Scheduled Construction Lane Closures For The Week Starting Monday 08/30/2010 Utica Region
Mainline I-90
| Between Exits |
Work Description |
Lane Closure Information |
Likely Impacts |
Comments |
| 27 & 29 | Bridge Work | West Left lane, Wed., 7:00AM - 5:00PM; Thurs., 7:00AM - 12:00NOON
Weather Permitting
| Minimal | Ramp Closed |
| 28 & 27 | Paving | East Alternating right lane with the left lane, Wed., 6:00AM - 6:00PM
| Minimal | * Conditional to Traffic Back-ups |
| 29 & 27 | Bridge Work | East Left lane, Wed., 7:00AM - 5:00PM; Thurs., 7:00AM - 12:00NOON;
Weather Permitting
| Minimal | Ramp Closed |
| 28 & 29 | Paving | East Alternating right lane with the left lane, Tues., 6:00AM - 6:00PM
West Left lane, Mon., 6:00AM - 6:00PM; (*Conditional to Traffic Back-ups, 11:00AM - 4:00PM)
West Left lane, Tues., 6:00AM - 6:00PM
West Left lane, Wed., 6:00AM - 6:00PM; (*Conditional to Traffic Back-ups from 1:00PM - 4:00PM)
| Minimal | * Conditional to Traffic Back-ups |
| 29A & 28 | Paving | West Left lane, Tues., 6:00AM - 6:00PM; Mobile Striping Operations
West Alternating right lane with the left lane, Wed., 6:00AM - 6:00PM; Mobile Striping Operations
East Alternating right lane with the left lane, Wed., 6:00AM - 6:00PM; Mobile Striping Operations
East Right lane, Mon., 6:00AM - 6:00PM; Mobile Striping Operations
(*Conditional to Traffic Back-ups, 10:00AM - 6:00PM)
| Minimal | * Conditional to Traffic Back-ups |
| 30 & 29A | Rock Blasting | East Right lane, Blasting for this project will take place once a day between 10 a.m. and 2 p.m. Monday through Thursday. This schedule will take place through the end of August 2010.
| Moderate | None |
Impact Key
| Impact |
Description | | None | None |
| Minimal | Traffic moving at posted speed |
| Minor | Traffic delayed up to 5 minutes more than normal time |
| Moderate | Traffic delayed from 5 to 20 minutes more than normal time |
| Severe | Traffic delayed 20 minutes or more over normal time |
|