS 11-46/D214106
    • Contractor: Villager Construction, Inc.
    • View Project on Map
  • North of Suffern (MP 32.42) Northbound: Rock Slope Stabilization and North of Nyack (MP 18.3) Southbound: Soil Slope Repair
    • Letting Date: 01/17/2007
    • Completion Date: 11/16/2007
    • Construction Amount: $2,391,796.48
    • Contract Number: TANY 07-1/D213278
    • Contractor: Ben Ciccone, Inc.
    • View Project on Map
  • West of Canajoharie (MP 200.6) to Utica (Exit 31, MP 232.0): Culvert Repairs and Construct Access Roads; and MP 177.70 Westbound Culvert: Repair of Collapsed Outlet and Headwall
    • Letting Date: 08/24/2005
    • Completion Date: 10/29/2007
    • Construction Amount: $4,229,489.05
    • Contract Number: TAS 05-8/D213370
    • Contractor: Delaney Construction Corporation
    • View Project on Map
  • West of Little Falls (MP 212.5 to MP 213.1) Westbound: Stabilization of Rock Slopes
    • Letting Date: 02/22/2006
    • Completion Date: 11/30/2006
    • Construction Amount: $3,262,880.47
    • Contract Number: TAS 06-16/D213354
    • Contractor: Rifenburg Construction, Inc.
    • View Project on Map
  • Major Deegan Expressway (MP 0.01) to Cross Westchester Expressway (Exit 8, MP 11.3): Pavement Resurfacing and Safety Upgrades
    • Letting Date: 10/01/2008
    • Completion Date: 04/12/2010
    • Construction Amount: $14,264,520.36
    • Contract Number: TANY 08-40/D213797
    • Contractor: Tully Construction Co., Inc.
    • View Project on Map
  • Newburgh (Exit 17, MP 60.1) to South of New Paltz (MP 74.5): Pavement Resurfacing with Selected Full Depth Repairs
    • Letting Date: 07/09/2008
    • Completion Date: 07/23/2009
    • Construction Amount: $5,677,994.19
    • Contract Number: TANY 08-31/D213790
    • Contractor: Callanan Industries, Inc.
    • View Project on Map
  • Woodbury Toll Barrier (MP 46.0) to Newburgh (Exit 17, MP 60.5): Pavement Resurfacing
    • Letting Date: 07/25/2007
    • Completion Date: 11/19/2008
    • Construction Amount: $10,785,583.70
    • Contract Number: TANY 07-32/D213686
    • Contractor: Tilcon New York, Inc.
    • View Project on Map
  • Woodbury Barrier (MP 46.0) to Newburgh (Exit 17, MP 60.5): Safety Upgrades
    • Letting Date: 03/24/2010
    • Completion Date: 05/24/2011
    • Construction Amount: $2,604,917.54
    • Contract Number: TANY 10-18/D213941
    • Contractor: J. Fletcher Creamer & Son, Inc.
    • View Project on Map
  • West of Batavia (MP 393.7) to West of Pembroke (MP 404.7): Pavement Resurfacing
    • Letting Date: 12/23/2009
    • Completion Date: 11/19/2010
    • Construction Amount: $8,687,172.43
    • Contract Number: TAB 09-28/D213868
    • Contractor: Keeler Construction Co., Inc.
    • View Project on Map
  • Batavia (Exit 48, MP 393.70) to West of Pembroke (MP 404.70): Safety Upgrades, Installation of Median Guiderail (MP 395 to MP 405), and MP 402.90, Rehabilitation of the Thruway Bridge over Murder Creek
    • Letting Date: 05/01/2013
    • Completion Date: 11/22/2013
    • Construction Amount: $3,262,774.75
    • Contract Number: TAB 13-8/D213943
    • Contractor: Cold Spring Construction
    • View Project on Map
  • Williams Street (Exit 52A, MP 424.92): Ramp Widening
    • Letting Date: 05/31/2006
    • Completion Date: 12/18/2006
    • Construction Amount: $1,134,617.26
    • Contract Number: TAB 06-33/D213603
    • Contractor: Nichols Long & Moore Construction Corporation
    • View Project on Map
  • Ripley Toll Barrier (MP 494.50): Construct 2 Additional E-ZPass Lanes
    • Letting Date: 05/31/2006
    • Completion Date: 12/08/2006
    • Construction Amount: $2,189,762.82
    • Contract Number: TAB 06-28/D213591
    • Contractor: Nichols Long & Moore Construction Corporation
    • View Project on Map
  • Grand Island Bridge (Exit 18A, MP N15.0 ) to Niagara Toll Barrier (MP N20.1): Pavement Resurfacing
    • Letting Date: 09/02/2008
    • Completion Date: 10/30/2008
    • Construction Amount: $2,230,606.20
    • Contract Number: NO TA/PC63883
    • Contractor: Midland Asphalt Materials, Inc.
    • View Project on Map
  • Grand Island Bridge (Exit 18A, MP N14.99 ) to Robert Moses Parkway (Exit 21, MP N21.2): Safety and Drainage Upgrades
    • Letting Date: 12/23/2009
    • Completion Date: 11/05/2010
    • Construction Amount: $1,394,235.00
    • Contract Number: TAN 09-62/D213913
    • Contractor: Keleman-Bauer Construction Co., Inc. dba Ed Bauer Construction
    • View Project on Map
  • Lackawanna Toll Barrier (MP 430.51) Pavement Rehabilitation and MP 430.51, NYCRR/Penn RR Bridge - Joint Repairs
    • Letting Date: 06/15/2011
    • Completion Date: 12/09/2011
    • Construction Amount: $2,238,899.91
    • Contract Number: TAB 11-9/D213962
    • Contractor: Union Concrete & Construction Corporation
    • View Project on Map
  • Woodbury Toll Barrier (MP 45.03): Highway Reconstruction South of Barrier and Rehabilitation of Exit 16 Bridge for Highway Speed E-ZPass (Phase I)
    • Letting Date: 11/29/2006
    • Completion Date: 12/21/2007
    • Construction Amount: $8,803,758.34
    • Contract Number: TANY 06-56/D213647
    • Contractor: Ben Ciccone, Inc.
  • MP 45.03: Woodbury Toll Barrier - Reconstruction for Highway Speed E-ZPass (Phase II)
    • Letting Date: 12/19/2007
    • Completion Date: 08/18/2010
    • Construction Amount: $79,539,499.03
    • Contract Number: TANY 07-59/D213735
    • Contractor: Yonkers Contracting Company, Inc.
  • West of Canastota (MP 268.0) to East of Manchester (MP 337.0): Pavement Resurfacing with Full Depth Repairs and Drainage Improvements
    • Letting Date: 05/03/2006
    • Completion Date: 05/29/2007
    • Construction Amount: $4,399,549.38
    • Contract Number: TAS 06-2/D213551
    • Contractor: Barrett Paving Materials, Inc.
  • MP 96.00: Ulster Service Area - Commercial Truck Parking Expansion
    • Letting Date: 09/05/2007
    • Completion Date: 07/15/2008
    • Construction Amount: $1,709,551.42
    • Contract Number: TAA 07-44/D213510
    • Contractor: Callanan Industries, Inc.
  • Guilderland and Pattersonville Service Areas: Commercial Truck Parking Resurfacing and Expansion, and Mohawk Service Area Truck Parking Resurfacing
    • Letting Date: 09/01/2010
    • Completion Date: 01/13/2012
    • Construction Amount: $4,298,332.35
    • Contract Number: TAA 10-28/D213972
    • Contractor: Callanan Industries, Inc.
  • MP 412.00: Clarence Service Area - Commercial Truck Parking Expansion
    • Letting Date: 03/28/2007
    • Completion Date: 11/30/2007
    • Construction Amount: $1,331,081.28
    • Contract Number: TAB 07-2/D213511
    • Contractor: UCC Constructors, Inc.
  • MP 103.00: Malden Service Area - Commercial Truck Parking Expansion
    • Letting Date: 07/21/2010
    • Completion Date: 05/17/2011
    • Construction Amount: $1,595,343.58
    • Contract Number: TAA 10-27/D213971
    • Contractor: Rifenburg Construction, Inc.
  • Watertown/Binghamton I-81 (Exit 36, MP 282.93): Toll Plaza Resurfacing
    • Letting Date: 04/29/2009
    • Completion Date: 11/07/2009
    • Construction Amount: $654,466.36
    • Contract Number: TAS 09-33/D213842
    • Contractor: CCI Companies, Inc.
    • View Project on Map
  • MP 141.92: Thruway Headquarters and 337 Southern Boulevard Buildings - Resurface Driveways and Parking Lots
    • Letting Date: 05/26/2010
    • Completion Date: 10/21/2010
    • Construction Amount: $1,167,194.02
    • Contract Number: TAA 10-16/D213957
    • Contractor: Carver Construction, Inc.
    • View Project on Map
  • New York Division: Pavement Striping - 2008
    • Letting Date: 11/07/2007
    • Completion Date: 11/04/2008
    • Construction Amount: $739,121.72
    • Contract Number: TANY 07-46/D213727
    • Contractor: Safety Marking, Inc.
  • Albany Division: Pavement Striping - 2008
    • Letting Date: 11/07/2007
    • Completion Date: 07/02/2008
    • Construction Amount: $606,033.23
    • Contract Number: TAA 07-47/D213728
    • Contractor: Straight Line Industries, Inc.
  • Syracuse Division: Pavement Striping - 2008
    • Letting Date: 11/28/2007
    • Completion Date: 07/23/2008
    • Construction Amount: $493,153.47
    • Contract Number: TAS 07-48/D213729
    • Contractor: Accent Stripe, Inc.
  • Buffalo Division: Pavement Striping - 2008
    • Letting Date: 11/28/2007
    • Completion Date: 11/07/2008
    • Construction Amount: $720,515.54
    • Contract Number: TAB 07-49/D213730
    • Contractor: Accent Stripe, Inc.
  • New York Division: Pavement Striping - 2009
    • Letting Date: 11/26/2008
    • Completion Date: 08/17/2009
    • Construction Amount: $488,834.69
    • Contract Number: TANY 08-50/D213828
    • Contractor: Safety Marking, Inc.
  • Albany Division: Pavement Striping - 2009
    • Letting Date: 11/12/2008
    • Completion Date: 08/25/2009
    • Construction Amount: $730,129.85
    • Contract Number: TAA 08-46/D213813
    • Contractor: Straight Line Industries, Inc.
  • Syracuse Division: Pavement Striping - 2009
    • Letting Date: 12/03/2008
    • Completion Date: 07/29/2009
    • Construction Amount: $358,236.73
    • Contract Number: TAS 08-47/D213815
    • Contractor: Straight Line Industries, Inc.
  • Buffalo Division: Pavement Striping - 2009
    • Letting Date: 12/03/2008
    • Completion Date: 09/03/2009
    • Construction Amount: $625,625.00
    • Contract Number: TAB 08-51/D213831
    • Contractor: Accent Stripe, Inc.
  • New York Division: Pavement Striping - 2010
    • Letting Date: 11/04/2009
    • Completion Date: 07/26/2010
    • Construction Amount: $623,021.12
    • Contract Number: TANY 09-43/D213899
    • Contractor: Safety Marketing, Inc.
  • Albany Division: Pavement Striping - 2010
    • Letting Date: 10/21/2009
    • Completion Date: 07/22/2010
    • Construction Amount: $339,871.91
    • Contract Number: TAA 09-44/D213900
    • Contractor: Straight Line Industries, Inc.
  • Syracuse Division: Pavement Striping - 2010
    • Letting Date: 10/21/2009
    • Completion Date: 07/28/2010
    • Construction Amount: $451,726.79
    • Contract Number: TAS 09-45/D213901
    • Contractor: Straight Line Industries, Inc.
  • Buffalo Division: Pavement Striping - 2010
    • Letting Date: 10/28/2009
    • Completion Date: 07/20/2010
    • Construction Amount: $787,927.71
    • Contract Number: TAB 09-46/D213902
    • Contractor: Accent Stripe, Inc.
  • Construct Noise Wall Barriers near Lackawanna Toll Barrier (MP 430.51 - MP 431.22) and South Ogden St. (Exit N1, MP N0.71 - MP N0.85)
    • Letting Date: 08/25/2010
    • Completion Date: 11/18/2011
    • Construction Amount: $2,968,480.91
    • Contract Number: TAB 10-41/D213993
    • Contractor: Keeler Construction Co., Inc.
    • View Project on Map
  • Syracuse Division: On-Demand Pavement Repairs - 2005
    • Letting Date: 07/06/2005
    • Completion Date: 11/18/2005
    • Construction Amount: $1,296,242.57
    • Contract Number: TAS 05-09/D213478
    • Contractor: Green Island Contracting, LLC
  • Buffalo Division: On-Demand Pavement Repairs - 2005
    • Letting Date: 07/06/2005
    • Completion Date: 06/08/2006
    • Construction Amount: $2,543,962.80
    • Contract Number: TAB 05-6/D213476
    • Contractor: UCC Constructors, Inc.
    • View Project on Map
  • Albany Division: On-Demand Pavement Repairs - 2006
    • Letting Date: 05/31/2006
    • Completion Date: 12/01/2006
    • Construction Amount: $1,927,845.42
    • Contract Number: TAA 06-8R/D213508
    • Contractor: Callanan Industries, Inc.
  • Buffalo Division: On Demand Pavement Repairs - 2006
    • Letting Date: 03/15/2006
    • Completion Date: 08/16/2006
    • Construction Amount: $2,302,099.17
    • Contract Number: TAB 06-10/D213557
    • Contractor: Oakgrove Construction, Inc.
  • Syracuse Division: Mill and Inlay with Selective Full Depth Repairs at Various Locations
    • Letting Date: 03/14/2007
    • Completion Date: 07/26/2007
    • Construction Amount: $1,815,315.66
    • Contract Number: TAS 07-16/D213658
    • Contractor: Villager Construction, Inc.
  • Buffalo Division: On-Demand Pavement Repairs - 2007
    • Letting Date: 02/21/2007
    • Completion Date: 06/13/2007
    • Construction Amount: $2,368,593.22
    • Contract Number: TAB 07-5/D213661
    • Contractor: Keeler Construction Co., Inc.
  • Syracuse Division: Highway Resurfacing at Various Locations
    • Letting Date: 06/04/2008
    • Completion Date: 11/07/2008
    • Construction Amount: $1,411,898.70
    • Contract Number: TAS 08-25/D213783
    • Contractor: Dolomite Products Company, Inc. dba Ulster Paving Company
  • Buffalo Division: Highway Resurfacing at Various Locations
    • Letting Date: 06/04/2008
    • Completion Date: 11/21/2008
    • Construction Amount: $4,847,229.38
    • Contract Number: TAB 08-10/D213759
    • Contractor: Oakgrove Construction, Inc.
  • North of Coxsackie (MP 129.1): Rock Removal
    • Letting Date: 11/01/2006
    • Completion Date: 08/07/2007
    • Construction Amount: $1,477,938.11
    • Contract Number: TAA 06-44/D213592
    • Contractor: Rifenburg Construction, Inc.
    • View Project on Map
  • Berkshire Thruway, Canaan Toll Barrier (MP BS17.6) to Massachusetts State Line (MP BS24.3): Pavement Resurfacing and Safety Upgrades
    • Letting Date: 04/07/2010
    • Completion Date: 11/19/2010
    • Construction Amount: $4,827,204.72
    • Contract Number: TABS 10-13/D213948
    • Contractor: Callanan Industries, Inc.
    • View Project on Map
  • New York Division: Pavement Striping - 2011
    • Letting Date: 11/10/2010
    • Completion Date: 09/10/2011
    • Construction Amount: $429,717.33
    • Contract Number: TANY 10-42/D213995
    • Contractor: Safety Marketing, Inc.
  • Albany Division: Pavement Striping - 2011
    • Letting Date: 11/10/2010
    • Completion Date: 07/21/2011
    • Construction Amount: $399,314.71
    • Contract Number: TAA 10-43/D213996
    • Contractor: Straight Line Industries, Inc.
  • Syracuse Division: Pavement Striping - 2011
    • Letting Date: 11/24/2010
    • Completion Date: 07/22/2011
    • Construction Amount: $474,233.92
    • Contract Number: TAS 10-44/D213997
    • Contractor: Accent Stripe, Inc.
  • Buffalo Division: Pavement Striping - 2011
    • Letting Date: 12/01/2010
    • Completion Date: 07/21/2011
    • Construction Amount: $748,817.10
    • Contract Number: TAB 10-45/D213998
    • Contractor: Accent Stripe, Inc.
  • Thompson Road (Exit 35, MP 279.3) to Liverpool/Electronics Parkway(Exit 37, MP 284.1): Pavement Resurfacing including Interchange Ramps
    • Letting Date: 11/25/2009
    • Completion Date: 05/18/2011
    • Construction Amount: $4,831,447.31
    • Contract Number: TAS 09-25/D213864
    • Contractor: Barrett Paving Materials, Inc.
    • View Project on Map
  • I-190 (Niagara Section), Ontario Street (Exit 14, MP N10.0) to River Road/Route 266 (Exit 17, MP N14.11): Concrete Pavement Repairs, Painting of Two Bridges (MP N11.55 and MP N13.54) and Substructure Repairs to the MP N11.55 Bridge
    • Letting Date: 06/29/2011
    • Completion Date: 09/26/2012
    • Construction Amount: $5,591,429.29
    • Contract Number: TAN 11-17/D214052
    • Contractor: Oakgrove Construction
    • View Project on Map
  • Albany Division: Installation of Median Guiderail
    • Letting Date: 08/09/2006
    • Completion Date: 12/15/2006
    • Construction Amount: $1,084,644.99
    • Contract Number: TAA 06-46/D213635
    • Contractor: Elderlee, Inc.
  • Removal of the Buffalo City Line (MP N0.53 NB) and Black Rock (MP N8.00 SB) Toll Barriers
    • Letting Date: 04/25/2007
    • Completion Date: 09/28/2007
    • Construction Amount: $795,345.33
    • Contract Number: TAN 07-27/D213690
    • Contractor: Oakgrove Construction, Inc.
  • MP 76.3: Expansion of the New Paltz (Exit 18) Park and Ride Lot
    • Letting Date: 09/12/2007
    • Completion Date: 12/07/2007
    • Construction Amount: $328,163.07
    • Contract Number: TANY 07-43/D213721
    • Contractor: Merritt Construction, Inc.
    • View Project on Map
  • West of Canajoharie (MP 199.9) to Little Falls (Exit 29A, MP 209.50) and Two Locations on the Berkshire Thruway: Installation of Median Guiderail
    • Letting Date: 05/13/2009
    • Completion Date: 09/11/2009
    • Construction Amount: $571,329.46
    • Contract Number: TAA 09-23/D213862
    • Contractor: Elderlee, Inc.
  • West of Little Falls (MP 212.6 to MP 213.1 Eastbound): Rock Slope Remediation
    • Letting Date: 10/07/2009
    • Completion Date: 11/30/2011
    • Construction Amount: $3,434,106.37
    • Contract Number: TAS 09-35/D213855
    • Contractor: Rifenburg Construction, Inc.
    • View Project on Map
  • Albany Division: Culvert Cleaning
    • Letting Date: 09/08/2010
    • Completion Date: 12/15/2010
    • Construction Amount: $66,462.25
    • Contract Number: TAA 10-38/D213989
    • Contractor: Precision Industrial Maintenance, Inc.
  • Syracuse Division Culverts: Remove Sediment, Restore Capacity and Inspect for Needed Repairs
    • Letting Date: 10/17/2012
    • Completion Date: 09/20/2013
    • Construction Amount: $398,846.00
    • Contract Number: TAS 11-29R/D214064
    • Contractor: Custom Crews, Inc.
  • Buffalo Division Culverts: Remove Sediment, Restore Capacity and Inspect for Needed Repairs
    • Letting Date: 05/15/2013
    • Completion Date: 10/10/2013
    • Construction Amount: $211,669.85
    • Contract Number: TAB 13-4/D214142
    • Contractor: Union Concrete & Construction Corporation
  • East of Amsterdam (MP 170.0) to East of Fultonville (MP 180.0): Safety Upgrades
    • Letting Date: 10/22/2008
    • Completion Date: 09/25/2009
    • Construction Amount: $1,934,853.03
    • Contract Number: TAA 08-20/D213755
    • Contractor: Callanan Industries, Inc.
    • View Project on Map
  • MP 202.45 to MP 202.65 WB: Slope Stabilization and Miscellaneous Work
    • Letting Date: 05/23/2012
    • Completion Date: 11/12/2012
    • Construction Amount: $577,912.86
    • Contract Number: TAS 12-20/D214151
    • Contractor: Ketco, Inc.
    • View Project on Map
  • Williamsville Toll Barrier (MP 419.4) to West of William Street (MP 425.9) and I-190 (Niagara Section), North of Church Street (MP N5.5) to Peace Bridge (Exit 9, MP N6.6): Pavement Resurfacing and Installation of Median and Ramp Gates
    • Letting Date: 06/08/2011
    • Completion Date: 12/03/2012
    • Construction Amount: $13,000,602.44
    • Contract Number: TAB 11-39/D214090
    • Contractor: Oakgrove Construction, Inc.
    • View Project on Map
  • Yonkers (MP 5.5) and New Rochelle (MP NE6.9) Toll Barriers: Installation of Treadles, Sensors and Complete Toll Plaza Modifications
    • Letting Date: 05/14/2008
    • Completion Date: 09/29/2008
    • Construction Amount: $182,692.23
    • Contract Number: TANY 08-28/D213787
    • Contractor: Power Line Constructors, Inc.
  • Williamsville (MP 419.7) and Lackawanna (MP 430.5) Toll Barriers: Installation of Treadles and Complete Toll Plaza Modifications
    • Letting Date: 08/06/2008
    • Completion Date: 11/14/2008
    • Construction Amount: $156,332.15
    • Contract Number: TAB 08-34/D213793
    • Contractor: Nichols Long & Moore Construction Corporation
  • East of Westfield (MP 483.0) to Penn. State Line (MP 496.0) Eastbound: Pavement Resurfacing, Driving Lane Only (Excluding the Ripley Toll Plaza)
    • Letting Date: 07/02/2008
    • Completion Date: 10/06/2008
    • Construction Amount: $1,128,885.01
    • Contract Number: TAB 08-39/D213796
    • Contractor: UCC Contractors, Inc.
    • View Project on Map
  • Newburgh (Exit 17, MP 60.2) to South of New Paltz (MP 68.0): Pavement Rehabilitation; South of New Paltz (MP 74.5) to New Paltz (Exit 18, MP 76.5): Safety Upgrades Only; MP 65.51: Thruway Bridge over Mill Street - Rehabilitation and MP 72.77: Thruway Bridge over Abandoned Rail Road - Removal
    • Letting Date: 06/01/2011
    • Completion Date: 04/12/2013
    • Construction Amount: $37,756,925.72
    • Contract Number: TANY 11-15/D214021
    • Contractor: A. Colarusso & Son, Inc.
    • View Project on Map
  • New York Division: Pavement Safety Striping - 2012
    • Letting Date: 11/23/2011
    • Completion Date: 07/19/2012
    • Construction Amount: $662,466.34
    • Contract Number: TANY 11-40/D214092
    • Contractor: Safety Marketing, Inc.
  • Albany Division: Pavement Safety Striping - 2012
    • Letting Date: 11/23/2011
    • Completion Date: 08/15/2012
    • Construction Amount: $441,392.79
    • Contract Number: TAA 11-41/D214093
    • Contractor: Straight Line Industries, Inc.
  • Syracuse Division: Pavement Safety Striping - 2012
    • Letting Date: 11/30/2011
    • Completion Date: 06/22/2012
    • Construction Amount: $717,598.14
    • Contract Number: TAS 11-42/D214094
    • Contractor: Accent Stripe, Inc.
  • West of Rotterdam (MP 164.9 to MP 165.1) Eastbound: Slope Stabilization
    • Letting Date: 06/17/2009
    • Completion Date: 10/16/2009
    • Construction Amount: $464,013.60
    • Contract Number: TAA 09-34/D213852
    • Contractor: KETCO, Inc.
    • View Project on Map
  • West Seneca (Exit 54, MP 427.7) to Lackawanna Barrier (MP 430.4): Pavement Resurfacing
    • Letting Date: 07/29/2009
    • Completion Date: 06/30/2010
    • Construction Amount: $1,988,780.36
    • Contract Number: TAB 09-26/D213866
    • Contractor: UCC Contructors, Inc.
    • View Project on Map
  • New York Division: Pavement Safety Striping - 2013
    • Letting Date: 12/12/2012
    • Completion Date: 08/12/2013
    • Construction Amount: $414,442.87
    • Contract Number: TANY 12-28/D214170
    • Contractor: Safety Marketing, Inc.
  • Albany Division: Pavement Safety Striping - 2013
    • Letting Date: 12/12/2012
    • Completion Date: 07/16/2013
    • Construction Amount: $171,876.15
    • Contract Number: TAA 12-29/D214171
    • Contractor: Straight Line Industries, Inc.
  • Syracuse Division: Pavement Safety Striping - 2013
    • Letting Date: 01/16/2013
    • Completion Date: 06/21/2013
    • Construction Amount: $685,083.43
    • Contract Number: TAS 12-30/D214172
    • Contractor: Accent Stripe, Inc.
  • Buffalo Division: Pavement Safety Striping - 2013
    • Letting Date: 01/16/2013
    • Completion Date: 07/12/2013
    • Construction Amount: $861,325.60
    • Contract Number: TAB 12-31/D214173
    • Contractor: Accent Stripe, Inc.
  • Buffalo Division: Pavement Safety Striping - 2012
    • Letting Date: 11/30/2011
    • Completion Date: 08/31/2012
    • Construction Amount: $810,469.13
    • Contract Number: TAB 11-43/D214095
    • Contractor: Accent Stripe, Inc.
  • I-787 (Exit 23, MP 141.9) to Northway (Exit 24, MP 148.15): Pavement Reconstruction with Congestion Relief and Painting of 3 Bridges
    • Letting Date: 11/17/2010
    • Completion Date: 12/16/2013
    • Construction Amount: $99,671,115.00
    • Contract Number: TAA 10-36/D213986
    • Contractor: Rifenburg Construction, Inc.
    • View Project on Map
  • East of Fultonville (MP 180.0) to West of Canajoharie (MP 197.9): Pavement Resurfacing
    • Letting Date: 04/21/2010
    • Completion Date: 12/17/2010
    • Construction Amount: $8,833,701.20
    • Contract Number: TAA 10-5/D213917
    • Contractor: Hanson Aggregates New York, LLC
    • View Project on Map
  • East of Fultonville (MP 180.0) to West of Canajoharie (MP 197.9): Safety Upgrades, Drainage Improvements and Misc. Work
    • Letting Date: 07/07/2010
    • Completion Date: 11/29/2011
    • Construction Amount: $2,421,579.50
    • Contract Number: TAA 10-33/D213983
    • Contractor: Callanan Industries, Inc.
    • View Project on Map
  • Saugerties (Exit 20, MP 100.8) to South of Catskill (MP 109.3): Safety Upgrades
    • Letting Date: 01/21/2009
    • Completion Date: 11/06/2009
    • Construction Amount: $1,924,250.06
    • Contract Number: TAA 08-24/D213763
    • Contractor: Callanan Industries, Inc.
    • View Project on Map
  • Saugerties (Exit 20, MP 100.8) to South of Catskill (MP 109.3): Pavement Resurfacing
    • Letting Date: 06/05/2008
    • Completion Date: 07/02/2008
    • Construction Amount: $1,461,376.94
    • Contract Number: NO TA/31509
    • Contractor: Midland Asphalt Materials, Inc.
    • View Project on Map
  • Geneva (Exit 42, MP 327.58) to Canandaigua (Exit 44, MP 347.10): Pavement Resurfacing and Safety Upgrades
    • Letting Date: 12/16/2009
    • Completion Date: 08/18/2011
    • Construction Amount: $14,973,227.66
    • Contract Number: TAS 09-22/D213861
    • Contractor: Villager Construction, Inc.
    • View Project on Map
  • Schenectady (Exit 25, MP 146.0) to I-88 (Exit 25A, MP 163.3): Pavement Resurfacing and Safety Upgrades
    • Letting Date: 05/09/2007
    • Completion Date: 11/28/2007
    • Construction Amount: $9,065,613.44
    • Contract Number: TAA 07-13/D213672
    • Contractor: Callanan Industries, Inc.
    • View Project on Map
  • Depew (Exit 49, MP 416.9) to Williamsville Toll Barrier (MP 419.6): Pavement Resurfacing and MP 407.0 to MP 415.5 - Installation of Median Guiderail
    • Letting Date: 05/27/2009
    • Completion Date: 11/10/2009
    • Construction Amount: $3,528,975.09
    • Contract Number: TAB 09-8/D213846
    • Contractor: Oakgrove Construction, Inc.
    • View Project on Map
  • North of New Paltz (MP 86.8) to North of Kingston (MP 93.8): Pavement Resurfacing and Safety Upgrades
    • Letting Date: 10/20/2010
    • Completion Date: 12/14/2011
    • Construction Amount: $4,023,104.22
    • Contract Number: TAA 10-47/D213975
    • Contractor: Callanan Industries, Inc.
    • View Project on Map
  • Kingston (Exit 19, MP 93.8) to Saugerties (Exit 20, MP 100.8): Pavement Resurfacing and Safety Upgrades, with Drainage Improvements at MP 99.0
    • Letting Date: 04/21/2010
    • Completion Date: 11/24/2010
    • Construction Amount: $4,646,146.88
    • Contract Number: TAA 10-3/D213914
    • Contractor: Callanan Industries, Inc.
    • View Project on Map
  • South of Coxsackie (MP 121.2) to I-787 (Exit 23, MP 141.3) and Northway (Exit 24, MP 148.1) to West of Schenectady (MP 154.4): Pavement Resurfacing
    • Letting Date: 07/21/2010
    • Completion Date: 04/27/2012
    • Construction Amount: $12,592,290.22
    • Contract Number: TAA 10-37/D213981
    • Contractor: Kubricky Construction Corp.
    • View Project on Map
  • South of Coxsackie (MP 121.2) to I-787 (Exit 23, MP 141.3) and Northway (Exit 24, MP 148.1) to West of Schenectady (MP 154.4): Safety Upgrades and Thruway over Coeymans Creek Bridge (MP 131.90) - Mill and Overlay Deck
    • Letting Date: 06/22/2011
    • Completion Date: 07/20/2012
    • Construction Amount: $3,038,885.28
    • Contract Number: TAA 11-23/D214033
    • Contractor: Callanan Industries, Inc.
    • View Project on Map
  • 10 Miles west of E. Syracuse (Exit 35) and I-690 Syracuse (Exit 39): Installation of Two Variable Message Signs
    • Letting Date: 11/16/2005
    • Completion Date: 12/28/2006
    • Construction Amount: $838,288.77
    • Contract Number: TAS 05-4I/D213492
    • Contractor: Planert Utility, Inc.
  • Buffalo Division ITS Phase 3: Installation of Fiber Opic Cable, TRANSMIT, Closed Circuit TV Cameras and Dynamic Message Signs
    • Letting Date: 03/08/2006
    • Completion Date: 03/11/2009
    • Construction Amount: $7,704,953.59
    • Contract Number: TAB 06-22I/D213505
    • Contractor: Power Line Constructors, Inc
  • Syracuse Division - Installation of ITS Equipment
    • Letting Date: 10/15/2008
    • Completion Date: 12/18/2009
    • Construction Amount: $2,268,099.41
    • Contract Number: TAS 08-32I/D213772
    • Contractor: Power Line Constructors, Inc.
  • MP 22.80: Spring Valley Toll Barrier Northbound - Commercial Vehicle Highway Speed E-ZPass
    • Letting Date: 02/22/2006
    • Completion Date: 09/22/2006
    • Construction Amount: $1,486,802.29
    • Contract Number: TANY 06-17/D213570
    • Contractor: Imperial Iron Works / Rhombus, JV
  • Installation of ITS Equipment in New York Division
    • Letting Date: 09/22/2010
    • Completion Date: 11/16/2012
    • Construction Amount: $8,606,399.30
    • Contract Number: TANY 10-34I/D213736
    • Contractor: Power Line Constructors
  • Albany Division - Installation of ITS Equipment
    • Letting Date: 09/29/2010
    • Completion Date: 03/13/2012
    • Construction Amount: $2,406,373.49
    • Contract Number: TAA 10-35I/D213969
    • Contractor: Power & Construction Group, Inc.
  • Installation of Fiber Optic Line along I-190 and 2 Dynamic Message Signs, 16 TRANSMIT and 15 Closed Circut TV Cameras along I-90 and I-190
    • Letting Date: 11/12/2008
    • Completion Date: 07/27/2011
    • Construction Amount: $10,005,320.65
    • Contract Number: TAB 08-29I/D213789
    • Contractor: Concrete Applied Technologies Corporation
  • Syracuse Division: Installation of ITS Equipment - 20 Closed Circuit TV Cameras, 17 TRANSMIT and 9 Dynamic Message Signs
    • Letting Date: 07/28/2010
    • Completion Date: 03/28/2012
    • Construction Amount: $4,284,552.97
    • Contract Number: TAS 10-31I/D213968
    • Contractor: Power Line Constructors, Inc.
  • Lockport: Lock E-34 & E-35 - Install Vehicular Barrier Railing, Niagara County
    • Letting Date: 07/27/2005
    • Completion Date: 09/07/2006
    • Construction Amount: $561,677.18
    • Contract Number: TAB 05-3C/D213436
    • Contractor: Oakgrove Construction, Inc.
  • Canastota to Erie Canal Village: Canalway Trail, Madison/Oneida Counties
    • Letting Date: 08/05/2009
    • Completion Date: 11/12/2010
    • Construction Amount: $2,081,010.59
    • Contract Number: TAS 09-38C/D213415
    • Contractor: Dolomite Products, Inc./dba Ulster Paving Company
  • Lyons: Abbey Park to Route 14: Canalway Trail, Wayne County
    • Letting Date: 08/29/2012
    • Completion Date: 11/05/2013
    • Construction Amount: $547,818.40
    • Contract Number: TAS 12-23C/D214164
    • Contractor: Keeler Construction Co., Inc.
  • Little Falls: Railroad Ave to Route 167: Canalway Trail, Herkimer County
    • Letting Date: 08/15/2012
    • Completion Date: 10/14/2013
    • Construction Amount: $861,646.00
    • Contract Number: TAS 12-24C/D214165
    • Contractor: ALX Hunter Excavation, Inc.
  • Jordan to Port Byron: Canalway Trail, Cayuga/Onondaga Counties
    • Letting Date: 01/25/2006
    • Completion Date: 10/30/2007
    • Construction Amount: $1,349,078.38
    • Contract Number: TAS 05-39C/D213553
    • Contractor: Vector Construction Corporation
  • Schenectady: Canalway Trail, Schenectady County
    • Letting Date: 08/12/2009
    • Completion Date: 11/30/2010
    • Construction Amount: $1,042,795.07
    • Contract Number: TAA 09-30C/D213785
    • Contractor: Carver Construction, Inc.

Go to Top | Bottom

Google Translate Disclaimer