Scheduled Construction Lane Closures

For The Week Starting Monday 08/30/2010
Erie Region

Mainline I-90
Between Exits Work Description Lane Closure Information Likely Impacts Comments
55 & 57  Conduit Work  West Left lane,
Monday 8/30/10 7pm -through- 6am Tuesday 8/31/10.

 
Minimal  None 
56 & 55  Bridge Work  West Right lane,
Wednesday 9/1/10 9:00am - 2:00pm.

East Right lane,
Wednesday 9/1/10 9:00am - 2:00pm.

 
Minor  None 
57 & 55  Conduit Work  East Left lane,
Tuesday 8/31/10 7pm -through- 6am Wednesday 9/1/10.

 
Minimal  None 
57 & 56  Bridge Work  East Right lane,
Monday 9:00am - 2:00pm.

 
Minor  None 
57 & 56  Other
Long Range: Permit number T4W100043 
West Left lane,
Tuesday 8/31/10 6pm -through- 6am Wednesday 9/1/10. Wednesday 9/1/10 6pm -through- 6am Thursday 9/2/10.

East Left lane,
Monday 8/30/10 6pm -through-6am Tuesday 8/31/10.

 
Minimal  None 
57 & 57A  Road Work  West Right lane,
Monday 8/30/10 6:00am - 10:00am. Tuesday 8/31/10 6:00am - 3:00pm. Wednesday 9/1/10 6:00am - 11:00am. Thursday 9/2/10 6:00am - 10:00am.

 
Minimal  None 
58 & 57A  Road Work  West Left lane,
Monday 8/30/10 6:00am - 11:00am Monday 8:30 1pm - through- 12noon Thursday 9/2/10.

East Left lane,
Monday 8/30/10 6:00am - 3:00pm. Monday 8/30/10 5pm -through- 12noon Thursday 9/2/10.

 
Minimal  None 

 
Impact Key
Impact Description
None None
Minimal Traffic moving at posted speed
Minor Traffic delayed up to 5 minutes more than normal time
Moderate Traffic delayed from 5 to 20 minutes more than normal time
Severe Traffic delayed 20 minutes or more over normal time