Scheduled Construction Lane Closures For The Week Starting Monday 08/30/2010 Erie Region
Mainline I-90
| Between Exits |
Work Description |
Lane Closure Information |
Likely Impacts |
Comments |
| 55 & 57 | Conduit Work | West Left lane, Monday 8/30/10 7pm -through- 6am Tuesday 8/31/10.
| Minimal | None |
| 56 & 55 | Bridge Work | West Right lane,
Wednesday 9/1/10 9:00am - 2:00pm.
East Right lane, Wednesday 9/1/10 9:00am - 2:00pm.
| Minor | None |
| 57 & 55 | Conduit Work | East Left lane,
Tuesday 8/31/10 7pm -through- 6am Wednesday 9/1/10.
| Minimal | None |
| 57 & 56 | Bridge Work | East Right lane,
Monday 9:00am - 2:00pm.
| Minor | None |
| 57 & 56 | Other Long Range: Permit number T4W100043 | West Left lane,
Tuesday 8/31/10 6pm -through- 6am Wednesday 9/1/10.
Wednesday 9/1/10 6pm -through- 6am Thursday 9/2/10.
East Left lane,
Monday 8/30/10 6pm -through-6am Tuesday 8/31/10.
| Minimal | None |
| 57 & 57A | Road Work | West Right lane,
Monday 8/30/10 6:00am - 10:00am.
Tuesday 8/31/10 6:00am - 3:00pm.
Wednesday 9/1/10 6:00am - 11:00am.
Thursday 9/2/10 6:00am - 10:00am.
| Minimal | None |
| 58 & 57A | Road Work | West Left lane,
Monday 8/30/10 6:00am - 11:00am
Monday 8:30 1pm - through- 12noon Thursday 9/2/10.
East Left lane,
Monday 8/30/10 6:00am - 3:00pm.
Monday 8/30/10 5pm -through- 12noon
Thursday 9/2/10.
| Minimal | None |
Impact Key
| Impact |
Description | | None | None |
| Minimal | Traffic moving at posted speed |
| Minor | Traffic delayed up to 5 minutes more than normal time |
| Moderate | Traffic delayed from 5 to 20 minutes more than normal time |
| Severe | Traffic delayed 20 minutes or more over normal time |
|